J. S. Cornell & Son, Inc. v. Rosenwald

13 A.2d 716, 339 Pa. 18, 1940 Pa. LEXIS 577
CourtSupreme Court of Pennsylvania
DecidedApril 10, 1940
DocketAppeal, 180
StatusPublished
Cited by14 cases

This text of 13 A.2d 716 (J. S. Cornell & Son, Inc. v. Rosenwald) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. S. Cornell & Son, Inc. v. Rosenwald, 13 A.2d 716, 339 Pa. 18, 1940 Pa. LEXIS 577 (Pa. 1940).

Opinions

Opinion by

Mr. Justice Linn,

This is a suit for a balance claimed for a contractor’s services in building a residence and appurtenances for defendant. It is alleged that the parties met in April, 1937, and discussed the project; it was proposed that the contractor should furnish materials and perform the contract on a cost-plus basis; the interview resulted in the understanding that the probable cost of the project would be $330,500, and that plaintiff should receive a contractor’s fee of $25,000 for its services. Defendant’s architect participated in the conference but at that time had not worked out detailed plans and specifications. Shortly afterward, plaintiff was notified it had been awarded the contract and on April 22, 1937, as appears by defendant’s petition, to be referred to later, a paper *20 entitled a “Building Agreement,” Exhibit A to defendant’s petition, was executed. They also- executed, as part of the building agreement, an instrument entitled “The General Conditions of the Contract for the Construction of Buildings,” Exhibit B to defendant’s petition. The plaintiff avers that on May 11, 1937, when the work of construction began, “no completed plans or specifications for any part of the said operation were supplied to plaintiff Company, and as the work progressed the magnitude and cost of the mansion and of its component parts and appointments and of its outlying appurtenances and complementary buildings were vastly increased, and continued to be increased from time to time as the work progressed by the specific direction and order of Grunsfeld [the architect] and of defendant; so that when the work was eventually completed and defendant and his wife were able to take up residence in the new mansion house the actual total cost of the entire project, instead of being $330,500, as originally planned and understood by Grunsfeld and plaintiff’s representatives as aforesaid, based upon specific information supplied by Grunsfeld to plaintiff’s representatives had been increased by $587,933.64, to make a grand total of $918,433.64.”

Paragraph 17 avers “From time to time, as the magnitude of the job increased as aforesaid, plaintiff, through its agent Allen D. Cornell, mentioned to defendant’s agent Grunsfeld that with the increase at the specific direction of Rosenwald and Grunsfeld in the actual cost of the job, plaintiff’s fee would have to be correspondingly increased, and Grunsfeld expressed approval of, and assent to, the statements so made to him.” The balance claimed by plaintiff is stated as follows: “19. A fair, reasonable, and customary percentage rate of fee, based upon a percentage of the total actual cost of construction, which in this instance was $918,433.64, as aforesaid is 7%% on first $350,000 or $26,250, and 5% on the balance of $568,433.64, or $28,421.68, *21 making a total percentage fee compensation of $54,671.68 payable as of the date on which defendant and his wife moved into the new house, March 18, 1939. Defendant has paid to plaintiff a total of $25,000, leaving a balance of principal due in the sum of $29,671.68, with interest from March 18, 1939, to date of payment.”

Instead of filing an affidavit of defense, defendant moved to require plaintiff to arbitrate: section 3 of the Arbitration Act of 1927, P. L. 381, as amended, 5 PS section 163. In his petition for the order to arbitrate, defendant averred that the parties had executed a written agreement by which plaintiff had agreed to demolish certain buildings on defendant’s land and to erect “certain new structures thereon" all as set forth in the contract” Exhibit A, attached to the petition. * He alleged that “the contract consisted of a building agreement, marked Exhibit ‘A’, and also drawings and specifications as described in Article I thereof.”

Plaintiff answered the petition, admitting the written contract, Exhibits A and B, but averring that the contract was “mutually abandoned . . . soon after the execution thereof” and that the services subsequently rendered, and for which compensation was demanded, were rendered in the circumstances alleged in the statement of claim.

*22 After hearing argument on the petition and answer an order was made requiring arbitration from which plaintiff appeals.

It is unnecessary to deal particularly either with plaintiff’s contention that the abandonment of the contract carried with it the arbitration provisions, or with defendant’s reply that the abandonment is not sufficiently alleged to deprive him of the right to arbitrate plaintiff’s claim for the increased fee. We say it is unnecessary because the order to arbitrate can only be sustained if the parties have agreed that the issue in dispute shall be submitted to arbitration. That issue, as claimed in plaintiff’s statement, is whether the contractor is entitled to additional compensation for services rendered beyond what was originally contemplated by the parties. Whether such a dispute is covered by the arbitration provisions is a question of law — the construction of the writing.

The written contract not only does not provide for the arbitration of all disputes that may arise in the performance or non-performance by either party, but provides for arbitration in only three cases. They are specified in Article XII of Exhibit A, the building agreement. It provides: “Art. XII. In case the Owner and Contractor fail to agree in relation to matters of payment, allowance or loss referred to in Arts. Ill or YIII of this contract, or should either of them dissent from the decision of the Architect referred to in Art. YII of this contract, which dissent shall have been filed in writing with the Architect within ten days of the announcement of such decision, then the matter shall be referred to a Board of Arbitration. ...”

The Article III, so referred to, provides: “No alterations shall be made in the work except upon written order of the Architect; the amount to be paid by the Owner or allowed by the Contractor by virtue of such alterations to be stated in said order. Should the Owner and Contractor not agree as to amount to be paid *23 oi’ allowed, the work shall go on under the order requix*ed above, and in case of failure to agree, the determination of said amount shall be referred to arbitration, as provided for in Art. XII of this contract.”

Articles VIII aud VII, also referred to in Article XII, need not be quoted; they deal with disputes about the amount to be paid, and by whom, for loss resulting fi’om delay, matters not now involved in the case. We are concerned only with the meaning of Article III dealing with payment or allowance for alterations made in the work.

The rule is that arbitration agreements are strictly construed and are not to be extended by implication. In Jacob v. Weisser, 207 Pa. 484, 489, 56 A. 1065, in limiting the jurisdiction of an architect, the court quoted Chandley Bros. v. Cambridge Springs, 200 Pa. 230, 49 A. 772, that “The terms of the agreement ax’e not to be strained to discover it. They must be clear and unmistakable to oust the jurisdiction of the courts; for trial by jury cannot be taken away by implication merely in any case.” For other applications of the rule, see Somerset Boro. v. Ott, 207 Pa. 539, 56 A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Le Vin Company v. Blue Star Wine Company
Superior Court of Pennsylvania, 2018
Metropolitan Edison Co. v. United Engineers & Constructors, Inc.
4 Pa. D. & C.3d 473 (Philadelphia County Court of Common Pleas, 1977)
Keystone Wire & Iron Works, Inc. v. Van Cor, Inc.
369 A.2d 758 (Superior Court of Pennsylvania, 1976)
Bangor Gas Co. v. Rosdor Construction Corp.
56 Pa. D. & C.2d 317 (Northampton County Court of Common Pleas, 1972)
Electrical Switchgear Union v. I-T-E Circuit Breaker Co.
36 Pa. D. & C.2d 178 (Philadelphia County Court of Common Pleas, 1964)
Jordan v. Allstate Insurance
30 Pa. D. & C.2d 486 (Delaware County Court of Common Pleas, 1963)
Philadelphia Transportation Co. v. Transport Workers Union of Philadelphia, Local No. 234
14 Pa. D. & C.2d 265 (Philadelphia County Court of Common Pleas, 1958)
International Ladies' Garment Workers' Union v. Nazareth Mills Co.
87 Pa. D. & C. 589 (Northampton County Court of Common Pleas, 1954)
Reading Tube Corp. v. Steel Workers Federation & Reading Tube Local
98 A.2d 472 (Superior Court of Pennsylvania, 1953)
McDevitt v. McDevitt
73 A.2d 394 (Supreme Court of Pennsylvania, 1950)
Wm. Linker Co., Inc. v. Feinberg Et Ux.
62 A.2d 839 (Supreme Court of Pennsylvania, 1948)
Schreiber v. Ostroff
65 Pa. D. & C. 601 (Philadelphia County Court of Common Pleas, 1948)
Margolies v. Zimmerman
19 A.2d 737 (Supreme Court of Pennsylvania, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
13 A.2d 716, 339 Pa. 18, 1940 Pa. LEXIS 577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-s-cornell-son-inc-v-rosenwald-pa-1940.