Reynolds v. Caldwell

51 Pa. 298
CourtSupreme Court of Pennsylvania
DecidedFebruary 9, 1866
StatusPublished
Cited by9 cases

This text of 51 Pa. 298 (Reynolds v. Caldwell) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reynolds v. Caldwell, 51 Pa. 298 (Pa. 1866).

Opinion

The opinion of the court was delivered, by

Strong, J.

— This was an action of covenant brought by Caldwell against Leech to recover compensation for the graduation, masonry, and other work done on section 43 of the Allegheny Yalley Railroad. Leech with others had been contractors for the entire work of the line,* and Caldwell was a sub-contractor with them for the work on one section.

The articles of agreement fixed very precisely the mode in which alone the sums due from time to time to the sub-contractor should be ascertained. This it did by reference to the estimates that the railroad company had agreed with the primary contractors should be made as the work progressed. And it was stipulated that on or about the first day of each month during the progress of the work, the estimate made of the quantity and relative value of the work done on the section, by the engineer of the railroad company, should be conclusive between the parties to the agreement, of the amount of said work, and that within ten days after the procurement of a certificate of such estimate from the railroad company, the defendant should pay eighty-five per cent, of the amount of such estimate, agreeably to the contract prices. The agreement then went on to declare that when all the work should be completed there should be a final estimate made by the chief or associate engineer of the quality, character and value of said work, agreeably to the terms of the agreement, when the balance appearing due to the sub-contractors should be paid upon their giving a release. After some other provisions, the contract concluded with the following clause: — “ And it is mutually agreed and distinctly understood, that the decision of the chief engineer shall be final and conclusive in any dispute which may arise between the parties to this agreement, relative to or touching the same, and each and every of said parties do hereby waive any right of action, suit or suits, or other remedy in law or otherwise, by virtue of said covenants, so that the decision of said engineer shall, in the nature of an award, be final and conclusive on the rights and claims of said parties.”

In view of these covenants, irrespective of the stipulation last quoted, it is plain the plaintiff can recover for work done by him under the contract only after estimates made by the engineer of the railroad company. Those estimates, it was agreed, should determine the quantity of work done, and its value, or the sum due to the sub-contractor. It was those that the defendants [306]*306covenanted to pay, and nothing else. Had no provision been made for an arbitrament, and had there been no waiver of right to sue at law, it was still an essential prerequisite to any action for work done under the contract that estimates of it should be made. It was assumed by both parties that they Would be made, and they were. The amounts certified as due in those that were made monthly during the progress of the work, the plaintiff received, and he gave written acknowledgments of the payments, but he refused to accept the balance appearing to be due by the final estimate, alleging that it was erroneous both in the quantity and in the classification of the work. Doubts were suggested in the argument whether there was in fact a final estimate, such as was called for in the articles of agreement. That there was seems to us, however, very clear. It is needless to consider the question now. If there was not, it is certain the plaintiff has no such cause of action as he asserts. But assuming that there was a final estimate, that it was erroneous, and that the covenants of the defendants were broken, the great question of the case remains whether in view of the last clause in the contract any action at law could be maintained upon it. Provisions similar to this are often introduced into such contracts, and they have more than once been under consideration in this court. Even when much less stringent than the present, they have been held effective to preclude any resort to an action at law. In The Monongahela Navigation Company v. Fenlon, 4 W. & S. 205, the agreement to submit did not contain any express waiver of the right to sue at law for a breach of the contract. It only declared that in any dispute between the contractor and the company, the decision of the engineer should be obligatory and conclusive without further recourse or appeal, yet it was held that no action by one party against the other would lie for a breach of the agreement; that the only resort was to the appointed tribunal. To the same effect are Faunce v. Burke & Gronder, 4 Harris 480, and other cases more recently decided. The doctrine of these eases was apparently acknowledged as a general rule, by the learned judge of the court below, but he applied it with most important and erroneous exceptions. He instructed the jury that the plaintiff could not escape the binding force of the clause in the contract, unless recourse to the tribunal selected was rendered no longer reasonably possible by circumstances over which he had no control, and which he could not prevent by reasonable diligence on his part; that unless a reference was prevented by act of the defendant, or, secondly, by the refusal of the chief engineer to act on proper application made to him; or, thirdly, by such gross and palpable mistake as amounted to fraud, the plaintiff could not recover. Thus a wide door was opened enabling the plaintiff to escape from the stringent ■covenant into which he had entered, and by which he had bound [307]*307himself to waive any right of action, suit or suits, or other remedy at law, and to leave the decision of any dispute that might arise relative to or touching the agreement to the final determination of the engineer. So in the answer to the points presented by the defendants below, the same exceptions to the rule laid down in Navigation Company’ v. Eenlon were constantly asserted. In this we are of opinion there was error. It nowhere appears in the case, nor is it alleged, that a reference of any dispute between the parties to the chief engineer of the railroad company was prevented by the defendant. If it had been thus prevented, perhaps the plaintiff might have resorted to a court of law, notwithstanding his waiver of such a right. But the plaintiff rests upon the allegations that the engineers were guilty of fraud, or made gross mistakes in their estimates equivalent to fraud, and that it was impracticable to procure the chief engineer to decide the controversy respecting the accuracy of the estimates after it had arisen. The court recognised these things, if found to have existed, as relieving the plaintiff from his obligation to waive a suit at law. But what had the fraud of the engineers, if any, to do with the plaintiff’s covenants ? How could the misconduct of the chosen arbitrator deprive the defendants of a right secured to them by the contract — a right of exemption from liability to any suit upon it ? If the engineer undertook to act as umpire and fraudulently injured the plaintiff, he had a remedy by action against the guilty agent, but not by suit on the contract. He cannot punish the defendants for a fault of which they are innocent. And how could the mistake of the engineer alter the covenants of the parties ? By agreeing to refer to him they took the risk of his mistakes. They were both interested in having the estimate made as large as possible, and both were injured by an under-estimate, if one was made. It was in view of such contingencies, as the plaintiff alleges have happened, that the parties renounced their right to any other remedy against each other, than the arbitrament of the chief engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nestor v. George
46 A.2d 469 (Supreme Court of Pennsylvania, 1946)
Patriotic Order Sons of America Hall Ass'n v. Hartford Fire Insurance
157 A. 259 (Supreme Court of Pennsylvania, 1931)
Commonwealth v. Eastern Paving Co.
8 Pa. D. & C. 357 (Dauphin County Court of Common Pleas, 1926)
Southern Manufacturing Co. v. R. L. Moss Manufacturing Co.
13 Ga. App. 847 (Court of Appeals of Georgia, 1913)
Thaler Bros. v. Greisser Construction Co.
79 A. 147 (Supreme Court of Pennsylvania, 1911)
McNally v. Montour Railroad
33 Pa. Super. 51 (Superior Court of Pennsylvania, 1907)
Payne v. Roberts
64 A. 86 (Supreme Court of Pennsylvania, 1906)
Gowen v. Pierson
31 A. 83 (Supreme Court of Pennsylvania, 1895)
Brown v. Decker
21 A. 903 (Philadelphia County Court of Common Pleas, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
51 Pa. 298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reynolds-v-caldwell-pa-1866.