Thaler v. Wilhelm Griesser Construction Co.

40 Pa. Super. 331, 1909 Pa. Super. LEXIS 617
CourtSuperior Court of Pennsylvania
DecidedJuly 14, 1909
DocketAppeal, No. 175
StatusPublished
Cited by2 cases

This text of 40 Pa. Super. 331 (Thaler v. Wilhelm Griesser Construction Co.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thaler v. Wilhelm Griesser Construction Co., 40 Pa. Super. 331, 1909 Pa. Super. LEXIS 617 (Pa. Ct. App. 1909).

Opinion

Opinion by

Morrison, J.,

It seems to be necessary to make a rather extended statement of the facts which the plaintiffs allege they could have sustained before the jury. In making the following statement we are not assuming that the alleged facts cannot be successfully contradicted, but only that the plaintiffs seemed to have made a prima facie case, provided the jury found various allegations in their favor. But the learned court below saw fit to give a binding instruction in favor of the defendants on a technicality and thus put the plaintiff out of court; hence, this appeal.

The Butler Brewing Company desiring to build a brewery in Butler, Penna., entered into a contract for the construction of the same with the Wilhelm Griesser Construction Company of New York and Pittsburg. Among other things to be furnished by the contractor were eleven chip vats or pressure tanks and the said contractor sublet that portion of its contract to Thaler Brothers of Chicago, plaintiffs, who undertook the construction [333]*333and putting in place of said vats and they actually did comply with their contract, in all respects, as they allege. The plaintiffs were to receive from the Griesser company $2,750 and actually received $1,380, leaving the sum of $1,370 due and unpaid. The plaintiffs who reside in Chicago averred that they furnished the material and completed the work according to their contract on July 26,1903. On October 16,1903, less than three months after the last work was done under plaintiffs’ contract, and more than thirty days before their lien was filed, the plaintiffs caused a written notice of their intention to file a mechanic’s lien against the brewery building, ground and property, to be served on David Smith, president of the brewery company, by the sheriff of Butler county. This notice embraced a copy of the written contract between the plaintiffs and the Griesser company, a statement of the contract, the character of the work and material, the contract price, the amount remaining due, and how made up, and the time when the last work was done and material furnished as required by the Act of June 4, 1901, P. L. 431. And within thirty days thereafter, notice was given to the owner that such lien had been filed of record. The contract was made between the subcontractors and the contractor by correspondence; the agreement made and signed by them and mailed to each other. At this time the plaintiffs did not have or see a copy of the plans and specifications which were referred to in their contract with the contractor. It is alleged, and we do not see that it is denied, that during all of the time while plaintiffs did their work and completed their contract with the contractor, said plans and specifications were in the possession of the owner, the Butler Brewing Company, at Butler, Penna. It appears that the contractor instead of furnishing the plaintiffs with a copy of the plans and specifications, sent them a typewritten letter, giving quantity of lumber, size of tanks, etc., shape of tanks, number of hoops, etc. This was about the time they signed the contract.

The plaintiffs sent their foreman to Butler to set up the tanks and the typewritten letter was handed to him, and it was never returned to the plaintiffs but was lost or destroyed. When the [334]*334notice was given to the owner by the plaintiffs of their intention to file a lien, they did not have the plans, specifications and drawings, nor the typewritten letter above mentioned. After sci. fa. was issued on the lien, the brewing company, owner, filed an affidavit of defense to which all the plans, drawings and specifications, and everything belonging to its contract with the contractor were attached, and thereby made a part of the record. This was within 'six months from the date when the plaintiffs did the last work and furnished the last material under their contract. Therefore, it appears that the managing officers of the brewing company had full knowledge of the entire matter, and plaintiffs allege, and it does not seem to be denied, that the owner, the brewing company, at this time had over $27,000 of the money due the contractor in its hands.

After the trial and verdict, the plaintiffs moved the court for leave to amend their lien and pleadings, so as to cure the notice and attach the plans and specifications, etc., which the court permitted as to the lien but held that the notice could not be amended as that was a preliminary matter to the filing of the lien, and that the court had no power to permit the notice to be amended.

The error complained of specifically is directing the jury to find a verdict in favor of the defendants as follows: “In this case notice was given thirty days prior to the filing of the lien, but it seems that that notice, whilst it embraced a copy of this contract, did not embrace a copy of the specifications referred to therein and according to which this work was to be done. Now under these circumstances we are obliged to say to you that this lien is for that reason not self-supporting; that the lien does not show that such notice was given embracing that portion of these specifications relating to the vats in controversy. No such notice seems to have been given to the owner, that portion seemingly having been omitted. For these reasons we are constrained to say that this claim cannot be supported and it is our duty to say to you under the law that it is your duty to return a verdict in favor of the defendant.” This charge was duly excepted to and a bill sealed.

In the first place, the contract between the plaintiffs and the [335]*335Griesser company did not make the plans and specifications and drawings between the owner and contractor, a part of said-contract, nor was it provided that they should be attached to the contract. It would seem that said contract between the plaintiffs and the Griesser Construction Company, dated April 25, 1902, for the construction of the vats, is largely copied from some other contract and it contains much irrelevant and immaterial matter, but it is clear and precise as to the eleven pressure tubs for the Butler brewery, to wit: “shall and will furnish all the material and perform all the work mentioned in the specifications and shown on the drawings prepared by the said architects for eleven pressure tubs for the Butler Brewery, Butler, Pa., delivered and set up, as per specifications at above brewery, which drawings and specifications are identified by the signatures of the parties hereto.” Now, as we have said, this contract does not make the plans and specifications a part of it, nor does it provide that a copy thereof shall be attached to the contract. Therefore, we hold that it was not necessary for the plaintiffs to attach a copy of said plans and specifications to their notice of lien. All that they could be legally required to do was to give notice of the character and amount of their claim and how made up, and attach a copy of the contract under which the work was done and the material furnished, and attach an affidavit as required by the act of June 4,1901. Especially is this so when it appears by the contract, and by the defendant’s affidavit of defense, that the officials of the brewing company actually had in their possession, during all the time, the plans, drawings and specifications about which they complain so vehemently now because of the failure of the plaintiffs to attach the same to their notice of lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gerhart v. Christ
10 Pa. D. & C. 813 (Lancaster County Court of Common Pleas, 1927)
Thaler Bros. v. Greisser Construction Co.
79 A. 147 (Supreme Court of Pennsylvania, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
40 Pa. Super. 331, 1909 Pa. Super. LEXIS 617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thaler-v-wilhelm-griesser-construction-co-pasuperct-1909.