Scandale Associated Builders & Engineers, Ltd. v. Bell Justice Facilities Corp.

455 F. Supp. 2d 271, 2006 U.S. Dist. LEXIS 73683, 2006 WL 2874326
CourtDistrict Court, M.D. Pennsylvania
DecidedOctober 11, 2006
Docket03cv1773
StatusPublished
Cited by2 cases

This text of 455 F. Supp. 2d 271 (Scandale Associated Builders & Engineers, Ltd. v. Bell Justice Facilities Corp.) is published on Counsel Stack Legal Research, covering District Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scandale Associated Builders & Engineers, Ltd. v. Bell Justice Facilities Corp., 455 F. Supp. 2d 271, 2006 U.S. Dist. LEXIS 73683, 2006 WL 2874326 (M.D. Pa. 2006).

Opinion

MEMORANDUM AND ORDER

JONES, District Judge.

THE BACKGROUND OF THIS ORDER IS AS FOLLOWS:

Two Motions are pending before this Court. First, Defendant, Bell Justice Facilities Corp. (“Defendant” or “Bell”), filed a Motion for Partial Summary Judgment (doc. 47) on March 31, 2006. Second, Plaintiff, Seandale Associated Builders & Engineers, Ltd. (“Plaintiff’ or “Seandale”), filed a Motion for Summary Judgment (doc. 49) on March 31, 2006. On May 19, 2006, both Motions were dismissed without prejudice. On August 23, 2006, this Court entered an Order enabling these Motions to be reasserted. For the reasons that follow, the Motions shall be denied.

PROCEDURAL BACKGROUND:

On or about September 10, 2003, Plaintiff filed a Complaint against Defendant in the Court of Common Pleas of Wayne County, Pennsylvania. On October 6, 2003, pursuant to 28 U.S.C. § 1446, Defendant filed a Notice of Removal with this Court. That same day, Defendant filed a Motion to Dismiss Count III of the Complaint that was granted by Order of December 5, 2003. (Rec.Doc.12). The remaining counts of Plaintiffs Complaint assert breach of contract (Count I), “unresolved additional direct cost issues” and delay and impact costs (Count II), and interest and penalties purportedly due under the Pennsylvania Contractors and Subcontractors Payment Act (Count IV).

Defendant did not file an Answer to Plaintiffs Complaint or raise any affirmative defenses. The time for filing or amending pleadings expired May 31, 2004. Discovery proceeded and closed. On March 31, 2006, Plaintiff and Defendant filed respective Motions for Summary Judgment that were briefed by the parties.

On April 24, 2006, Defendant filed a Motion for Leave to File an Answer, which was granted by Order of May 19, 2006. (Rec.Doc.63). That Order also reopened discovery for a period of sixty (60) days and dismissed the Motions for Summary Judgment without prejudice. On May 31, 2006, Defendant filed an Answer. (Rec. Doc.65). Subsequently, the period of discovery closed.

On August 23, 2006, this Court entered an Order allowing the previously filed and briefed Motions for Summary Judgment to be reasserted. (Rec.Doc.71). The Motions are therefore ripe for disposition.

STANDARD OF REVIEW:

Summary judgment is appropriate if “there is no genuine issue as to any material fact and ... the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c); see also Turner v. Schering-Plough Corp., 901 F.2d 335, 340 (3d Cir.1990). The party moving for summary judgment bears the burden of showing “there is no genuine issue for trial.” Young v. Quinlan, 960 F.2d 351, 357 (3d Cir.1992). Summary judgment should not be granted when there is a disagreement about the facts or the proper inferences that a fact finder could draw from them. See Peterson v. Lehigh Valley Dist. Council, 676 F.2d 81, 84 (3d Cir.1982).

Initially, the moving party has a burden of demonstrating the absence of a genuine issue of material fact. See Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). This may be met by the moving party pointing out to the court that there is an absence of evidence to support an essential element as to which the non-moving party will bear the burden *273 of proof at trial. See id. at 325, 106 S.Ct. 2548.

Rule 56 provides that, where such a motion is made and properly supported, the non-moving party must then show by affidavits, pleadings, depositions, answers to interrogatories, and admissions on file, that there is a genuine issue for trial. See Fed.R.Civ.P. 56(e). The United States Supreme Court has commented that this requirement is tantamount to the non-moving party making a sufficient showing as to the essential elements of their case that a reasonable jury could find in its favor. See Celotex, 477 U.S. at 322-23, 106 S.Ct. 2548 (1986).

It is important to note that “the non-moving party cannot rely upon conclusory allegations in its pleadings or in memoranda and briefs to establish a genuine issue of material fact.” Pastore v. Bell Tel. Co. of Pa., 24 F.3d 508, 511 (3d Cir.1994) (citation omitted). However, all inferences “should be drawn in the light most favorable to the non-moving party, and where the non-moving party’s evidence contradicts the movant’s, then the non-movant’s must be taken as true.” Big Apple BMW, Inc. v. BMW of North America, Inc., 974 F.2d 1358, 1363 (3d Cir.1992) (citations omitted).

Still, “the mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). “As to materiality, the substantive law will identify which facts are material.” Id. at 248, 106 S.Ct. 2505. A dispute is considered to be genuine only if “the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Id.

STATEMENT OF RELEVANT FACTS:

The facts in this matter are largely disputed by the parties. We are presented with detailed disputed factual summaries and extensive discovery material. We will not attempt to conduct a piecemeal examination of each fact presented by the parties, but will discuss the relevant factual background necessary to resolve the pending Motions. We will, where necessary, view the facts and all inferences to be drawn therefrom in the light most favorable to the non-moving party in our analysis of the pending Motions.

Bell was the general contractor on a project for the construction of the United States Penitentiary/Federal Prison Camp at Canaan, Pennsylvania (“Project”). (Rec. Docs. 48-3, ¶ 3; 54, ¶ 3). The owner of the Project is the United States Department of Justice/Federal Bureau of Prisons (“FBOP”). (Rec. Docs. 48-3, ¶ 3; 54, ¶ 3). On or about January 4, 2001, Scandale and Bell entered into a fixed-price written subcontract agreement (the “Subcontract”) pursuant to which Scandale agreed to perform concrete work on Bell’s Project. (Rec.Doc.1-3, Ex. A, ¶ 1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clipper Pipe & Service, Inc. v. Ohio Casualty Insurance
115 A.3d 1278 (Supreme Court of Pennsylvania, 2015)
Mastercraft Woodworking Co. v. Jim Lagana Plumbing & Heating Inc.
9 Pa. D. & C.5th 251 (Berks County Court of Common Pleas, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
455 F. Supp. 2d 271, 2006 U.S. Dist. LEXIS 73683, 2006 WL 2874326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scandale-associated-builders-engineers-ltd-v-bell-justice-facilities-pamd-2006.