GC3, L.L.C. v. Empowerment Temple, Inc.

2024 Ohio 5509
Ohio Court of Appeals·Decided November 22, 2024·No. 30197·Published

Opinion

IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT MONTGOMERY COUNTY

GC3 LLC :

:

Appellees : C.A. No. 30197 :

v. : Trial Court Case No. 2020 CV03040 :

EMPOWERMENT TEMPLE INC., ET : (Civil Appeal from Common Pleas AL. : Court)

:

Appellant :

...........

OPINION

Rendered on November 22, 2024 ...........

JONATHAN HOLLINGSWORTH, Attorney for Appellant ANDREW M. HANNA, Attorney for Appellee .............

TUCKER, J.

{¶ 1} Empowerment Temple, Inc. appeals from the trial court’s entry of summary judgment against it on its slander-of-title counterclaim against appellee GC3, LLC.

Empowerment Temple filed the counterclaim in response to GC3’s placing a mechanic’s lien on Empowerment Temple’s property and seeking foreclosure on the lien.

{¶ 2} Empowerment Temple contends the trial court misapplied summary-

judgment standards by misallocating the burden of proof. Empowerment Temple also asserts that genuine issues of material fact exist as to whether GC3 reasonably believed it had a valid contractual claim against Empowerment Temple when placing a mechanic’s lien on Empowerment Temple’s property or, later, when an arbitrator ruled against GC3 on the contractual claim and the trial court confirmed the arbitrator’s decision. Finally, Empowerment Temple contends the trial court erred in finding that GC3 reasonably waited until April 2023 to release the mechanic’s lien, which had been recorded in January 2020.

{¶ 3} We conclude that our de novo review renders harmless any error by the trial court in allocating the applicable summary-judgment burdens. Construing the evidence in a light most favorable to Empowerment Temple, we believe reasonable minds could disagree about whether GC3 acted with reckless disregard as to the invalidity of its mechanic’s lien, either when it filed the lien or at various points in time thereafter, and long before releasing the lien. Accordingly, the trial court’s entry of summary judgment in favor of GC3 on Empowerment Temple’s slander-of-title counterclaim will be reversed, and the case will be remanded for further proceedings.

I. Background

{¶ 4} Empowerment Temple hired GC3 to repair tornado damage to its buildings.

The parties executed a June 2019 construction-services contract memorializing their

agreement. GC3 subsequently performed some work for which Empowerment Temple refused to pay. As a result, GC3 initiated arbitration against Empowerment Temple for breach of contract. It also recorded a mechanic’s lien against Empowerment Temple’s property in January 2020. GC3 then filed the present action in the trial court seeking to foreclose on the mechanic’s lien. In response, Empowerment Temple filed a slander-of- title counterclaim alleging that GC3’s lien was baseless. The trial court stayed litigation while the arbitration proceeded.

{¶ 5} In January 2022, the arbitrator issued a final decision denying GC3’s contractual claim. Although the parties had entered into a written agreement, the arbitrator found that key terms were undefined. The “scope of work” to be performed by GC3 was identified only as the “scope of loss” by Empowerment Temple. The agreement stated that the “scope of loss” would be determined by the insurance carrier, and GC3’s “work” would be limited to that “scope of loss” unless GC3 and Empowerment Temple agreed otherwise in writing. The agreement recognized that the “scope of work” was still “being developed.” It provided that the “scope of work” would be made part of the agreement through a “change order” when completed. Finally, the agreement provided that the “contract price” would be whatever the insurance company agreed to pay plus any additional work required or authorized by Empowerment Temple.

{¶ 6} The arbitrator determined that the “scope of work” to be performed never was defined and made part of the agreement through a required change order. The arbitrator also found no agreed price. Therefore, the arbitrator found GC3 entitled to no compensation under the agreement. Although GC3 had performed “significant

preparatory work,” the arbitrator saw no evidence that Empowerment Temple “was clearly aware of the work” or that Empowerment Temple had “obtained direct benefits from it.” The arbitrator reasoned that “[s]ometimes in litigation, money for work cannot be awarded—not because no work was performed, but because any calculation of such damages is contrary to the terms of a contract that allocated risk.” The arbitrator found that “GC3 failed to complete a key term in a contract that it drafted.” The arbitrator concluded that “GC3 proceeded to do significant work under a contract before it had the documentation required under the express terms of a contract that it drafted; so accordingly, the risk, not-unfairly, falls to GC3.” Later in its decision, the arbitrator reasoned that “GC3 proceeded with work on a contract before the price was determined according to the Contract’s express terms, meaning it cannot get a fee for work that was not yet approved under the Contract’s terms.”

{¶ 7} Following the arbitrator’s ruling, Empowerment Temple sought summary judgment on GC3’s lien-foreclosure cause of action and on the liability portion of its own slander-of-title counterclaim. Before addressing summary judgment, the trial court confirmed the arbitrator’s decision in May 2022. Thereafter, in February 2023, the trial court entered summary judgment for Empowerment Temple on GC3’s lien-foreclosure claim. In light of the arbitrator’s decision, the trial court found no debt owed to GC3 by Empowerment Temple under the contract. Without a valid underlying debt, the trial court found nothing for GC3 to secure and no basis for a mechanic’s lien.

{¶ 8} With regard to Empowerment Temple’s counterclaim for slander of title, the trial court opined that genuine issues of material fact precluded summary judgment for

Empowerment Temple. On that issue, the trial court reasoned:

Here, reasonable minds could conclude that GC3 operated under a good faith belief that it had a legitimate claim to payment/compensation for work it performed pursuant to the Contract. The Arbitrator ultimately concluded that an award of damages was not appropriate, not because no work was performed, but because any calculation of such damages would be contrary to the terms of the contract that allocated risk. The Arbitrator determined that GC3 failed to complete a key term in the contract that it drafted and proceeded to do significant work under a contract before it had the documentation required under the express terms of the contract that it drafted. The Arbitrator also concluded that no equitable or other justifiable basis to award damages existed, explaining that “there is no evidence that Empowerment was clearly aware of the work or that it obtained direct benefits from it.” As a result, this Court cannot conclude that the third element of malice or reckless disregard is satisfied in this instance.

However, while it is true that GC3 previously acted with the reasonable belief that it had a meritorious claim for money due under the contract for work performed, this belief is arguably no longer reasonable in light of the Arbitrator’s decision and this Court’s confirmation of the arbitration award.

Therefore, at this time, this Court must conclude that genuine issues of material fact exist with respect to Empowerment’s claim for slander of title.

(Citations omitted.) February 8, 2023 Decision, Order, and Entry at 9-10.

{¶ 9} In response to the trial court’s summary-judgment ruling, GC3 filed a lien release on March 3, 2023. That filing was ineffective, however, as it was done in Cuyahoga County. GC3 subsequently filed an effective lien release in Montgomery County on April 12, 2023. Thereafter, in July and August 2023, the parties filed additional briefing on Empowerment Temple’s slander-of-title counterclaim. After giving notice to the parties and without objection, the trial court construed the briefs as cross-motions for summary judgment on the counterclaim.

Free access — add to your briefcase to read the full text and ask questions with AI

GC3, L.L.C. v. Empowerment Temple, Inc., 2024 Ohio 5509 (Ohio Ct. App. 2024).

2024 Ohio 5509 (GC3, L.L.C. v. Empowerment Temple, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Elmer J. Benes v. United States
276 F.2d 99 (Sixth Circuit, 1960)
Mann v. Resolution T Co., L.L.C.
2014 Ohio 2451 (Ohio Court of Appeals, 2014)
Mann v. Resolution T Co., L.L.C.
2015 Ohio 3266 (Ohio Court of Appeals, 2015)
Staffilino Chevrolet, Inc. v. Balk
814 N.E.2d 940 (Ohio Court of Appeals, 2004)
Horton v. City of Dayton
558 N.E.2d 79 (Ohio Court of Appeals, 1988)
Green v. Lemarr
744 N.E.2d 212 (Ohio Court of Appeals, 2000)
Prater v. Dashkovsky, 07ap-389 (12-18-2007)
2007 Ohio 6785 (Ohio Court of Appeals, 2007)
Rhododendron Holdings, L.L.C. v. Harris
2021 Ohio 147 (Ohio Court of Appeals, 2021)
McAlpine v. McCloud
2021 Ohio 2430 (Ohio Court of Appeals, 2021)
Zara Constr., Inc. v. Belcastro
2022 Ohio 788 (Ohio Court of Appeals, 2022)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
Meyer v. Lucas
2024 Ohio 3035 (Ohio Court of Appeals, 2024)