LVI Environmental Services Inc. v. Duane Morris LLP
This text of 12 Pa. D. & C.5th 457 (LVI Environmental Services Inc. v. Duane Morris LLP) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Philadelphia County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Plaintiff LVI Environmental Services Inc. (LVI) brought this action against its former attorneys, defendant Duane Morris LLP (DM), alleging professional malpractice in connection with [459]*459DM’s representation of LVI in a lawsuit entitled LVI v. Delta/B.J.D.S. Inc. July term 2001, no. 01811 (Phila. Cty.) (the underlying action). LVI’s claim for delay damages in the underlying action was dismissed by the trial court, and DM failed timely to appeal the trial court’s ruling on that issue.
In this action, DM argues, correctly, that if the trial court’s ruling in the underlying action would have been sustained on appeal, then LVI suffered no damages as a result of DM’s malpractice. Without damages, LVI may not prevail on its claims for professional malpractice.1 In deciding the appeal, the Superior Court would have had to determine if the trial court erred as a matter of law, not of fact.2 Therefore, in deciding the case within this case, this court must determine, as a matter of law, if the trial court in the underlying action was wrong. The court cannot send this issue of law to the jury.3
The relevant facts of record in the underlying action are as follows. LVI was a sub-subcontractor on a con[460]*460structionproject at 1500 Spring Garden Street (the project). LVI entered into a contract with Delta/B J.D.S. Inc. (Delta) under which LVI was to perform certain demolition work on the project. Delta was the subcontractor responsible for asbestos removal on the project. The contract between Delta and LVI provided:
“If the subcontractor is delayed, disrupted or interfered with at any time in the commencement or progress of the work by an act or neglect of the contractor or of a separate subcontractor employed by the contractor, or by changes ordered in the work, or by fire, unavoidable casualties or any other cause wholly beyond the subcontractor ’s control, or by delay authorized by the contractor pending mediation and dispute resolution, then the agreement time shall be extended by change order for such reasonable time as the contractor may determine. No claim for delay, disruption or interference shall be allowed unless it increases the overall critical path duration of the schedule in effect at the time of the delay and unless the subcontractor has used its best efforts to offset such delay or disruption by making appropriate changes to other parts of the schedule. The subcontractor shall not be entitled under any circumstance to any adjustment in compensation or any damages or other compensation whatsoever in the event of any delay, disruption or interference in the progress of the work, regardless of the cause(s), unless owner agrees to such compensation in writing and contractor4 is not at fault, in whole or in part, for such delay, disruption or interference.”5
[461]*461By including this provision in their contract, the parties agreed that more time, rather than more money, was their preferred remedy for the delays which so often occur in construction projects.
As part of their contract, LVI and Delta agreed upon a schedule for the performance of their work under which LVI would have exclusive access to each floor to do its work before or after Delta performed its asbestos abatement work.6 The work did not proceed as planned. LVI claims that Delta fell behind schedule, and LVI was not given the exclusive access to which the parties agreed. As a result, LVI was forced to complete its work in a less efficient and more expensive manner.
In April 2001, LVI hired DM, who filed the underlying action on LVI’s behalf against Delta. In the underlying action, LVI asserted claims against Delta for breach of contract and violation of the Contractor and Subcontractor Payment Act. Delta moved for summary judgment based on the no damages for delay clause in the contract. The trial judge granted Delta’s motion and dismissed LVI’s delay damages claims.7 The parties settled the remaining claims and cross claims.
DM filed a notice of appeal of the dismissal of LVI’s approximately $1,700,000 in delay damages. The trial [462]*462judge requested a statement of issues upon which the appeal was based. DM neglected timely to serve the statement of issues on the trial judge. As a result, LVI’s appeal was quashed.
LVI filed this action against DM for legal malpractice. LVI’s expert in this action opines that the trial court’s dismissal of LVI’s delay damage claim in the underlying action would have been reversed on appeal but for DM’s malpractice in failing to serve the statement of issues on the trial judge.8 LVI’s expert claims that the facts of this case fit the exceptions to enforcement of no damages for delay clauses.
A no damages for delay clause will not be enforced, i.e., delay damages may be recovered, where the delay “was not in the class of difficulties and delays which were in the minds of the parties” when they entered into their contract.9 The type of facts that give rise to this exception are akin to those that give rise to a claim for fraud in the inducement10 or mutual mistake of fact.11 Under all three legal theories, courts will not enforce a contract, or the relevant provisions of a contract, where the material facts underlying the transaction are not as the parties believed them to be at the time of contract[463]*463ing.12 There is no claim in this case that the circumstances existing at the time LVI and Delta entered into the contract were not as LVI believed them to be. Instead, LVI’s claim is that Delta’s promised future performance did not occur in the orderly fashion that LVI anticipated.
A no damages for delay clause may also be avoided “where an owner by an unwarranted positive act interferes with the execution of the contract, or where the owner unreasonably neglects to perform an essential element of the work in furtherance thereof, to the detriment of the contractor.13 Delay occasioned by the work of other contractors on the job site is not usually sufficient to meet this standard.14
On one occasion, the Pennsylvania Supreme Court found that the interference of other contractors was such an impediment to the complaining contractor’s work that delay damages were recoverable despite the no damages for delay clause in the parties’ contract.15 However, the [464]*464holding of that case must be limited to the rather troubling facts upon which it was based. In that case, it appears the interfering contractors and the owner of the project fraudulently conspired to misuse the project’s funds, which delayed the project and the complaining contractor. 16
There is no evidence that any such grand criminal conspiracy existed with respect to the project at issue in the underlying action. Instead, the evidence showed that Delta fell behind schedule in its own work and attempted to make up the lost time by working concurrently with its subcontractor, LVI, to LVI’s apparent detriment.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
12 Pa. D. & C.5th 457, 2010 Phila. Ct. Com. Pl. LEXIS 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lvi-environmental-services-inc-v-duane-morris-llp-pactcomplphilad-2010.