Curran v. Philadelphia

107 A. 636, 264 Pa. 111, 1919 Pa. LEXIS 603
CourtSupreme Court of Pennsylvania
DecidedMarch 10, 1919
DocketAppeal, No. 135
StatusPublished
Cited by22 cases

This text of 107 A. 636 (Curran v. Philadelphia) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Curran v. Philadelphia, 107 A. 636, 264 Pa. 111, 1919 Pa. LEXIS 603 (Pa. 1919).

Opinion

Opinion by

Mr. Justice Moschziskeb,

Prank Curran sought to recover from the City of Philadelphia a balance alleged to be due under a contract for cleaning certain of its streets. The agreement in question provides, by section 16 of the specifications, that the “engineer” is to “determine all questions in relation to the work and the prosecution thereof,” and “decide every question which may arise relative to the performance of the service covered by this contract”; further, that his “decision shall be final and conclusive.” Section 76 stipulates the “Director of Public Works” shall at stated periods determine what, if any, abatement shall be made from moneys due the contractor, as “liquidated damages” for various specified defaults, not af[114]*114fecting the amount of work done but the method of accomplishment ; and, in this connection, the exact damage to be deducted, for each of a listed number of delinquencies, is named, it being provided that the decisions of the director as to such deductions “shall be final and conclusive.” The work is to be performed to the “entire satisfaction” of the director “or his duly authorized agent or agents”; and the specifications say that, whenever the term “director” is used, it shall mean the director of public works, “or his authorized representatives.” Finally, the last paragraph in the contract states: “It is further expressly understood and agreed ......that nothing contained in this contract, or in the specifications hereto attached, shall be taken or construed to preclude the [city] from contesting the estimates or certificates of any officer of the city, or the claim of the [contractor] under this contract, or under such estimate or certificate; but the [city] shall be at full liberty to take every legal defense to the character, quality and quantity of the said work and materials, and to the time and manner in which the same shall be furnished and done, notwithstanding the certificates of approval of any officer of the said city.”

At trial, plaintiff proved that $1,566 had been deducted by the director from a stated settlement; that, of this sum, only $10 represented unperformed work, the balance, constituting the amount in controversy, being withheld for alleged defaults in the time and manner of performance, i. e., neglect to uniform street cleaners, failure to operate certain machines strictly in accord with the specifications, absence of employees, and such like omissions.

Binding instructions were given for defendant on the ground that, under the contract, the decision of the director was final and conclusive; a verdict was entered accordingly, judgment followed, and plaintiff has appealed.

[115]*115Appellant first contends that, since the agreement makes the decisions of the referees named therein binding upon the contractor but not upon the city, the submission to arbitration lacks mutuality and, therefore, obligates no one; and, on this theory, he urges that the award of the director cannot bar his right of recovery in the present suit. The point is well made if this clause of the contract has any controlling effect; but, as we shall show, it has not.

The provision in question must be considered in connection with the arbitration clauses of the agreement, and with the thought in mind that submissions are always construed so as to carry out the prime intention of the parties (Graham v. Graham, 9 Pa. 254, 256-257; Rogers v. Playford, 12 Pa. 181, 185; Kennedy v. Poor et al., 151 Pa. 472, 474), every reasonable intendment being made in favor of their validity: Pinch v. Lamberton, 62 Pa. 370, 373; Painter v. Kistler, 59 Pa. 331, 333; Robinson v. Bickley, 30 Pa. 384, 389-390; Bemus v. Clark, 29 Pa. 251, 253-254; Buckley v. Ellmaker, 13 S. & R. 71, 76; Gonsales v. Deavens, 2 Yeates 539, 541; Byrd v. Odem, 9 Ala. 755, 766; Joy v. Simpson, 2 N. H. 179, 181.

The clause under discussion is repugnant to the arbitration provisions of the contract and, if operative, avoids the latter, on the principle that submissions which are not binding on both parties obligate neither: Christman v. Moran, 9 Pa. 487; Keiser v. Berks Co., 253 Pa. 167, 169; Yeamans v. Yeamans, 99 Mass. 585; Onion v. Robinson, 15 Vt. 510. What is the effect of this situation?

The paramount purpose of the contracting parties must prevail. The city, being the one having the right to assert the repugnant clause, treats the writing as an arbitration agreement; since the intent it shall be such is too plain to be disregarded, the purpose of the parties in that respect is to be adhered to, if possible (McManus v. McCulloch, 6 Watts 357, 360; Somerset Boro. v. Ott, 207 Pa. 539, 542; Bubb v. Parker, etc., Oil Co., 252 Pa. [116]*11626, 29; 13 Corpus Juris, sec. 482, p. 521 et seq.), and, in order to accomplish this, the provision that the city shall not be bound by the award of the arbitrators may, and should, be held inoperative; for, as previously said, it is in conflict with the two arbitration clauses, which undoubtedly represent the predominant intent of both parties to the contract: Morrill, etc., Construction Co. v. Boston, 186 Mass. 217, 220; Smith v. Davenport, 34 Me. 520, 528. All of which brings us to this conclusion: Were the city itself to invoke the repugnant clause, as a defense to an award, it would not be sustained; hence the contract may, and should, be read as though that clause were absent; and, when so viewed, the lack of mutuality in the submission is only apparent, not real. Appellant’s first contention is dismissed.

The conclusion just stated leaves the arbitration and other features of the agreement standing; and we shall now consider the question raised by plaintiff concerning the proper construction to be placed thereon; also as to the validity of the director’s award.

Appellant contends that the various deductions made from the moneys due him, excepting, possibly, those hereinbefore referred to as amounting to $10, were all in the nature of penalties, and not liquidated damages. We cannot sustain this contention. Liquidated damages may be provided for in every instance where, from the character of work to be performed, it is manifestly impossible, or most difficult, to measure the damages, particularly for defined anticipated defaults which may be classified as probably harmful: Emery v. Boyle, 200 Pa. 249, 253; York v. York Rys. Co., 229 Pa. 236, 241.

The present is peculiarly a case for liquidated damages. As stated in the city solicitor’s brief, “The question as to whether or not the streets of a city are clean at any particular time is a matter susceptible of such wide divergence of opinion, that a contract for this purpose must deal mostly with the means by which that end is produced. It is necessary, therefore, to have specifications [117]*117based upon the experience of the department, showing what number of men, teams and implements shall be employed, how the work shall be done, in what manner the men must clothe and conduct themselves, so they may be easily identified and the work performed without offense to the public. The damage resulting from nonperformance of any of these items, or others like them, cannot be accurately determined. While the absence of a man, or an implement, might not prevent the cleaning of a street, yet it might keep a whole gang of men idle.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Toll Naval Associates v. Chun-Fang Hsu
85 A.3d 521 (Superior Court of Pennsylvania, 2014)
Pennsy Supply, Inc. v. Nicholson Co.
468 A.2d 808 (Supreme Court of Pennsylvania, 1983)
W. V. Pangborne & Co. v. Wark & Co.
64 Pa. D. & C.2d 109 (Philadelphia County Court of Common Pleas, 1974)
Reisman v. Ranoel Realty Co.
303 A.2d 511 (Superior Court of Pennsylvania, 1973)
Weiss v. Zerman Realty & Construction Co.
251 A.2d 810 (Superior Court of Pennsylvania, 1969)
Local 149, Boot and Shoe Workers Union v. Faith Shoe Co.
201 F. Supp. 234 (M.D. Pennsylvania, 1962)
Povey v. the Midvale Co.
105 A.2d 172 (Superior Court of Pennsylvania, 1954)
Scholler Bros. v. Otto A. C. Hagen Corp.
44 A.2d 321 (Superior Court of Pennsylvania, 1945)
Campbell v. Industrial Union of Marine & Shipbuilding Workers
52 Pa. D. & C. 597 (Delaware County Court of Common Pleas, 1944)
Seaboard Surety Co. v. Commonwealth
38 A.2d 58 (Supreme Court of Pennsylvania, 1944)
Rosenbaum v. Drucker
31 A.2d 117 (Supreme Court of Pennsylvania, 1943)
Seaboard Surety Co. v. Commonw'lth.
27 A.2d 27 (Supreme Court of Pennsylvania, 1942)
Britex Waste Co. v. Nathan Schwab & Sons, Inc.
12 A.2d 473 (Superior Court of Pennsylvania, 1939)
Canuso v. Philadelphia
192 A. 133 (Supreme Court of Pennsylvania, 1937)
Kaplan v. Bagrier
12 Pa. D. & C. 693 (Philadelphia County Court of Common Pleas, 1929)
Bashford v. West Miami Land Co.
145 A. 673 (Supreme Court of Pennsylvania, 1928)
Commonwealth v. Eastern Paving Co.
136 A. 853 (Supreme Court of Pennsylvania, 1927)
Commonwealth v. Eastern Paving Co.
8 Pa. D. & C. 357 (Dauphin County Court of Common Pleas, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
107 A. 636, 264 Pa. 111, 1919 Pa. LEXIS 603, Counsel Stack Legal Research, https://law.counselstack.com/opinion/curran-v-philadelphia-pa-1919.