Hunn v. Pennsylvania Institution for the Instruction of the Blind

70 A. 812, 221 Pa. 403, 1908 Pa. LEXIS 496
Supreme Court of Pennsylvania·Decided May 18, 1908·No. Appeal, No. 91·Published·Cited by 19 cases

Opinion

Opinion by

Mr. Justice Elkin,

The plaintiff brought an action of assumpsit to recover an alleged balance due on a building contract and in his statement of claim averred performance. The defendant entered a plea of non assumpsit, payment and set-off, to which plaintiff replied non solvit, no set-off and issue. When the case came on for trial the plaintiff offered in evidence the contract, plans and specifications, and then produced as a witness J. W. Mercur, a member of the contracting firm. Counsel being asked what he intended to prove by this witness, placed on record an elaborate offer covering the purpose of the testimony to be given. Counsel for defendant objected on the ground that the contract between the parties showed that final payment was not to be made until the architects had certified that the work had been completed in accordance with the plans and specifications, and it was not proposed to show that the architects had passed upon questions in dispute between the parties, and for the further reason that complete performance having been averred, proof which shows nonperformance or part performance, is not sufficient to sustain the allegata, which objection was sustained by the court.

No further testimony was offered and the learned trial judge directed the jury to return a verdict for defendant. This appeal raises the question whether the proof offered, but rejected, should have been admitted and, if so, was it sufficient to sustain the averments of the declaration. It is elementary that the probata must sustain the allegata, and of course one who avers performance and fails to prove it has no right to recover. In the present case, however, the contention is [409] not only that performance was averred, but that the proof offered showed performance within the meaning of the law. Whether the contention can prevail necessarily depends upon the facts. The suit was brought to recover the balance due for the construction of a completed building, and the facts show that the building was completed at the time the action was commenced. The performance averred and necessary to be proven was the completion of the building, not the completion within the time fixed in the contract. Failure to complete within the specified time did not forfeit the right to recover, if completed at a later date, but subjected the contractors who might be in default in this respect to the payment of a certain sum for each day of delay as liquidated damages. It was not necessary either to aver or prove completion on August 1, 1898, in order to recover such balance as might be justly due under the contract. Time is not of the essence of the contract in question in the sense that failure to complete within a fixed period forfeits the right to recover for work already done at the date fixed for completion, or yet to be done at that time. The contract provides, not a forfeiture of the right to recover, upon failure to complete on a certain date, but for liquidated damages to be deducted from the contract price. Nor, as we construe the contract, did the right to recover depend upon the completion of the building bjr the contractors themselves, because it is therein provided in clause eleven that upon the happening of certain contingencies the owners shall have the right to enter upon the premises, takes possession of materials, employ men and' complete the building, which right was exercised in this case. The final payment of any balance due the contractors, in the event of the owners electing to complete, was to be held in abeyance until the building was thus completed, when upon settlement the owners were authorized to deduct from the balance due the contractors, the cost of completion, and such damages as may have resulted to the owners by the alleged default of the contractors. By the express covenants of the contract it clearly appears the parties had in contemplation, first, completion by the contractors, and, second, under certain circumstances part performance by the contractors, and final completion by the owners, and the right to recover such balance [410] as was justly due did not depend upon entire completion by the contractors, but upon completion, either by the contractors, or partly by the contractors and partly by the owners, and when completed in either way, final settlement was to be made in the manner provided. We, therefore, hold that the averment of complete performance in so far as the construction of the building is involved is sustained by proof which shows that the contractors performed a large part of the work and that the building was finally completed by the owners in accordance with the contract. When the owners completed the building the day of final settlement had arrived, subject, of course, to the respective rights of the contracting parties as defined by the contract. The contract itself pointed out the method of settlement, which was that the contractors were entitled to receive the total contract price for a completed building, with such allowance or deduction as should be made for alterations, less advances made from time to time, and in the event of the building being completed by the owners, then the cost of completion to be deducted, together with an allowance for such damage as may have resulted by delay or otherwise in completing according to contract. The contracting parties themselves provided an orderly and sensible .method of making settlement, and we can see no reason why pleadings framed and proofs offered, in an action brought to determine the legal rights of the parties, which produce and sustain an issue by means of which an alleged balance claimed to be due may be ascertained in accordance with the terms of the contract, should be held insufficient.

Free access — add to your briefcase to read the full text and ask questions with AI

Hunn v. Pennsylvania Institution for the Instruction of the Blind, 70 A. 812, 221 Pa. 403, 1908 Pa. LEXIS 496 (Pa. 1908).

70 A. 812 (Hunn v. Pennsylvania Institution for the Instruction of the Blind) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Giant Markets, Inc. v. Sigma Marketing Systems, Inc.
459 A.2d 765 (Superior Court of Pennsylvania, 1983)
Bacon v. Newtown Friends' School
77 Pa. D. & C. 324 (Bucks County Court of Common Pleas, 1950)
Sanctis Construction, Inc., Arbitration Case
43 A.2d 581 (Superior Court of Pennsylvania, 1945)
J. S. Cornell & Son, Inc. v. Rosenwald
13 A.2d 716 (Supreme Court of Pennsylvania, 1940)
Vecellio v. Bopst
6 S.E.2d 708 (West Virginia Supreme Court, 1939)
Zimmerman v. Marymor
138 A. 824 (Supreme Court of Pennsylvania, 1927)
Jost Jost v. Kurtz Kurtz
82 Pa. Super. 205 (Superior Court of Pennsylvania, 1923)
Finley v. Pew
205 P. 310 (Wyoming Supreme Court, 1922)
Dinnie v. Lakota Hotel Co.
186 N.W. 248 (North Dakota Supreme Court, 1921)
Cramp & Co. v. Central Realty Corp.
110 A. 763 (Supreme Court of Pennsylvania, 1920)
Forty-Sixth Ward
58 Pa. Super. 428 (Superior Court of Pennsylvania, 1914)
Reilly v. Rodef Sholem Congregation
90 A. 345 (Supreme Court of Pennsylvania, 1914)
Shoemaker v. Riebe
88 A. 662 (Supreme Court of Pennsylvania, 1913)
Smith v. Cunningham Piano Co.
86 A. 1067 (Supreme Court of Pennsylvania, 1913)
Kann v. Bennett
82 A. 1111 (Supreme Court of Pennsylvania, 1912)
Thaler Bros. v. Greisser Construction Co.
79 A. 147 (Supreme Court of Pennsylvania, 1911)
Conneaut Lake Agricultural Ass'n v. Pittsburg Surety Co.
74 A. 620 (Supreme Court of Pennsylvania, 1909)