Commonwealth v. Nelson-Pedley Construction Co.

154 A. 383, 303 Pa. 174
CourtSupreme Court of Pennsylvania
DecidedFebruary 3, 1931
DocketAppeal, 11
StatusPublished
Cited by24 cases

This text of 154 A. 383 (Commonwealth v. Nelson-Pedley Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth v. Nelson-Pedley Construction Co., 154 A. 383, 303 Pa. 174 (Pa. 1931).

Opinion

Opinion by

Mr. Justice Simpson,

The Nelson-Pedley Construction Company, Inc., one of the defendants, entered into a written agreement with *177 the Commonwealth to construct for the latter the first part of what is known as “South Office Building No. 2 in Capitol Park at Harrisburg.” The other defendant is the surety for the completion of the contract; but no defense peculiar to the surety is alleged, and hence its agreement need not be considered. When the building was about eighty per cent finished, and was still in the possession of the contractor, a fire of unstated origin injured certain of the materials which had been set in place, and the ultimate question to be decided is whether the Commonwealth or the defendants must bear the loss thus occasioned. The court below, to whom the controversy was submitted in accordance with the Declaratory Judgments Act, decided in favor of defendants, and the Commonwealth thereupon prosecuted the present appeal. The declaratory judgment must be reversed.

In the court below and here, much time was spent in debating whether the construction contract is an entire or divisable one. We are clear that it is an entire contract, but do not care to discuss the question, since, no matter by what name it may be entitled, the rights of the parties are readily determinable from the language appearing in it. Where the validity of a cause of action or defense depends on the character of the contract in suit, that question must be decided in order to do justice between the parties; but where their respective rights, so far as they are at issue in the particular case, are governed by the written language of their contract, a statement of the class to which it belongs is of no moment, — the language controls. In this case, the contract says that the “Contractor agrees to......do and perform all labor, superintendence and all means of construction necessary to execute, construct and finish in an expeditious, substantial and workmanlike manner, the work necessary for the construction [of the building], all said work to be done in accordance with said plans and specifications and general conditions and other terms and conditions of this contract to the satis *178 faction and acceptance of the department of property and supplies of the Commonwealth......[and the] Commonwealth agrees in consideration of the completion by contractor of the work contemplated in this contract in strict accordance therewith to the satisfaction and acceptance of said department of property and supplies to pay to the contractor the sum of $3,430,000” in monthly installments as the work progresses. Under this language, the contractor must complete the work in accordance with the plans and specifications, to the satisfaction and acceptance of the department, for this it has expressly agreed to do. Until it has done so, it has not complied with its contract, though the building ad interim has been damaged by fire; the cost of restoration, in that event, being upon the contractor and not upon the Commonwealth: Murphy v. Liberty Nat. Bank, 184 Pa. 208, 217; Cramp & Co. v. Central Realty Corp., 268 Pa. 14, 20.

Another paragraph of the contract makes this conclusion particularly clear. It says: “The work in every respect, from the execution of the contract bond and during its progress until final acceptance, shall be under the charge and in the care of the contractor and at his risk. He shall properly safeguard against any and all injury or damage to the public, [and] to any property, material or thing, except when stipulated otherwise in the specifications, and shall alone be responsible for any damage or injury from his undertaking of this work to any person or persons or thing connected therewith.” Defendants contend that the word “work” in the first sentence of this paragraph “can refer only to the work of construction, not to the thing constructed.” Assuming this, the sentence would then read: “The work [of construction] in every respect, from the execution of the contract bond and during its progress until final acceptance shall be under the charge and in the care of the contractor and at his.risk.” If the work of construction is “in every respect” at the contractor’s risk, until *179 its completion by Mm and its final acceptance by tbe department, then he must take the risk of anything happening to it until it is completed and accepted. This is emphasized by the next sentence which requires the contractor to “properly safeguard against any and all injury to the public [and] to any property, material or thing,” and to “be responsible for any damage or injury from his undertaking of this work to any person or persons or thing connected therewith ” It follows that the contractor cannot escape its liability to the Commonwealth unless the latter was responsible for the fire, or in some way defaulted in its duty under the contract,— neither of which is pretended, — or unless there are other provisions in the contract so paramount and mandatory as to overcome wholly those above quoted, or unless there is some statute which is controlling. Under none of these heads can defendants find relief from liability.

So far as concerns the other provisions of the contract, defendants point to the fact that the building to be constructed is but a “part of South Office Building No. 2”; that certain kinds of work necessary to be done in order that it may be ready for actual occupancy and use as an office building, were excluded from the contract; that a percentage of the appraised value of the work actually done is to be paid monthly; and that the Commonwealth reserved the right to delay the performance, and perhaps to annul the contract, should “unforeseen causes” so require. It might be. necessary to decide what inferences should be drawn from these provisions if defendants’ liability itself depended on inferences, but, as it is based on express and positive language, they are of no moment whatever: Expressio unius est exclusio alterius, Broom’s Legal Maxims *657. The contractor expressly agreed to complete the work specified; though it was but a part of the building ultimately to be constructed, and was but a part of that needed before its actual occupancy and use as an office building; though the work to be done was to be paid for *180 in the way stated; and though the contract contained the reserved rights referred to, — which were never exercised, however. Having expressly agreed to be liable although these several matters appeared in the contract, defendants cannot be heard to say they are not liable because of their appearance in it. This is an impossible contention, since it is, within itself, a contradiction in terms.

Up to this point, we are in accord with the court below, but have now “reached the parting of the ways.” It held that, despite the foregoing, the Commonwealth could not recover because of section 31 of the general conditions of the contract (interpreted according to the rule of construction which says that, where the language of a contract is ambiguous, it must be construed most strongly against the party who drew it, — in this instance the Commonwealth), when considered in connection with the Insurance Fund Act of May 14, 1915, P. L. 524, as amended in immaterial particulars by the Acts of May 8, 1919, P. L. 157, and May 12, 1921, P. L. 549.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Fuel Gas Distribution Corp. v. Pennsylvania Public Utility Commission
511 A.2d 907 (Commonwealth Court of Pennsylvania, 1986)
Commonwealth v. Frank Briscoe Co.
460 A.2d 367 (Commonwealth Court of Pennsylvania, 1983)
Latrobe Municipal Authority v. Youngstown Borough Municipal Authority
456 A.2d 234 (Commonwealth Court of Pennsylvania, 1983)
Hartford Fire Ins. Co. v. Riefolo Constr. Co.
390 A.2d 1210 (New Jersey Superior Court App Division, 1978)
Pennsylvania Department of Transportation v. DePaul
371 A.2d 261 (Commonwealth Court of Pennsylvania, 1977)
Mullen v. Travelers Indemnity Co.
67 Pa. D. & C.2d 181 (Monroe County Court of Common Pleas, 1974)
Baker v. Commonwealth
315 A.2d 669 (Commonwealth Court of Pennsylvania, 1974)
Lehman Bros. v. Redevelopment Authority
64 Pa. D. & C.2d 533 (Dauphin County Court of Common Pleas, 1973)
Remsco Associates, Inc. v. Beaver Falls Municipal Authority
63 Pa. D. & C.2d 561 (Beaver County Court of Common Pleas, 1973)
Robert F. Felte, Inc. v. White
302 A.2d 347 (Supreme Court of Pennsylvania, 1973)
Bessen Bros. v. Brooks
107 A.2d 623 (Superior Court of Pennsylvania, 1954)
Welsh's Estate
61 Pa. D. & C. 47 (Philadelphia County Orphans' Court, 1947)
Wolter's Estate
61 Pa. D. & C. 133 (Philadelphia County Orphans' Court, 1947)
Spingarn v. Fidelity-Philadelphia Trust Co.
49 Pa. D. & C. 383 (Philadelphia County Court of Common Pleas, 1943)
DeChicchis v. Elizabeth Borough School District
15 A.2d 492 (Superior Court of Pennsylvania, 1940)
State Ex Rel. City of Missoula v. Holmes
47 P.2d 624 (Montana Supreme Court, 1935)
Henry Shenk Co. v. Erie County
178 A. 662 (Supreme Court of Pennsylvania, 1935)
Commonwealth v. Great American Indemnity Co.
167 A. 793 (Supreme Court of Pennsylvania, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
154 A. 383, 303 Pa. 174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-v-nelson-pedley-construction-co-pa-1931.