Boro Construction, Inc. v. Ridley School District

992 A.2d 208, 2010 Pa. Commw. LEXIS 124, 2010 WL 759835
CourtCommonwealth Court of Pennsylvania
DecidedMarch 8, 2010
Docket16 C.D. 2009, No. 17 C.D. 2009
StatusPublished
Cited by22 cases

This text of 992 A.2d 208 (Boro Construction, Inc. v. Ridley School District) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boro Construction, Inc. v. Ridley School District, 992 A.2d 208, 2010 Pa. Commw. LEXIS 124, 2010 WL 759835 (Pa. Ct. App. 2010).

Opinion

OPINION BY

Senior Judge KELLEY.

Boro Construction, Inc. (Boro) and Rid-ley School District (District) have filed cross appeals from the orders entered in the Court of Common Pleas of Delaware County (trial court) denying their motions for post-trial relief and entering judgment in favor of the District and against Boro on the complaint, and in favor of Boro and against the District on the District’s counterclaims. We affirm.

On June 7, 1999, Boro and the District entered into contracts for general construction and electrical construction of a new high school building. See Reproduced Record (RR) at 836a-841a, 858a-863a. The sum due for completion under the General Construction Contract totaled $5,411,800.00, and the sum due for completion under the Electrical Contract totaled $4,599,000.00. Id. at 837a, 859a. Both contracts indicated that Boro would achieve substantial completion of the entire work under the contracts by August 15,2002. Id. 1

*211 On May 12, 2004, Boro filed a complaint the Court of Common Pleas of Montgomery County alleging that the District had breached the contracts by failing to *212 pay the final sums due under both the General Construction Contract and the Electrical Contract. In particular, Boro alleged that although the District had paid approximately $10,000,000.00 under the contracts, the District owed Boro the following additional sums: (1) a remaining balance due on the General Construction Contract totaling $44,237.06; (2) a remaining balance due on the Electrical Contract totaling $13,295.20; (3) approved change orders under the Electrical Contract totaling $6,444.60; (4) monies lost due to the improper disposal and use of dumpsters on site by other contractors totaling $64,-157.92 2 ; (5) damages for delay in completion of the project totaling $40,026.83 3 ; (6) costs for cellular telephone usage on site totaling $2,890.05 4 ; (7) costs for revising the building locator maps due to changes in the high school’s room numbers totaling $4,751.25; and (8) costs for the installation of theatrical wiring outside the scope of the contract work totaling $72,026.89. The case was transferred to the trial court at the District’s request.

On May 19, 2005, the District filed an answer to the complaint with new matter and counterclaims. In the counterclaims, *213 the District sought damages totaling $27,736.02 for the costs of reinstalling doors and door hardware that had been improperly installed by Boro. The District also sought credit change orders owed by Boro totaling $10,981.02. In addition, the District sought attorney fees pursuant to the “no damages for delay” clause of Section 8.3.4 of the Supplementary Conditions which provided that they could be recovered based on Boro’s claim for delay damages. See RR at 947a. 5

A non-jury trial was conducted before the trial court on July 5 through July 7, 2006. On November 6, 2006, the trial court entered a verdict in favor of the District and against Boro on the complaint, and in favor of Boro and against the District on the District’s counterclaims.

On May 24, 2007, the trial court issued orders denying the parties’ motions for post-trial relief. 6 Boro and the District then filed the instant appeal and cross- *214 appeal from the trial court’s orders. 7 , 8

The sole claim raised by Boro in its appeal is that the trial court erred in determining that it was not entitled to recover its claims for the remaining balances due under the General Construction Contract and the Electrical Contract because it failed to submit applications for final payment. In contrast, in its appeal, the District claims that the trial court erred in determining that the District was not entitled to attorney fees because they are specifically provided for in a “no damages for delay” clause of the contract.

Boro claims that the trial court erred in determining that it was not entitled to recover its claims for final payment due under the General Construction Contract or the Electrical Contract because it failed to submit applications for final payment. We do not agree. 9

With respect to Boro’s claim for final payment under the contracts, it is well settled that the fundamental rule in construing the provisions of a contract is to ascertain and to give effect to the intention of the parties. Empire Sanitary Landfill v. Riverside School District, 739 A.2d 651 (Pa.Cmwlth.1999). If the contract terms are clear and unambiguous, the intention of the parties must be ascertained from the document itself. Id. This Court’s inquiry should focus on what the agreement itself expressed, and not on what the parties may have silently intended. Id. It is not appropriate, under the guise of contract construction, to alter the terms to which the parties expressly agreed, whether in wisdom or folly. Id.

In addition, “[t]he public contract here is subject to the Procurement Code, specifically Chapter 39. 62 Pa.C.S. § 102(a); 3901-3942. Section 3931 entitles a contractor who performs in accordance with the contract to prompt payment by the government agency. 62 Pa.C.S. § 3931[ 10 ] *215 .... ” James Corporation v. North Allegheny School District, 938 A.2d 474, 488 (Pa.Cmwlth.2007) (footnote added). Nevertheless, Section 3932(a) of the Procurement Code provides, in pertinent part, that “[t]he government agency shall pay the contractor ... strictly in accordance with the contract.” 62 Pa.C.S. § 3932(a). 11

Moreover, as this Court has previously noted, a “condition precedent” may be defined as a condition that must occur before a duty to perform under a contract arises. Beaver Dam Outdoors Club v. Hazleton City Authority, 944 A.2d 97 (Pa.Cmwlth.2008). While the parties to a contract do not need to use any particular words to create a condition precedent, an event or act enumerated in a contract will not be construed as a condition precedent unless it clearly appears to have been the parties’ intention. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TALLEY v. SAVAGE
E.D. Pennsylvania, 2022
69-71 N. 2nd St. LLC v. Chancery Lane Partners
Superior Court of Pennsylvania, 2022
E. Stroudsburg Area S.D. v. Meadow Lake Plaza, LLC
Commonwealth Court of Pennsylvania, 2019
Marchwood Assoc. GP, LLC v. Downingtown Area SD
Commonwealth Court of Pennsylvania, 2019
Allegheny Intermediate Unit v. East Allegheny School District
203 A.3d 371 (Commonwealth Court of Pennsylvania, 2019)
Estate of: John Leslie Rupert
Superior Court of Pennsylvania, 2016
American Diabetes Ass'n v. Friskney Family Trust, LLC
177 F. Supp. 3d 855 (E.D. Pennsylvania, 2016)
John Spearly Construction, Inc. v. Penns Valley Area School District
121 A.3d 593 (Commonwealth Court of Pennsylvania, 2015)
East Coast Paving & Sealcoating, Inc. v. North Allegheny School District
111 A.3d 220 (Commonwealth Court of Pennsylvania, 2015)
Meir Gelley v. Park Pleasant Inc
494 F. App'x 187 (Third Circuit, 2012)
Roethlein v. PORTNOFF LAW ASSOCIATES, LTD.
25 A.3d 1274 (Commonwealth Court of Pennsylvania, 2011)
Victoria Gardens Condominium Ass'n. v. Kennett Tp. of Chester
23 A.3d 1098 (Commonwealth Court of Pennsylvania, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
992 A.2d 208, 2010 Pa. Commw. LEXIS 124, 2010 WL 759835, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boro-construction-inc-v-ridley-school-district-pacommwct-2010.