Southern Manufacturing Co. v. R. L. Moss Manufacturing Co.

81 S.E. 263, 13 Ga. App. 847
CourtCourt of Appeals of Georgia
DecidedJuly 1, 1913
Docket1905
StatusPublished
Cited by24 cases

This text of 81 S.E. 263 (Southern Manufacturing Co. v. R. L. Moss Manufacturing Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Manufacturing Co. v. R. L. Moss Manufacturing Co., 81 S.E. 263, 13 Ga. App. 847 (Ga. Ct. App. 1913).

Opinion

Russell, J.

In this ease the statutory lien of a builder and materialman was foreclosed upon the real estate of the opposite party to a written building contract in which it was stipulated that the decision of all questions as to the completion of the contract, as well as the builder’s compliance with the specifications, should be submitted to engineers as agents of both the contracting parties. Since we are of the opinion that the nature of the plaintiff’s action could not be disregarded, nor a new contract be substituted for that entered into by the parties, and which was necessarily the foundation of the action sub judice, and that therefore the lower court should have disposed of the ■ case upon the defendant’s motion, it is unnecessary to refer to the contentions of the defendant as set forth in its answer, and we shall state only the case as made by the plaintiff in the petition, with the amendments [849]*849allowed by the court, and the defendant’s objections to the proceeding. ■ ■' '

The R. L. Moss Manufacturing Company, a corporation, brought' suit in the city court of Athens, against the Southern Manufactur-' ing Company, to foreclose a builder’s lien for a balance alleged to-be due the plaintiff for building 25 operatives’ houses- for the' Southern Manufacturing Company, which the petition alleged were built under a written contract between the parties, according to' plans and specifications referred to in the contract. The petition alleged, that the plaintiff complied with the terms of its contract and built the houses as it had contracted to do; that as the work progressed the defendant paid the plaintiff sums aggregating $12,725, but failed and refused to pay the balance due on said written contract, and that the defendant was liable for an additional sum of $721.75 for extra material and work and insurance on three houses, as set forth in the declaration. It was further alleged that the plaintiff filed and recorded its contractor’s lien within three months after the completion of the contract, as required' by law. ‘

The written contract which was the basis of the suit was not attached to the petition, and the defendant demurred to the petition, as follows: To the second paragraph (which alleged the written contract for the building of the 25 .houses according to the plans and specifications which were a part of 'the said contract),upon the ground that the written contract and the plans and specifications were not set out, either by copy or in substance, an'd that the second paragraph is vague and uncertain by reason of the: fact that it does not disclose what are- the terms and conditions either of the contract or of the plans and specifications. ' For the same reasons the defendant demurred also to paragraphs 3, 4, .5,- and 6- of the petition. Pending 'a ruling upon the demurrer the plaintiff, by way of amendment, attached a copy of the original contract and of the plans and specifications, and offered another amendment, setting up that during the progress of the work the engineers in charge under the contract were frequently upon the ground where the work was in progress, and that no objection, verbal or in writing, was ever made by them to any of the material placed in said houses, or to any of the workmanship done on them, although the petitioners repeatedly requested said engineers to in[850]*850spect the work as it progressed and to point out to the petitioner anything objectionable in the material or workmanship^ and that the engineers failed to inspect or point out defects; that when some of the houses were completed and the petitioner urged the engineers to inspect them and give to the petitioner a certificate for payment, the engineers declined (as averred by the plaintiff), solely because the defendant did not have any money and did not wish them inspected and a certificate given; that the petitioner called the attention of the engineers to that item of the specifications which called for a second coat of plastering, to be put on in accordance with the directions of the manufacturers and to be floated down to a sand finish, and that the manufacturers said that on lath work the plastering must not be floated, and that some of the plasterers were floating it and some troweling it, and requested the engineers to direct how the plastering should be put on, and the engineers failed and refused to give any direction as to how the plastering should be put on; that one of the engineers was taken into one of the houses and shown the plastering, after it was completed, and inspected it and made no objection; that this inspection was made before the plastering in any of the other houses was completed, and no objection was made to the plastering, or direction given; that the engineers frequently passed by the houses while they were in course of construction and saw the material and workmanship, and made no objection to either; that when the work was in process of construction the petitioner repeatedly urged the engineers and the defendant to inspect thé same and point out any defects in material and workmanship; that the defendant’s authorized agents were often on the ground where said houses were being erected, at all periods of the work, and were urged to have the engineers point out any defects, and that they failed and refused to do so, but permitted petitioner to proceed with the construction of the said houses to completion, and until it was practically impossible to remedy any defects in material or workmanship, if any existed. The amendment, further alleged that when the houses were completed and tendered to the defendant, the defendant refused to pay the contract price, upon the ground that they were not up to the contract, and offered to arbitrate the differences between petitioner and defendant. It was further alleged that the defendant did not at any time demand [851]*851that the petitioner get a certificate from the engineers, and did not at any time refuse to pay the contract price because the certificate was not obtained, but based its refusal to pay entirely upon the ground that the houses were not built according to specifications; that the petitioner urged the defendant and the engineers to. point out any defects in material or workmanship in said houses, and both refused to do so, declaring that the petitioner and the defendant must get together and make such adjustment of the matter as they could. In fine, the amendment to the petition alleged that, by reason of the defendant’s conduct as therein set forth, it had waived its right to have the engineer’s certificate produced, under the terms of the contract, as a prerequisite to payment of the amount due according to the contract, and that the defendant was estopped from denying that the work was done and the material furnished according to contract.

The defendant moved the court to disallow and strike the amendment, on the following grounds: “Because the terms of the contract which by amendment had been made a part of plaintiff’s petition, and was the foundation of the suit, showed on its face and provided in substance that the contractor should provide all materials and perform all work for the complete construction of the buildings referred to, as shown on the drawings and described in the specifications prepared by Miles & Bradt Company, the engineers; that it was understood and agreed by and between the.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ebony Smoot v. State
Court of Appeals of Georgia, 2012
M.C. Anderson v. Golden
569 F. Supp. 122 (S.D. Georgia, 1982)
Starling, Inc. v. Housing Authority
293 S.E.2d 392 (Court of Appeals of Georgia, 1982)
Thornton v. Davis
293 S.E.2d 1 (Court of Appeals of Georgia, 1982)
Gellis v. B. L. I. Construction Co.
251 S.E.2d 800 (Court of Appeals of Georgia, 1978)
I. Perlis & Sons v. Peacock Construction Co.
152 S.E.2d 390 (Supreme Court of Georgia, 1966)
College Park Builders, Inc. v. Uplands Construction Corp.
127 S.E.2d 812 (Court of Appeals of Georgia, 1962)
Rainbow Realty Corp. v. Porter
121 S.E.2d 791 (Court of Appeals of Georgia, 1961)
Finn v. Carden
110 S.E.2d 693 (Court of Appeals of Georgia, 1959)
Nutting v. Wilson
42 S.E.2d 575 (Court of Appeals of Georgia, 1947)
Meeks v. Adams Louisiana Co.
49 F. Supp. 489 (S.D. Georgia, 1943)
Smith v. Hanna Manufacturing Co.
23 S.E.2d 552 (Court of Appeals of Georgia, 1942)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
Sovereign Camp Woodmen of the World v. Heflin
200 S.E. 489 (Court of Appeals of Georgia, 1938)
United States Building & Loan Ass'n v. France
70 P.2d 374 (Idaho Supreme Court, 1937)
American National Insurance v. Parker
190 S.E. 427 (Court of Appeals of Georgia, 1937)
Life & Casualty Insurance v. Carter
191 S.E. 153 (Court of Appeals of Georgia, 1937)
Cox v. Bailey
180 S.E. 494 (Court of Appeals of Georgia, 1935)
Ross & Williams v. Southern Exchange Bank
144 S.E. 338 (Court of Appeals of Georgia, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
81 S.E. 263, 13 Ga. App. 847, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-manufacturing-co-v-r-l-moss-manufacturing-co-gactapp-1913.