Henry Shenk Co. v. Erie County

178 A. 662, 319 Pa. 100, 1935 Pa. LEXIS 646
CourtSupreme Court of Pennsylvania
DecidedMarch 26, 1935
DocketAppeal, 111
StatusPublished
Cited by46 cases

This text of 178 A. 662 (Henry Shenk Co. v. Erie County) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henry Shenk Co. v. Erie County, 178 A. 662, 319 Pa. 100, 1935 Pa. LEXIS 646 (Pa. 1935).

Opinion

Opinion bx

Mr. Justice Kephart,

The Commissioners of Erie County were directed, through proper proceedings, to remodel the old courthouse and enlarge it by adding a new wing. The general plans and specifications were approved, and, after due authorization, a contract was let October 4, 1928, for the general building and remodeling program to Henry Shenk Company for $400,000, to be completed within one year, or October 5, 1929. Shenk’s contract did not include the outside facing and fixed office equipment, nor did it include plumbing, heating, electric wiring and ventilating necessary to complete the structure.

The specifications for the stone facing was approved by the court October 18, 1928, and on November 23d a contract was awarded by the commissioners to plaintiff. The court refused to approve this contract, and formally rejected it December 28th. After repeated efforts to secure suitable materials, a new contract was awarded April 3d which was approved by the court April 15,1929.

The plans and specifications for the office equipment were approved by the court October 31,1929, but the contract for materials was rejected. A new contract was approved January 24,1930.

Plaintiff completed its construction September 15, 1930, or about a year beyond the time fixed for completion. The work was done in a satisfactory manner and it has been paid for at the contract price with the extras agreed upon. Shenk Company brought the present action to recover damages from the county because it claimed the delays incident to letting the two contracts just mentioned caused them additional unnecessary expense. The case was tried by the judge without a jury and Shenk was awarded a substantial sum, which the court in banc refused to disturb. The county takes this appeal.

While it is true that municipalities may construct and carry forward public undertakings authorized or directed by law and it has been stated that they will be *103 governed by the same rules in the interpretation and enforcement of such contracts as private citizens, and will not be permitted, at its pleasure, to violate or abandon such contracts (People v. Sohmer, 207 N. Y. 450) ; in this State we have held that where there is doubt as to the interpretation or application of the provision of a contract with public authorities “The contract will be interpreted in favor of the public”: Com. v. Nelson-Pedley Const. Co., 303 Pa. 174, 180. There are certain impediments to the contractual power of municipal officers which everyone who deals with them is bound to know and be governed by. When such officers do acts for which they as individuals may be personally liable, such acts, in determining whether liability is to be imposed on a municipality, are governed by different rules if done in furtherance of a governmental function by a government agent, or if the officer, in acting, is subservient to or controlled by a supervisory body such as a court.

In the interpretation of this contract, these principles must be kept in mind. It is not the policy of courts to countenance or encourage dishonesty or overreaching by public officers in their official conduct, more particularly where the municipality benefits from such acts, though at times it would seem that municipalities or school districts do profit through the mistakes of their officers. We do not here deal with dishonesty, overreaching or unfair advantage; we have here delays of contractors and public officers claimed to be tantamount to negligence in failing to perform a public duty to the detriment of appellee.

The contract contained a provision relative to delays by the acts or neglect of the owner, architect, or other contractor or for any delays incident to the work. * The rule *104 relative to delays in the prosecution of work by an act or neglect of the owner, architect, or other contractors, or changes in the work and damages for wrongful acts or neglect has been thus stated. In construction work, an owner does not generally guarantee or indemnify against loss occasioned by the delays of independent contractors connected with the work which may be reasonably anticipated. The owner fulfills his duty when he selects as contractor a person generally known as responsible. Where contracts contain a provision against delay of other contractors or other incidents of the work, which provide in substance as this one does for no liability on the part of the owner for delays of contractors or changes in the work, such provision includes delays of other contractors in connection with the work, or delays which are covered by the contract or reasonably anticipated from the circumstances attending the project: Restatement of Contracts, section 315 (1) (b); see Goss v. Northern Pac. Hosp. Assn., 50 Wash. 236; Thompson v. St. Charles Co., 227 Mo. 220. But such provisions have no reference to an affirmative or positive interference on the part of the owner or his representative apart from the contract, or ordinarily to a failure to act in some essential matter necessary to the prosecution of the work unless delay in performance is contemplated by the contract; these interferences or failures may cause damages in other ways than that contemplated by the provision against delays: See Mulholland v. City of New York, 113 N. Y. 631; Weeks v. Rector, etc., of Trinity Church, 67 N. Y. S. 670; Erickson v. U. S., 107 Fed. 204; Cornell Co. v. Schuylkill *105 Co., 222 Fed. 876; Sheehan v. Pgh., 213 Pa. 133; Pitt. Con. Co. v. Dayton, 237 Fed. 305. Such provisions do not include negligent acts of public officers in performing governmental functions, which will be discussed later.

Where a party under a delay and time extension provision on entering a contract foresees or should foresee that the work might be delayed by the failure of the owner or another contractor to perform, “the remedy therefor . . . [is an] extension of time on the part of those who perform the work, and the presumption arises that this was intended to measure the rights of the contractor thereunder”: Goss v. Northern Pac. Hosp. Assn., supra; Cornell Co. v. Schuylkill Co., supra; see Richard v. Clark, 88 N. Y. S. 242; Haydnville M. & M. Co. v. Art Institute, 39 Fed. 484.

The general rule as to affirmative or positive acts is that where they materially interfere with the forwardness of the work, or cause other damage, the owner is liable, or as to negative action where the execution of such contract is dependent upon something essential, which is to be performed by the owner, the default of the owner for an unreasonable time, resulting in damages to the contractor, may render the owner liable for such damages. “Article 31” on “Damages” in the contract is within this rule. The wrongful act or neglect referred to in article 31 relates to loss sustained by causes not within article 18, the provision for delays. Illustration of a positive act within provisions similar to article 31 apart from the immediate contract is where the owner’s engineers in the construction of a road gave a wrong grade (Mulholland v. City of New York, supra), or furnished defective materials (McPherson v. San Joaquin Co., 6 Cal. Unrep. 257, 56 Pac. 802), willful interference with contract, thus raising price of bricks (King & Kennedy v. Des Moines, 99 Iowa 432), willful acts of the owners (Merrill v. I. & O. R. R., 16 Wend.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Spearly Construction, Inc. v. Penns Valley Area School District
121 A.3d 593 (Commonwealth Court of Pennsylvania, 2015)
Sewer Authority of Scranton v. Pennsylvania Infrastructure Investment Authority
81 A.3d 1031 (Commonwealth Court of Pennsylvania, 2013)
Quinn Construction, Inc. v. Skanska USA Building, Inc.
730 F. Supp. 2d 401 (E.D. Pennsylvania, 2010)
LVI Environmental Services Inc. v. Duane Morris LLP
12 Pa. D. & C.5th 457 (Philadelphia County Court of Common Pleas, 2010)
Eastern Electric Corp. v. Shoemaker Construction Co.
657 F. Supp. 2d 545 (E.D. Pennsylvania, 2009)
Mar-Paul Co. v. Jim Thorpe Area School District
7 Pa. D. & C.5th 387 (Carbon County Court of Common Pleas, 2008)
James Corp. v. North Allegheny School District
938 A.2d 474 (Commonwealth Court of Pennsylvania, 2007)
Guy M. Cooper, Inc. v. East Penn School District
903 A.2d 608 (Commonwealth Court of Pennsylvania, 2006)
ILM Systems, Inc. v. Suffolk Construction Co.
252 F. Supp. 2d 151 (E.D. Pennsylvania, 2002)
Grimme Combustion, Inc. v. Mergentime Corp.
595 A.2d 77 (Superior Court of Pennsylvania, 1991)
Deligiannis v. PepsiCo, Inc.
757 F. Supp. 241 (S.D. New York, 1991)
K.L. Conwell Corp. v. City of Albuquerque
802 P.2d 634 (New Mexico Supreme Court, 1990)
Coatesville Contractors & Engineers, Inc. v. Borough of Ridley Park
506 A.2d 862 (Supreme Court of Pennsylvania, 1986)
Sullivan v. County of Bucks
499 A.2d 678 (Commonwealth Court of Pennsylvania, 1985)
Pee Jay's Packing Co. v. Makfil Systems
34 Pa. D. & C.3d 285 (Philadelphia County Court of Common Pleas, 1983)
Draft Systems, Inc. v. Rimar Manufacturing, Inc.
524 F. Supp. 1049 (E.D. Pennsylvania, 1981)
EC Ernst, Inc. v. Koppers Co., Inc.
476 F. Supp. 729 (W.D. Pennsylvania, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
178 A. 662, 319 Pa. 100, 1935 Pa. LEXIS 646, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henry-shenk-co-v-erie-county-pa-1935.