Boettler v. Tendick

5 L.R.A. 270, 11 S.W. 497, 73 Tex. 488, 1889 Tex. LEXIS 1223
CourtTexas Supreme Court
DecidedApril 12, 1889
DocketNo. 6171
StatusPublished
Cited by48 cases

This text of 5 L.R.A. 270 (Boettler v. Tendick) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boettler v. Tendick, 5 L.R.A. 270, 11 S.W. 497, 73 Tex. 488, 1889 Tex. LEXIS 1223 (Tex. 1889).

Opinion

Stayton, Chief Justice.—

Appellant constructed a stone building for appellee under a contract which contained full specifications of the work to be done and of the character of the material to be used, all of which was to be furnished by the appellant.

The plans and specifications were prepared by architects in the employment of appellee, and the contract contains the following agreement.-

"Sixth. It is furthermore agreed between the contracting parties-, hereto that the said Wahrenberger & Beckmann are the architects under whose supervision, directions, and control the said materials are to be-furnished and the said labor to be performed as mentioned in said plans and specifications and details, and in all cases of difference or dispute as to the character of the labor performed by the said party of the second part, or as to the meaning and intent of said specifications, plans,, and details, or as to any word, term, or phrase therein employed, the same is to be referred for decision to said Wahrenberger & Beckmann,, their decision to be final, neither party having the right to appeal therefrom.”

The house was constructed under the supervision of the architects-named.

The sum to be paid for the entire building was $3500, which was to be» paid as follows: "Eighty per cent of the amount due for said work, from time to time as the condition of the work in the opinion of the» architects will justify, said amounts to be paid upon the certified estimates of said architects that so much is due upon said work; the remaining twenty per cent of the difference in the aggregate payments so made-as aforesaid and the said sum of three thousand five hundred dollars to-be paid upon the final completion of the said building and the acceptance of the same by the party of the first part through his architects.”

At the end of each week while the work progressed the architects gave certificates on which payments were .made as provided by the contract,, [491]*491and on the completion of the house it was received by the- architects, who> gave a certificate on which the final payment was made.

Some time after the house had been received the walls cracked, and appellee demanded that appellant should then make all necessary repairs-at his own cost, which he refused to do. Appellant having executed a bond with surety for the proper execution of the work, appellee brought suit on that bond, after having caused repairs to be made at his own expense, to recover the sum of $1426.45 as damages for failure of appellant to construct the house in accordance with the contract, and recovered a judgment for $326.45.

The contract was made a part of the petition. The petition did not allege wherein appellee had failed to do the work in a workmanlike manner as required by the contract, nor did it allege wherein appellant had failed to use such material as was called for in the contract, but- did allege that it was discovered after the building was received “that said foundation was not built and constructed in a thorough and workmanlike manner, nor was the material used therein in accordance with the specifications in said contract,” and “that during the progress of repairs other defects were discovered in the said building, caused by bad workmanship and faulty material used by said defendant in the construction of the said building;” and further, “that owing to the bad workmanship and faulty material used by defendant in the construction of said house the front walls and other portions thereof are permanently damaged.”

The defendant filed a special exception to the petition, which questioned its sufficiency, in that it did not specify wherein the workmanship and materials used were not in accordance with the contract.

This exception was overruled and this ruling is assigned as error.

The averments of the petition are but the conclusions of the pleader,, and did not inform the defendant what particular facts would be relied upon to fix liability upon him.

While the petition may have been sufficient, even on general demurrer it was the right of the defendant to be informed wherein his workmanship was faulty or the material furnished by him not such as his-contract required, and when by specific exception he pointed out the want of more specific averments, and sought further information as to. the very facts on which the plaintiff relied for a recovery, he should not have been forced to go to trial until this information was given. The special exceptions should have been sustained.

The petition was further excepted to on the ground that it did not allege that any question of defective workmanship or material was at any time submitted to and decided by the architects, in accordance with the-terms of the contract, and that exception was overruled.

The petition was silent as to whether the architects had supervised the-[492]*492work while the house was in course of construction, and also as to whether the architects had given certificates as to the work as it progressed, or as to whether they had given a certificate on which the final payment was made and the house accepted.

All these facts, however, the answer alleged to have occurred, and if the petition in this respect was defective the issue which the defendant desired to raise was presented and the ruling of the court on the exception became unimportant.

Many witnesses were called by the plaintiff, to whom he propounded the general question whether the work was done in a workmanlike manner or not.

The answers were objected to on the ground that “the contract sued upon provides that all differences as to the quality of material or workmanship used in the construction of said building must be submitted to the .supervising architects, Wahrenberger & Beckmann, for decision, neither party having the right to appeal therefrom, and the pleadings do not •charge that said supervising architects had rendered any decision thereon by fraud, collusion, or mistake, through gross neglect, or in bad faith,” .and the court overruled the objections. The admission of this evidence is assigned as error.

The petition contained no averment that the supervising architects in passing on the work and material or in accepting the work had acted fraudulently, collusively, through mistake, gross neglect, or in bad faith, nor was there any averment that appellant had in any manner concealed •either bad workmanship or material.

Another assignment of error is as follows: “The court erred in rendering judgment for the plaintiff, because the evidence shows that the work done and material furnished by the defendant Boettler in the construction of plaintiff’s house were inspected and examined from time to time during the construction of said house by the superintending ar•chitects, Wahrenberger & Beckmann, and by them decided and received as having been done in accordance with the contract for said building, their decision under said contract being final, and no appeal being permitted "therefrom by either party, judgment should have been for defendants.”

As the judgment will be reversed on a ground already noticed, on the last two assignments we will state, without considering them separately, what we understand the law arising on the contract to be.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Transamerica Insurance Co. v. Housing Authority of Victoria
669 S.W.2d 818 (Court of Appeals of Texas, 1984)
Lebco, Inc. v. MacGregor Park National Bank of Houston
500 S.W.2d 698 (Court of Appeals of Texas, 1973)
City of Midland v. Waller
430 S.W.2d 473 (Texas Supreme Court, 1968)
Cantrell v. Woodhill Enterprises, Inc.
160 S.E.2d 476 (Supreme Court of North Carolina, 1968)
Hooks v. Cook
345 S.W.2d 592 (Court of Appeals of Texas, 1961)
Hines v. Farr
111 S.E.2d 33 (Supreme Court of South Carolina, 1960)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
White v. Dozier Const. Co.
70 S.W.2d 240 (Court of Appeals of Texas, 1934)
Stehlick v. Dozier Const. Co.
68 S.W.2d 284 (Court of Appeals of Texas, 1934)
Wengenroth v. Agold
27 S.W.2d 294 (Court of Appeals of Texas, 1930)
Brammer Wilder v. Limeston County
24 S.W.2d 99 (Court of Appeals of Texas, 1929)
Lennox v. Texas Farm Bureau Cotton Ass'n
16 S.W.2d 413 (Court of Appeals of Texas, 1929)
Southern Surety Co. v. Sealy Independent School Dist.
10 S.W.2d 786 (Court of Appeals of Texas, 1928)
Head v. Scurr
8 S.W.2d 819 (Court of Appeals of Texas, 1928)
Alexander v. Good Marble & Tile Co.
4 S.W.2d 636 (Court of Appeals of Texas, 1928)
Totten v. Houghton
2 S.W.2d 530 (Court of Appeals of Texas, 1927)
Wittliff v. Pierce
291 S.W. 916 (Court of Appeals of Texas, 1927)
Blum Milling Co. v. Moore-Seaver Grain Co.
277 S.W. 78 (Texas Commission of Appeals, 1925)
Craven v. Davison
276 S.W. 193 (Texas Commission of Appeals, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
5 L.R.A. 270, 11 S.W. 497, 73 Tex. 488, 1889 Tex. LEXIS 1223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boettler-v-tendick-tex-1889.