IPS Elec, Servs., L.L.C. v. Univ. of Toledo

2016 Ohio 361
CourtOhio Court of Appeals
DecidedFebruary 2, 2016
Docket15AP-207
StatusPublished
Cited by2 cases

This text of 2016 Ohio 361 (IPS Elec, Servs., L.L.C. v. Univ. of Toledo) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
IPS Elec, Servs., L.L.C. v. Univ. of Toledo, 2016 Ohio 361 (Ohio Ct. App. 2016).

Opinion

[Cite as IPS Elec, Servs., L.L.C. v. Univ. of Toledo, 2016-Ohio-361.] IN THE COURT OF APPEALS OF OHIO

TENTH APPELLATE DISTRICT

IPS Electric Services, LLC, :

Plaintiff-Appellant/ : No. 15AP-207 Cross-Appellee, (Ct. of Cl. No. 2013-00528) v. : (REGULAR CALENDAR) University of Toledo, :

Defendant-Appellee/ : Cross-Appellant.

D E C I S I O N

Rendered on February 2, 2016

Kohrman Jackson & Krantz, Luther L. Liggett, Jr., and David M. Scott, for IPS Electric Services, LLC.

Michael DeWine, Attorney General, James E. Rook, and Richard J. Silk, Jr., for University of Toledo.

APPEAL from the Court of Claims of Ohio

LUPER SCHUSTER, J. {¶ 1} Plaintiff-appellant/cross-appellee, IPS Electric Services, LLC ("IPS"), appeals from a judgment of the Court of Claims of Ohio rendered in favor of defendant- appellee/cross-appellant, University of Toledo ("UT"), on IPS's breach of contract claim against UT. For the following reasons, we affirm. I. Facts and Procedural History {¶ 2} This case arises from a construction contract dispute. On September 19, 2012, UT contracted with Henning Electrical Services, LLC ("Henning"), to perform electrical work on a public improvement project involving the construction of an enclosure connecting existing buildings at the UT Health Science Campus and the remodeling of existing building space (referred to as the "project"). The contract includes "General Conditions," addressing such issues as "Contract Modifications" (Article 7) and No. 15AP-207 2

"Dispute Resolution" (Article 8). The contract defines UT as the "owner" and Henning as the "contractor." (UT exhibit No. 1.) In October 2012, Henning changed its name to IPS. {¶ 3} Problems impacted the completion of the project. Numerous times during the project, IPS corresponded with Christopher Levicki, project manager for UT, regarding the problems. By letter dated October 24, 2012, IPS complained to UT regarding the modified scheduled completion date, and "several issues that are beyond the control of [IPS] that are adversely impacting [IPS's] progress." (IPS exhibit D.) The October 24, 2012 letter indicates that, in order for IPS to meet an accelerated completion schedule, "IPS will need to work overtime, increase crew size and work in shifts – all of which greatly impact productivity and increase costs." (IPS exhibit D.) {¶ 4} By letter dated December 24, 2012, IPS complained to UT about "scheduling and other issues" concerning the project. (IPS exhibit D, Dec. 24, 2012 letter, 1.) The December 24, 2012 letter states that IPS "committed manpower and resources to meet the revised January completion date, which included additional costs to account for the recognized acceleration." (IPS exhibit D, Dec. 24, 2012 letter, 1.) The December 24, 2012 letter identifies numerous problems caused by UT, which impacted IPS's work, including the late delivery of the air handling units and slow responses to requests for information, resulting in the delay of overhead duct work and installation of wall studs. Generally, the December 24, 2012 letter indicates IPS's position that UT should compensate IPS for costs associated with the acceleration of the completion schedule and delays. {¶ 5} On January 22, 2013, IPS sent a letter to UT indicating it had "previously provided to [UT] written notices of impacts and claims with respect to this matter. We are arguably obligated under the contract documents to provide additional support for our claims as a follow-up to our prior submissions." (IPS exhibit D.) IPS stated its "unanticipated labor cost associated with schedule compression from 8/12/12 to 10/28/12 is $50,000" due to an accelerated completion date of January 2, 2013. (IPS exhibit D.) IPS also stated that, with a project completion date of March 15, 2013, the "cost associated with the disruptions to our performance as we described in our earlier correspondence is $110,000." (IPS exhibit D.) IPS further stated the "missed dry-in date" and delays in No. 15AP-207 3

moving the temporary patient corridors had resulted in $20,000 of additional "general conditions costs" to IPS. (IPS exhibit D.) {¶ 6} On February 21, 2013, IPS sent a letter to UT containing "back-up information as a detailed justification to that January 22, 2013 letter * * * which [IPS] listed $160,000 of unanticipated labor costs." (IPS exhibit D.) IPS attached an addendum to the February 21, 2013 letter, detailing the additional costs as reflected in man-hours that IPS was incurring due to the accelerated calendar and delays in various areas of the project. IPS also attached proposed "Change Orders" to the February 21, 2013 letter "for these additional costs" associated with "schedule changes, delays in start of scheduled work, lack of schedule coordination, impacted worker productivity and acceleration of schedule." (IPS exhibit D.) {¶ 7} On April 25, 2013, IPS submitted its "Certified Claim" to UT "[p]ursuant to Article 8 of the Contract General Conditions" and "for the cumulative impact of the University of Toledo and its agents for the work that IPS performed" on the project. (IPS exhibit D.) The letter states "IPS gave notice of delay and potential costs impacts in its October 24, 2012, December 24, 2012, January 22, 2013 and February 21, 2013 letters." (IPS exhibit D.) IPS identified three categories of cost impact: 1) $50,000 claim for schedule compression * * * [as] documented in our February 21, 2013 letter, the areas where work was affected occurred in Area A between September 9, 2012 and November 11, 2012.

***

2) $210,000 for disruptions of performance * * * [as] documented in our February 21, 2013 letter, the areas where work was affected occurred in Areas A, B, C (Pharmacy) and the Mall for the periods of time noted in the Addendum to that letter. Since the date of the letter, there has been an additional identifiable damage totally [sic] an approximate $100,000.

3) $20,000 for additional General Conditions * * * [as documented in IPS's] letters of notice to the University of Toledo as Project Owner on October 24, 2012, December 24, 2012, January 22, 2013 and February 21, 2013 and in this No. 15AP-207 4

certified claims letter. There is an additional claim for General Conditions because we are now substantially complete and can fully quantify the GCs. The total amount of General Conditions owed is $70,898.29.

(Emphasis deleted.) (IPS exhibit D.) The "Certified Claim" letter includes the following certification of IPS's senior project manager, Tim Rauch: The undersigned Contractor certifies that the claim is made in good faith; that the supporting data is accurate and complete to the best of the Contractor's knowledge and belief; that the amount requested is a fair, reasonable, and necessary adjustment for which the Contractor believes the State is liable; and that the undersigned is duly authorized to certify the claim on behalf of the Contractor.

(IPS exhibit D.) {¶ 8} In September 2013, IPS initiated this action against UT in the Court of Claims alleging breach of contract and unjust enrichment. The case proceeded to trial on both causes of action in December 2014. The parties filed post-trial briefs, and IPS filed a motion for leave to amend the pleadings to conform to the evidence. In March 2015, the Court of Claims issued its decision addressing the merits of IPS's claims. Based on its finding that a written contract governs the relationship between the parties, the Court of Claims dismissed IPS's unjust enrichment claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cleveland Constr., Inc. v. Ruscilli Constr. Co., Inc.
2023 Ohio 363 (Ohio Court of Appeals, 2023)
Jutte Elec., Ltd. v. Ohio Facilities Constr. Comm.
2016 Ohio 8580 (Ohio Court of Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2016 Ohio 361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ips-elec-servs-llc-v-univ-of-toledo-ohioctapp-2016.