Lebco, Inc. v. MacGregor Park National Bank of Houston

500 S.W.2d 698, 1973 Tex. App. LEXIS 2620
CourtCourt of Appeals of Texas
DecidedSeptember 19, 1973
Docket810
StatusPublished

This text of 500 S.W.2d 698 (Lebco, Inc. v. MacGregor Park National Bank of Houston) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lebco, Inc. v. MacGregor Park National Bank of Houston, 500 S.W.2d 698, 1973 Tex. App. LEXIS 2620 (Tex. Ct. App. 1973).

Opinion

CURTISS BROWN, Justice.

This case involves an action and a cross-action on a construction contract.

Lebco, Inc. (Lebco) brought suit on a contract for the construction of a bank building and parking lot against Mac-Gregor Park National Bank of Houston (the Bank). Thé Bank brought a cross-action on the contract warranties for the costs of replacing the entire parking lot *699 (less expenses for the addition of lime which was not called for in the original specifications), the attendant expense of hiring traffic officers, and interest on such sums. Transamerica Insurance Company (Transamerica), surety for Lebco on its construction bond, was joined as a third party defendant.

The case was tried to the court. It entered a judgment in favor of Lebco for the $12,923.73 with interest (being funds retained. by the Bank to protect it against certain possible lien claims) and judgment in favor of the Bank against Lebco and Transamerica for $29,153.50 (which represents repairs of $33,311 less $6,500 for lime work plus $2,342.50 for the traffic control officers) with interest. Appropriate findings of fact and conclusions of law were made in support of the judgment.

Lebco and Transamerica have duly perfected this appeal.

Appellants’ basic contentions are twofold. First, they contend that the trial court erred in finding and concluding that a letter agreement of September 16, 1969, did not amend the contract so as to modify the scope of the guarantee relative to the parking lot. Second, they contend that the Bank failed to establish liability on its cross-action because the approval of the Bank’s architect to the corrective work was essential to recovery, but not obtained.

The construction contract related to the Bank’s new building and parking lot. The facilities were constructed by Lebco and the Bank opened for business in its new quarters on May 25, 1969. The Bank seems to have been entirely pleased with the work of the contractor with respect to the building itself. This suit originated in problems arising out of the parking lot. Shortly following the opening, difficulties began to develop in the parking area. Ruts formed in the drive-in lanes in front of the windows. After a time pavement wrinkled at the edges where cars parked on the lot. Cracks formed and water seepage of unknown origin appeared.

The Bank requested laboratory tests to determine whether the lot met the specifications of the contract. A report by TriWestern Testing Laboratories dated May 31, 1969, showed that the parking lot failed to meet specifications in several material respects. First, the middle layer of the three layers composing the parking lot was not of sufficient thickness. In many areas there were substantial variances from the 6" specifications. Second, the moisture content of the limestone in many areas was too high. Third, the compaction specifications for the middle layer were not satisfied in several locations on the lot. Lebco has never disputed that the lot as completed did not meet contract specifications.

The contract contains the following provision :

“4.5 WARRANTY AND GUARANTEE
4.5.1 The Contractor warrants and guarantees to the Owner and the Architect that all materials and equipment incorporated in the Project will be new unless otherwise specified, and that all Work will be of good quality, free from faults and defects and in conformance with the Contract Documents. All Work not so conforming to these standards may be considered defective by the Owner or the Architect. If required by the Architect, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment.
4.5.2 The warranties and guarantees provided in this Paragraph 4.5 and elsewhere in the Contract Documents shall be in addition to and not in limitation of any other warranty or guarantee or remedy required by law or by the Contract Documents.”

In addition to the general conditions the parties entered into an additional paragraph to the contract which was typed. Most of the contract was printed.

The typewritten provision is labeled “Article 9” and reads as follows:

“ARTICLE 9
The warranties and guaranties provided in this paragraph shall be in addition to *700 and not in limitation of any other warranty or remedy required by law or by the contract documents.
Contractor unconditionally guarantees all labor, materials and equipment furnished and all work performed against any and all defects in workmanship and materials for a period of one year from the date of final payment; and Contractor agrees to promptly correct and replace any such defective workmanship, materials and equipment, and further agrees to pay for any injury or damage to other work resulting therefrom, if such injury or damage is discovered within the one year guaranty period. This guaranty shall not be affected by acceptance, possession or use by Owner of any work done or performed by Owner. Owner agrees to give Contractor written notice of such defect with reasonable promptness; if Contractor fails within 15 days after receipt of any such notice to begin the correction of any such specified defects, or if Contractor fails to prosecute such work with no interruption, Owner may, at Owner’s option, proceed with the correction of such defects and any such injury or damage at the expense of Contractor who shall repay to Owner the reasonable cost thereof on demand. This paragraph replaces and is substituted for paragraph 13.2.2 of Article 13 of the General Condition.”

Complaints of the Bank relative to the lot caused Lebco to undertake repairs on several occasions during the summer of 1969. Lebco remedied the drive-in lanes by installing cement stabilizing shell. It also installed such shell in an area where certain trash trucks operated. This latter work was apparently done at the expense of the Bank because of the unusual use of the area.

Despite these efforts satisfactory results were not obtained and in early September of 1969 representatives of the parties met on the parking lot to discuss and attempt to resolve the problems presented. As a result of that meeting the parties signed an agreement reduced to writing in a letter prepared by the Bank’s attorneys and addressed to Lebco dated September 16, 1969. 1

*702 The September 9, 1969, agreement, which is referred to in the letter of September 16, 1969, recites :

“The contractor shall make the repairs to the paving as shown on this sheet. When these repairs meet the approval of the architect the contractor shall give the entire flexible base topping one coat of “jennite” seal coat according to the manufacturer’s specifications. When the “jennite” seal coat meets the approval of the architect the paving shall be re-stripped as it was when the bank opened. When the above conditions have been met the flexible base will be accepted as meeting the requirements of the plans and specifications.”

The work as set out in the letter agreement was performed satisfactorily by Leb-co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McMahon v. Christmann
303 S.W.2d 341 (Texas Supreme Court, 1957)
City of San Antonio v. McKenzie Construction Co.
150 S.W.2d 989 (Texas Supreme Court, 1941)
Boettler v. Tendick
5 L.R.A. 270 (Texas Supreme Court, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
500 S.W.2d 698, 1973 Tex. App. LEXIS 2620, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lebco-inc-v-macgregor-park-national-bank-of-houston-texapp-1973.