Thaler Bros. v. Greisser Construction Co.

79 A. 147, 229 Pa. 512, 1911 Pa. LEXIS 522
CourtSupreme Court of Pennsylvania
DecidedJanuary 3, 1911
DocketAppeal, No. 37
StatusPublished
Cited by15 cases

This text of 79 A. 147 (Thaler Bros. v. Greisser Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thaler Bros. v. Greisser Construction Co., 79 A. 147, 229 Pa. 512, 1911 Pa. LEXIS 522 (Pa. 1911).

Opinion

Opinion by

Mr. Justice Moschziskeb,

This was a mechanic’s lien proceeding in which Thaler Brothers, subcontractors, were plaintiffs, and the Butler Brewing Company, owner, and the Wilhelm Greisser Construction Company, contractor, were defendants. The verdict was for the plaintiffs for the full amount of their claim with interest, and the defendants have appealed.

The claim was founded upon a written contract dated September 25, 1902. Throughout this contract the plaintiffs are designated as “the contractor,” and the construction company as “the owner;” and it is therein provided, “The contractor under the direction and to the satisfaction of Wilhelm Greisser Construction Company, architects, acting for the purpose of this contract as agents of the said owner, shall and will provide all the materials and perform all the work mentioned in the specifications and shown on the drawings prepared by the said architects for the eleven (11) pressure tubs for the Butler Brewery, Butler, Pa., delv. and set up, as per specifications at above Brewery, which drawings and specifications are identified by the signatures of the parties hereto.” It is also provided: “The architects shall furnish to the contractor such further drawings and explanations as may be necessary to detail and illustrate the work to be done,” and “It is hereby mutually agreed .... that the sum to be paid by the owner to the contractor for said work and material shall be $2,750. . . . All payments shall be made upon written certificates of the architects to the effect that such payments have become due.” Further, “It is ... . agreed .... that no certificates given or payments made under this contract except the final certificate or final payment shall be conclusive evidence of the performance of this contract, either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper material.”

[516]*516The plaintiffs claimed that their work had been properly performed and that a balance of $1,370 was due and unpaid. In addition to a defense that the tubs were deficient in several particulars, which defense was correctly and fairly submitted to the jury, the defendants contended on other grounds that the plaintiffs should not be allowed to recover.

The plaintiffs failed to produce a certificate from the architects that the balance claimed was due them. Their testimony was that while they had received payments on account during the progress of the work, they had never received a certificate from the architects; that upon the completion of the work they made a demand for such a certificate; that the certificate was not given, but at that time the construction company sent them a check for $500 on account, which check was returned marked “no funds;” and that no fault had been found with their work or material until after the filing of the mechanic’s lien. No specific reason appears to have been assigned for the failure or refusal to give the certificate. The plaintiffs showed that after the completion of the work the head brew-master of the brewery expressed satisfaction with the tubs in the presence of Mr. Greisser, a representative of the construction company, and of Mr. Smith, the president of the brewing company; and that Mr. Greisser made no complaint at that time; that in point of fact Mr. Greisser had never made any complaint, although Mr. Smith in 1904 after the filing of the lien said for the first time that “the tubs was not good.” One of the plaintiffs testified that in 1903 prior to the filing of the lien, in an effort to secure the money due them, he had met Mr. Greisser and had been referred by him to Mr. Smith who said he would not “pay out money until Mr. Greisser gets through completely,” but found no fault with the work and offered the witness “two $1,000 second mortgage bonds for the brewery for our amount that was due the Greisser Construction Company;” that at a later date subsequent to the filing of [517]*517the lien, when the brewery was running and the tubs were in use, the witness again saw Mr. Smith who told him “that he had $2,700, holding back from the Greisser Construction Company and said that I would have to get the money from them and that they would pay Mr. Greisser just as soon as he got through with the buildings and the contractors;” Smith then for the first time said that “some of the tubs down there had worm-holes in them.” The tubs are still in use at the brewery, and one of the witnesses for the defense stated that they had not had any material trouble with them for the last three years.

The trial judge instructed the jury that if the declara-,, tion of dissatisfaction by the construction company was made in good faith, it was a sufficient defense and the! plaintiffs could not recover; on the other hand, if it was| not made in good faith, but was merely an arbitrary ex-f pression of dissatisfaction for the purpose of avoiding,) payment of the balance due on the contract, then would not be a good defense.

In considering these instructions, it is to be borne in mind that the lien was not filed under a contract between the brewing company, the real owner, and the construction company, the main contractor, but under a contract between the latter company and the plaintiffs in which the brewing company is nowhere referred to as the owner. On the contrary the construction company is expressly designated as owner, and it is provided that the work shall be done “under the direction and to the satisfaction of Wilhelm Greisser Construction Company, architects, acting for the purpose of this contract as agents of said owner.” In other words for the purposes of the contract the construction company was the owner, the agent of the owner and the architect.

In Pennsylvania two classes of cases involving con-i tracts requiring satisfactory performance have given rise 1 to two lines of decisions, the first of which is most aptly illustrated by Singerly v. Thayer, 108 Pa. 291, and the [518]*518other by Payne v. Roberts, 214 Pa. 568. (The former of these eases lays down the rule to be applied' where the work or material is to be satisfactory to the party acquiring it, and the latter ,where it must be' satisfactory , to a third party designated as arbiter. Under the first rule the question for determination is not as to whether "or not the one complaining ought to be satisfied, but Solely as to the good faith of the dissatisfaction alleged. i‘To justify a refusal to accept .... on the ground that it is not satisfactory, the objection should be made in good faith. It must not be merely capricious:” Singerly v. Thayer, 108 Pa. 291; followed in Krum v. Mersher 116 Pa. 17; Seeley v. Welles, 120 Pa. 69; Sidney School Furniture Co. v. Warsaw School District, 130 Pa. 76; Howard v. Smedley, 140 Pa. 81; Adams Radiator, etc., Works v. Schnader, 155 Pa. 394. Under the second rule it is not a question of the good faith of the dissatisfaction alleged; there, in order to maintain the action the claimant .must show that the expression of dissatisfaction was the result of fraudulent collusion between the arbiter and the owner: Payne v. Roberts, 214 Pa. 568. Also see Pittsburg Terra-Cotta Lumber Co. v. Sharp, 190 Pa. 256; Brown v. Decker, 142 Pa. 640; Hostetter v. Pittsburg, 107 Pa. 419; Reynolds v. Caldwell, 51 Pa. 298; McNally v. Montour R. R. Co., 33 Pa. Superior Ct. 51.

In the present case, while the mere fact that the construction company had a direct interest in the matter in controversy would not debar it from acting as a designated arbiter (Monongahela Navigation Co. v. Fenton, 4 W. & S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bonfitto v. Nationwide Mutual Insurance
172 A.2d 176 (Superior Court of Pennsylvania, 1961)
Sanctis Construction, Inc., Arbitration Case
43 A.2d 581 (Superior Court of Pennsylvania, 1945)
Rex v. Lehigh Valley Transit Co.
199 A. 324 (Supreme Court of Pennsylvania, 1938)
O'Hare v. McGee
176 A. 525 (Superior Court of Pennsylvania, 1934)
Gulf Refining Co. v. Frazier
15 Tenn. App. 662 (Court of Appeals of Tennessee, 1932)
Mills-Morris Co. v. Champion Spark Plug Co.
7 F.2d 38 (Sixth Circuit, 1925)
Jessup & Moore Paper Co. v. Bryant Paper Co.
129 A. 559 (Supreme Court of Pennsylvania, 1925)
Clark & Son v. Ley
1 Pa. D. & C. 437 (Crawford County Court of Common Pleas, 1921)
State Hospital for Criminal Insane v. Consolidated Water Supply Co.
110 A. 281 (Supreme Court of Pennsylvania, 1920)
Standard Construction Co. v. Quaker City Cracker Co.
73 Pa. Super. 402 (Superior Court of Pennsylvania, 1920)
Curran v. Philadelphia
107 A. 636 (Supreme Court of Pennsylvania, 1919)
Williams v. Notopolos
103 A. 290 (Supreme Court of Pennsylvania, 1918)
Stuart & Peterson Co. v. Newton
52 Pa. Super. 158 (Superior Court of Pennsylvania, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
79 A. 147, 229 Pa. 512, 1911 Pa. LEXIS 522, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thaler-bros-v-greisser-construction-co-pa-1911.