Grimme Combustion, Inc. v. Mergentime Corp.

595 A.2d 77, 406 Pa. Super. 620, 1991 Pa. Super. LEXIS 1819
CourtSuperior Court of Pennsylvania
DecidedJuly 2, 1991
Docket02170
StatusPublished
Cited by36 cases

This text of 595 A.2d 77 (Grimme Combustion, Inc. v. Mergentime Corp.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grimme Combustion, Inc. v. Mergentime Corp., 595 A.2d 77, 406 Pa. Super. 620, 1991 Pa. Super. LEXIS 1819 (Pa. Ct. App. 1991).

Opinions

MONTGOMERY, Judge:

The plaintiff-appellant Grimme Combustion, Inc. instituted the instant action to seek damages allegedly arising out of its work as a subcontractor on a highway construction project in Philadelphia. Defendant-appellee Mergentime Corporation was the general contractor on that Pennsylvania Department of Transportation (hereinafter “PennDOT”) project, and defendant-appellee Insurance Company of North America (hereinafter “INA”) acted as a surety in providing a payment bond for Mergentime with regard to the project. After the close of the pleadings, the defendants filed a motion to dismiss for lack of subject matter jurisdiction and for failure to join an indispensable party. The plaintiff filed a response in opposition to the motion, and the defendants filed a reply memorandum. After consideration, the trial court entered an order granting the defense motion to dismiss. It did so based upon its conclusion that PennDOT was an indispensable party in the litigation. The plaintiff thereafter instituted the instant appeal.

In the absence of an indispensable party, a court lacks jurisdiction over matters before it. Columbia Gas Transmission Corp. v. Diamond Fuel Co., 464 Pa. 377, 379, 346 A.2d 788, 789 (1975). A trial court order dismissing an action because a plaintiff fails to join an indispensable party is a final and appealable order, as it puts the [624]*624parties out of court without reaching the merits of the action. Damico v. Royal Insurance Company, 383 Pa.Super. 239, 556 A.2d 886 (1989). In our review of a trial court order dismissing an action on such a basis, we must take as true all well-pleaded facts revealed in the complaint and exhibits properly attached thereto. Witmer v. Exxon Corporation, 260 Pa.Super. 537, 394 A.2d 1276 (1978), affirmed 495 Pa. 540, 434 A.2d 1222 (1981); Com. ex rel. Shumaker v. New York & Pennsylvania Co., Inc., 367 Pa. 40, 79 A.2d 439 (1951). It is evident that on this appeal we must carefully review the plaintiffs pleadings as well as any appropriate exhibits.

Plaintiff’s complaint included five counts. Count I asserted that in January 1985, Mergentime entered into a contract with PennDOT for the improvement of a certain section of a state highway in the City of Philadelphia known as the Schuylkill Expressway. In conjunction therewith, INA provided a payment bond on behalf of Mergentime. In February 1985, Mergentime entered into a written subcontract with plaintiff Grimme, pursuant to which Grimme agreed to perform work known as pressure mortar surfacing for the substructure on specific portions of the project. Subsequently, Mergentime and Grimme agreed to expand the subcontract to include repair work on deteriorated concrete at certain locations on the job. Grimme claimed it had completed all of its work under the subcontract as of November 1986. Further, the plaintiff alleged that as of January 1987, it had submitted and defendant Mergentime had approved invoices totalling $272,392.35, of which Mergentime had paid $224,761.79, leaving the sum of $47,630.56 due and owing. In addition, Grimme asserted that defendant Mergentime had agreed, under the subcontract, to pay Grimme a ten percent increase in unit prices for all work performed after May 1, 1986, and that by virtue thereof, Mergentime allegedly owed Grimme an additional $17,-736.64. Based upon these allegations, the plaintiff maintained that it was owed a total of $65,367.20, for which both Mergentime, as principal, and INA, as surety, were jointly [625]*625and severally liable. In addition, the plaintiff sought additional interest, costs and attorney fees.

Count II of the complaint repeated all of the foregoing assertions of fact, and also alleged that Mergentime was obligated to assure that Grimme’s work would be coordinated with other work on the project to assure that Grimme could perform its work while various ramps were closed to traffic, and so that Grimme could perform its work from staging areas contiguous with the actual work sites. Grimme asserted that Mergentime had failed in such coordination obligations, such that Grimme was forced to perform its work when the ramps were not closed to traffic, and further, was required to work from staging areas far removed from the sites of its construction responsibilities. The plaintiff also contended that compounding the fact that it was forced to work from remote staging areas was the fact that PennDOT noted additional repairs to be performed, which were not included as part of Grimme’s original subcontract.

The plaintiff detailed the alleged damages which resulted from each incident of alleged failure in coordination responsibilities by Mergentime. Thus, the plaintiff asserted a claim for $264,188.68 for cost overruns on one area of ramp repairs denoted as the South Street ramps, and $46,075.88 for cost overruns on a second area of ramp repairs, designated as the University Avenue ramps. With respect to this ramp work, the plaintiff’s claims were based upon the contention that Mergentime coordination failures caused it to work from and move to remote staging or mobilization areas. The balance of the Count II claims, relating to so-called Mainline repairs, allegedly resulted from a combination of the Expressway being open to traffic during the time of the repairs, the requirement that Grimme work from an excessively distant staging area, an excessive number of unanticipated repairs which had to be made, and extra work assigned to Grimme as a result of requests by PennDOT for a significant number of unexpected repairs. The plaintiff contended it experienced out-of-pocket ex[626]*626penses for some of this Mainline work amounting to $161,-714.78, and costs, overhead and profits in the amount of $193,985.42 for other work. In addition, the plaintiff claimed a total of $176,250.00 for lost profits and other problems relating to all three portions of the project.

In Count III, the plaintiff reasserted the allegations set forth in Count I of the complaint. However, in Count III, Grimme only sought a judgment against Mergentime. The Count III claim was for $65,367.20, the same amount as sought in Count I.

Count IV also asserted a claim only against Mergentime. In that regard, Count IV repeated all of the claims for damages, in the same amounts, as were set forth in Count II of the complaint.

In Count V, the plaintiff alleged that by reason of all of the matters alleged in the foregoing sections of the complaint, its working capital and net worth had been impaired such that it had lost all of its bonding capacity. Accordingly, Grimme maintained that it had an inability to obtain work for which contract performance and/or payment bonds would be required. This purported lack of bonding capacity allegedly caused Grimme to suffer losses in an amount in excess of $549,675.59, and would in the future cause it to suffer additional damages. A recovery for these alleged past damages and expected future harm was sought only against Mergentime in Count V.

In addition to the counts in the complaint, it is appropriate to refer to a particular section of the Grimme-Mergentime subcontract, which was an exhibit to the complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rehab Financial Group v. Grimes, B.
Superior Court of Pennsylvania, 2025
Estate of Rocco, P., Appeal of: Passanante, P.
2025 Pa. Super. 120 (Superior Court of Pennsylvania, 2025)
Cavallo Mineral Partners v. EQT Production
Superior Court of Pennsylvania, 2025
In Re: Est. of D.A.A., Appeal of: Anderson, R.
2024 Pa. Super. 117 (Superior Court of Pennsylvania, 2024)
Washington Area Humane v. Harr, C.
Superior Court of Pennsylvania, 2022
Liberty Mutual Group v. 700 Pharmacy, LLC
2022 Pa. Super. 19 (Superior Court of Pennsylvania, 2022)
Walker, D. v. Maffeo, M.
Superior Court of Pennsylvania, 2020
Blackmon, D. v. Moore, Z.
Superior Court of Pennsylvania, 2020
Lowell Funding Group v. Moore, W.
Superior Court of Pennsylvania, 2018
Skanska USA Building v. Universal Concrete
Superior Court of Pennsylvania, 2018
Peoples Security Bank v. Fritz, R.
Superior Court of Pennsylvania, 2017
Lafferty, H. v. Ferris, T.
Superior Court of Pennsylvania, 2017
Brown, M. v. Zhang, T.
Superior Court of Pennsylvania, 2017
Shannon, L. v. Pride Health Care, Inc.
Superior Court of Pennsylvania, 2016
Northern Forests II, Inc. v. Keta Realty Co.
130 A.3d 19 (Superior Court of Pennsylvania, 2015)
Orman, L. v. Mortgage I.T.
118 A.3d 403 (Superior Court of Pennsylvania, 2015)
Herbert, A. v. Kholyavka, L.
Superior Court of Pennsylvania, 2015
Martin v. Rite Aid of Pennsylvania, Inc.
30 Pa. D. & C.5th 260 (Philadelphia County Court of Common Pleas, 2013)
Sauer Inc. v. Honeywell Building Solutions SES Corp.
742 F. Supp. 2d 709 (W.D. Pennsylvania, 2010)
LVI Environmental Services Inc. v. Duane Morris LLP
12 Pa. D. & C.5th 457 (Philadelphia County Court of Common Pleas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
595 A.2d 77, 406 Pa. Super. 620, 1991 Pa. Super. LEXIS 1819, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grimme-combustion-inc-v-mergentime-corp-pasuperct-1991.