Payne v. Roberts

64 A. 86, 214 Pa. 568, 1906 Pa. LEXIS 699
CourtSupreme Court of Pennsylvania
DecidedApril 9, 1906
DocketAppeal, No. 241
StatusPublished
Cited by14 cases

This text of 64 A. 86 (Payne v. Roberts) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Payne v. Roberts, 64 A. 86, 214 Pa. 568, 1906 Pa. LEXIS 699 (Pa. 1906).

Opinion

Opinion by

Mr. Justice Stewart,

By written articles of agreement entered into June 1, 1902, George F. Payne & Company, here the appellees, undertook to construct and erect for Percival Roberts, Jr., the appellant, a dwelling house at Narberth, Penna., in accordance with certain plans and specifications made part of the agreement, to provide all the materials for the same, and perform the work in connection therewith in a good and workmanlike manner, under the direction of the architects, Peabody & Stearns, for the consideration of $247,000. The work under the contract was duly entered upon, and had so far progressed that the walls of the house were in the course of erection, some of them being as high as the second story, when the contractors were required by the owner to cease work and turn over to him the unfinished building, to be completed by his own workmen. The owner claimed the right to do this under the third clause in the contract, which reads as follows : “ In case of any failure or unreasonable delay of the said party of the second part, whether by act or default in the performance of any of the [575]*575above stipulations, or compliance with the true intent of these presents, not authorized in writing, by the said party of the first part, it shall be lawful for the said party of the first part, after ten days’ notice in writing to the said party of the second part, to provide other workmen and materials to complete the said work in the place of the said party of the second .part, and to deduct the costs and charges thereby occasioned from the sums otherwise becoming due the said party of the second part under this agreement, without prejudice to any other remedy which the said party of the first part may have for breach thereof.” The contractors, being thus required -to relinquish the work, brought this action against the owner to recover damages on account of an alleged breach of contract. In the statement of claim filed by the plaintiffs in the action, the breach complained of was thus averred: “ That after the execution of said agreement, to wit, on or about the 1st day of June, 1902, they entered upon the performance of their contract, began the construction of the said dwelling house at Narberth, Penna., referred to in said contract, and continued in the construction of the same until on or about the 20th day of February, 1903, when the defendant arbitrarily, wrongfully and illegally refused to permit the plaintiffs to proceed further with the construction of the said dwelling house and in the performance of their contract, although ready and willing so to do.” That the defendant did interfere and require the plaintiffs to cease and quit the work at the point of time alleged, is a fact in the case; whether he did so arbitrarily, wrongfully and illegally, is the question to be resolved. It was resolved by the jury under instructions from the court as to the law applicable to the case, and adversely to the defendant, against whom a verdict for $96,184.98 was returned, subsequently reduced by the court to $92,497.70. The appellant insists that the instructions of the court were erroneous, and that the jury were permitted to pass on questions not proper for their consideration.

With the frequent disputes which arose between owner and contractors as the work progressed, we have no concern. We may wholly dismiss them from consideration, since it was but a single act of the owner, and that the final one, requiring the contractors to give over the work, that is complained of as the [576]*576breach; and this if excusable or justifiable, was so because of the final act of the contractors in refusing to take down the walls which had been condemned by the architects. On January 21, 1908, the architects having made an examination of the work so far as then completed, reported in writing to the contractors, and verbally to the owner, that the work failed to comply with the specifications in five particulars. These particulars all relate to the'walls which had been erected, and while each might well be regarded as a matter of moment, it is unnecessary here to specify more than one. The third particular as stated in the report made special reference to the substitution of a different cement, in the exterior brick walls and interior walls containing limestone, for the particular cement' called for by the specifications. The report says: “ The use of the common cement in the walls renders them of very much less value than if the specifications had been complied with, and we cannot accept the work. It is impossible to remedy this without' taking down the walls which have been erected, and we therefore reject the walls so far as you have them finished, and require you to take them down under the clause of the contract which requires you to immediately remove any work or materials unsatisfactory to the architects.” The report concludes : “ Upon discovering to-day the serious condition of the work, we directed, through your representative, that all work should be stopped, and have notified the owner of the condition of affairs.” The clause of the contract to which reference is here made, is to be found in the first section and reads as follows : “ And in case any of said work done or materials provided by the said party of the second part shall be unsatisfactory to the said architects, then the said party of the second part will, on being notified thereof by the said architects, immediately remove such unsatisfactory work and materials, and supply the place thereof with other work and materials satisfactory to the said architects.” Acting upon this report of the architects the owner wrote to the contractors under date of January 22, 1903, as follows: “ I am also in receipt of copy of letter to you from Messrs. Peabody & Stearns under date of 1 /21 /03. From this it appears that the situation at Narberth has not improved but grown steadily worse. Notwithstanding notices given your Mr. Beehold by Mr. Stearns [577]*577to suspend work as same was not in accordance with specifications, I am informed that you are proceeding with the same to-day. I hereby notify you that owing to the unsatisfactory condition of affairs I will exercise my light in clause three of the contract and take possession of the work with my own men ten days from this date.” At the end of the ten days, the contractors being still in the possession of the building, and not having taken down the walls as required by the architects, but continuing to build thereon, counsel for the owner addressed to the contractors a written demand for a surrender of the premises. This not being complied with, on February 9, the owner filed his bill in equity praying among other things for an injunction restraining the contractors from proceeding further with the work. No answer was filed, but on representation to counsel for the contractors that the five day injunction would on the following day he asked for on the bill, the contractors withdrew from the building, protesting that they yielded only for the purpose of avoiding litigation, without admitting that the walls did not correspond to the specifications. We have here stated every material fact that is necessary for an understanding of this appeal. The case as tried in the court below would seem somewhat anomalous, inasmuch as the record shows an action successfully maintained for damages resulting from an alleged breach of contract, when the damages claimed and allowed resulted, not from any breach of the contract by the owner, but in consequence of his strict observance of the contract in pursuing a remedy therein provided, and in the way therein prescribed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boro Construction, Inc. v. Ridley School District
992 A.2d 208 (Commonwealth Court of Pennsylvania, 2010)
Appel Media, Inc. v. Clarion State College
327 A.2d 420 (Commonwealth Court of Pennsylvania, 1974)
John Conti Co., Inc. v. Donovan
57 A.2d 872 (Supreme Court of Pennsylvania, 1947)
Stierheim v. Bechtold Et Ux.
43 A.2d 916 (Superior Court of Pennsylvania, 1945)
Snyder v. Reading School District
166 A. 875 (Supreme Court of Pennsylvania, 1933)
Evans, Inc. v. School District of Township of Darby
164 A. 826 (Superior Court of Pennsylvania, 1932)
Callone v. Fisher
11 Pa. D. & C. 705 (Northampton County Court of Common Pleas, 1928)
Commonwealth v. Eastern Paving Co.
8 Pa. D. & C. 357 (Dauphin County Court of Common Pleas, 1926)
Fay v. Moore
65 Pa. Super. 615 (Superior Court of Pennsylvania, 1917)
Reilly v. Rodef Sholem Congregation
90 A. 345 (Supreme Court of Pennsylvania, 1914)
Stuart & Peterson Co. v. Newton
52 Pa. Super. 158 (Superior Court of Pennsylvania, 1912)
Thaler Bros. v. Greisser Construction Co.
79 A. 147 (Supreme Court of Pennsylvania, 1911)
Hunn v. Pennsylvania Institution for the Instruction of the Blind
70 A. 812 (Supreme Court of Pennsylvania, 1908)
Fay v. Lester Piano Co.
32 Pa. Super. 437 (Superior Court of Pennsylvania, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
64 A. 86, 214 Pa. 568, 1906 Pa. LEXIS 699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/payne-v-roberts-pa-1906.