Cramp & Co. v. Central Realty Corp.

110 A. 763, 268 Pa. 14, 1920 Pa. LEXIS 623
CourtSupreme Court of Pennsylvania
DecidedJune 26, 1920
DocketAppeal, No. 188
StatusPublished
Cited by12 cases

This text of 110 A. 763 (Cramp & Co. v. Central Realty Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cramp & Co. v. Central Realty Corp., 110 A. 763, 268 Pa. 14, 1920 Pa. LEXIS 623 (Pa. 1920).

Opinion

Opinion by

Mr. Justice Frazer,

Plaintiff contracted to provide materials and perform the work necessary in the construction of an eight-story building situate in the City of Philadelphia, in accordance with plans and specifications prepared by the Hoffman Company, architect, and approved by Smith, Hinehman & Grylls, supervising architects. During the progress of the work extras in the form of labor and materials were required and delays occurred, resulting in additional cost incident to the completion of the building; [18]*18to recover for these items, and an unpaid balance on the contract, this action was commenced. The total amount claimed was $149,813.46, made up of an unpaid balance on the contract price, in accordance with certificates of the architects, amounting to $34,290.09; a claim of $57,-465.17 for delay alleged to have been caused through the fault of the owner; $13,606.05 for extra work; and $44,-452.15 as consequential damages to plaintiff by reason of increased cost due to delay in completion of the work, for which delay it is alleged defendant was responsible. An affidavit of defense was filed raising a question of law as to the sufficiency of the statement of claim and, after argument and reargument of the rule for judgment, the court below entered judgment in plaintiff’s favor for the unpaid balance of $34,290.09, with leave to defendant to file an affidavit of defense to the merits of the item of $57,465.17, and judgment in favor of defendant as to the claims for extra work and consequential damages. Plaintiff appealed and the only questions before this court refer to the correctness of the lower court’s conclusion with respect to the items of $13,-606.05 and $44,452.15.

The claim of $13,606.05 is made up of two items which must necessarily be considered separately. The first is for $12,656.05, representing additional outlay incident to the construction of extra footings for the foundation of the building, rendered necessary by an order of the building inspector of the city, to the effect that the soil at the depth specified in the plans was of insufficient character to support the weight of the building, and directing that the excavation be deepened and the foundation and columns increased in size. To defeat this claim, as a matter of law, defendant asserts article VI of the contract provides that “No alterations or additions, or anything that shall put additional cost or charge upon the owner shall be made in or to the work except upon the written order of the architects countersigned by the treasurer of the owner,” and avers such order was not [19]*19given; that under article III of the contract the decision of the architects “as to the true construction and meaning of the drawings and specifications shall be final” and that the statement disclosed the architects had rejected plaintiff’s claim; and further that the extra footings were required because the plans and specifications could not be carried out as contemplated, which circumstance imposed no liability upon defendant for the cost of the extra work, as the contract provided all work should be done and materials furnished in accordance with law and the city ordinances and should comply with all “building laws and orders of the authorities.” Defendant also contended the requirement of extra footings was an unforeseen contingency which, under the contract and the law, was assumed by plaintiff.

We need not consider the question of the sufficiency of the averment of waiver of the provision that extra work would not be paid for by the owner unless upon the written order of the architects countersigned by the treasurer, in so far as it applies to extra footings, for the reason the additional work was made necessary by the order of a public official, acting within the police power of the city and out of consideration for the public safety, and was not a matter as to which either the owner of the building or the contractors or architects could exercise an option. The requirement of the official was final and conclusive on all parties, regardless of whether or not an order for the change was signed by the architects: Cunningham v. Fourth Baptist Church, 159 Pa. 620. Neither is there merit in the contention that the clause, making final the decision of the architects as to the true construction and meaning of the drawings and specifications, must govern the question raised, as this is not a question of construing the meaning of the drawings and specifications, but one relating to the effect of an order of the building inspector upon the contract between the parties. The law recognizes the right of parties to contracts to stipulate the method of arbitrating [20]*20questions arising between them in the performance of tbeir agreement, but, since such privilege is in derogation of the common law right of trial by jury, it will not be extended beyond the express terms agreed upon between the parties, and the burden of showing that a particular question is within the arbitration clause rests upon the party asserting it: Hunn v. Penna. Ins. for the Blind, 221 Pa. 403, 411. The question under discussion does not appear to be within the scope of matters to be construed by the architects, and in fact defendant seems to concede the correctness of this view and bases its argument mainly upon the ground that, under the contract and the law applicable to its provisions, there was no liability imposed upon it to assume the cost of construction of the extra footings.

It is conceded that, under the common law rule, a contractor who undertakes an entire contract for erecting a building is presumed, in absence of an express provision to the contrary, to have assumed the risk of unforeseen contingencies arising during the course of the work, unless performance is rendered impossible by the act of God, the law, or the other party: Miller v. Homeopathic Hospital, 243 Pa. 502. Under this rule there is no implied Avarranty of the sufficiency of the soil to support the building to be erected, and the contractor assumes the risk of a loss incident to such defectiveness. It is contended, however, the contract in this case contains provisions bringing it within the exception to the above rule, and in support of that contention plaintiff relies mainly on Miller v. Homeopathic Hospital, supra. Plaintiff there agreed to furnish the materials and labor in the construction of a building in accordance with plans and specifications, and before its completion the foundations gave way necessitating the rebuilding of a portion of the wall on more substantial footings. The court held the contractor was entitled to recover the additional expenses of enlarging the footings and reconstructing the wall. ' The contract in that case contained the usual [21]*21provisions of the standard printed form of contracts generally followed in such undertakings, many of them being almost identical with pertinent provisions of the present contract. There are, however, points of distinction between that case and this considerably affecting the weight of the former as a precedent. The architect there was plainly the agent of the owner, and the contractor, in addition to other work, was required to build a platform for the purpose of making tests if directed to do so by the architect. This requirement necessarily implied that the contractor was under no further duty to make tests and personally determine the sufficiency of the bearing surface of the soil. The court there found it was the duty of the architect, as agent of the owner, to make the soil tests and prepare necessary changes in the plans of the footings, as specified, where found to be insufficient.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Newcomb v. Schaeffler
279 P.2d 409 (Supreme Court of Colorado, 1955)
Freeman v. Stanbern Construction Co.
106 A.2d 50 (Court of Appeals of Maryland, 1954)
O'Neill Construction Co. v. Philadelphia
6 A.2d 525 (Supreme Court of Pennsylvania, 1939)
Com. v. Consolidated Indemnity & Insurance
164 A. 78 (Superior Court of Pennsylvania, 1932)
Stange v. Philadelphia
162 A. 833 (Supreme Court of Pennsylvania, 1932)
Commonwealth v. Nelson-Pedley Construction Co.
154 A. 383 (Supreme Court of Pennsylvania, 1931)
Garman Bros. v. Hoover Et Ux.
95 Pa. Super. 203 (Superior Court of Pennsylvania, 1928)
Smith v. Faust
92 Pa. Super. 267 (Superior Court of Pennsylvania, 1927)
Lehr v. St. Paul's Evangelical Lutheran Congregation
4 Pa. D. & C. 709 (Lehigh County Court of Common Pleas, 1924)
White v. Mitchell
213 P. 10 (Washington Supreme Court, 1923)
Rose v. Scott
75 Pa. Super. 196 (Superior Court of Pennsylvania, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
110 A. 763, 268 Pa. 14, 1920 Pa. LEXIS 623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cramp-co-v-central-realty-corp-pa-1920.