Southern Surety Co. v. Sealy Independent School Dist.

10 S.W.2d 786
CourtCourt of Appeals of Texas
DecidedOctober 17, 1928
DocketNo. 7222.
StatusPublished
Cited by15 cases

This text of 10 S.W.2d 786 (Southern Surety Co. v. Sealy Independent School Dist.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Surety Co. v. Sealy Independent School Dist., 10 S.W.2d 786 (Tex. Ct. App. 1928).

Opinion

McCLENDON, C. J.

Suit by Southern Surety Company (1) against Sealy independent school district for balance of $12,267.45 on a school building contract; (2) against the trustees of the district for wrongfully diverting $6,200 from the district building fund; and (3) against Sealy National Bank for wrongfully appropriating such diverted fund. The school district reconvened for $35,000, alleging breach of the building contract by the surety company and Wertz, the original contractor. Trial to court without a jury, and judgment- denying the surety company any recovery and awarding a found net balance in favor of the district on its cross-action against the surety company. The latter has appealed.

The record is unusually and .quite unnecessarily large, and the briefs, especially that of appellant, are of like character. The questions involved, while in some respects presenting difficulty, are in the main ruled by adjudicated cases. An outline statement of the uncontroverted facts will, we believe, facilitate a clear understanding of the questions the appeal presents.

On July 10, 1922, the school district contracted with Wertz for the construction according to plans and specifications made by Finn, the architect, of a two-story brick school building. The contract price was $40,-900, subject to additions and deductions, and payments were to be made monthly if requested to the amount of 85 per cent, of labor and material furnished, upon certificates of the architect. The contract authorized the withholding of certificates by the architect for the protection of unpaid laborers, materialmen, and the surety. At the same time the Southern Surety Company executed a bond in the penal sum of $20,000, assuring the faithful performance of the contract and the payment by Wertz of all labor and material bills. This bond was expressly made for the benefit, not only of the school district, but for such laborers and materialmen. In the application for this bond, Wertz assigned to the surety company all sums to become due under the contract. Wertz began and prosecuted the erection of the building; and three estimates were certified by the architect and paid by the district, aggregating $20,478.36. On November 14,1922, Wertz presented an estimate of some $8,500, for which the architect declined to issue a certificate, because unpaid bills of materialmen had been filed with him, and he demanded that Wertz satisfy these claims as a condition precedent to issuing the certificate. On November 17, 1922, Wertz abandoned the work, and on November 22, 1922, the architect addressed a letter to him at his last-known address, notifying him that the surety would be called *788 on to complete the building. Copy oí this notice whs sent the surety company, and formal demand made on it to complete the building. On November 24, Í922, the surety company acknowledged this notice and in writing agreed to complete the building, assuming all unpaid labor and material bills that were a proper charge against it as surety, and making formal claim for all sums due or to become due under the contract. At that time extras had been allowed by the architect to the amount of $75. The surety company employed a contractor on a cost plus basis; the work proceeded to completion; and on March 8, 1923, the surety, company téndered the building to the architect for the district as completed. In the meantime $8,500 had been paid to the surety company on architect’s estimate, and on January 26, 1923, the architect had issued a certificate in favor of Wertz for $6,200, upon which a warrant was drawn by the district and delivered to the bank. The latter, which was also the treasurer of the district, transferred the amount from the district building fund to the personal account of Wertz, and applied it on notes which Wertz owed it for advances made to satisfy his pay rolls. On March 9, 1923, the architect in writing accepted the building on behalf of the trustees of the, district, “as being substantially and satisfactorily completed according to plans and specifications agreed upon by the board of trustees and 0. Frost Wertz, as contractor.” The instrument, however, stated that, while the improvements were accepted as substantially completed according to plans and specifications, “the same cannot be accepted as being completed, according to the terms and provisions of the contract * * * until satisfactory evidence is made to us that all claims for labor and material against the improvements, incurred by Wertz, or by you as his successor and surety, have been paid in full.” This evidence was later furnished and the final payment demanded. Shortly after March 9, 1923, the district went into possession and continued using the building. A little later it was discovered that the walls leaked very badly, and further payment was declined.

Appellant’s brief presents 58 assignments of error, briefed under 32 propositions. The court’s findings of fact are questioned in every conceivable manner. Several propositions relate to the question of substantial performance. These become immaterial in the view we take of the case, and will therefore not be discussed. The contention embodied in the remaining propositions will be considered under the following eight general subjects:

(1) The necessity of making Wertz a party, and incidentally the imputation- of his fraud to the surety company.

(2) The finality and binding effect of the architect’s acceptance, both contractually and by way of estoppel.

(3) The sufficiency of the pleading to avoid the acceptance;- .

(4) The effect of limitation on the school district’s cross-action.

(5) The sufficiency of the evidence both as a matter of law and as to its preponderating effect to establish (1) fraud of the surety company or contractor that would avoid the acceptance; and (2) breach of the contract in the several respects found by the court.

(6) The measure of damages applied by the court to the cross-action.

(7) Sufficiency of the evidence to sustain the $6,200 payment to Wertz, and its appropriation by the bank.

(8) Amount of the unpaid balance due under the contract, including allowed extras.

The judgment is assailed as fundamentally erroneous, because Wertz was not made a party to the cross-action against the surety company, the pleadings not alleging facts which would authorize suit against the surety without joining the principal. R. S. 1925, art. 1987. This contention is overruled because it appears affirmatively from the pleadings of both parties, as well as ’from the undisputed evidence that after Wertz defaulted the surety company assumed all his liabilities then incurred, and obligated itself to complete the contract, claiming all sums thereunder, then or thereafter to become due. In so far as the relations between the surety company and the district are concerned, the former ceased to be a surety for Wertz, but became the original contractor and liable primarily to the district. The cross-action was therefore maintainable in its entirety against the surety company as an original and primary obligee. The following decisions in principle support this holding: American Bonding Co. v. Regents of University of Idaho, 11 Idaho, 163, 81 P. 604; Watterson v. Canal Co., 25 Cal. App. 247, 143 P. 90; State v. Cornwall, 102 Or. 220, 201 P. 1072; Particularly do we direct attention to the paragraph at the bottom of page 610 and top of page 611, and the last sentence of first paragraph on page 612, of case in 81 P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peek v. Equipment Service Co. of San Antonio
779 S.W.2d 802 (Texas Supreme Court, 1989)
Carter v. Quick
563 S.W.2d 461 (Supreme Court of Arkansas, 1978)
Barrientos v. Government of Capital
97 P.R. 539 (Supreme Court of Puerto Rico, 1969)
Barrientos v. Gobierno de la Capital
97 P.R. Dec. 552 (Supreme Court of Puerto Rico, 1969)
McQuagge v. United States
197 F. Supp. 460 (W.D. Louisiana, 1961)
Ketchey v. West
326 S.W.2d 40 (Court of Appeals of Texas, 1959)
Ruebeck v. Hunt
171 S.W.2d 895 (Court of Appeals of Texas, 1943)
American Nat. Ins. Co. v. Nicholson
119 S.W.2d 128 (Court of Appeals of Texas, 1938)
Grand Lodge Free & Accepted Masons of Texas v. Walker
110 S.W.2d 945 (Court of Appeals of Texas, 1937)
Verschoyle v. Holifield
90 S.W.2d 907 (Court of Appeals of Texas, 1935)
Thurber Const. Co. v. Kemplin
81 S.W.2d 103 (Court of Appeals of Texas, 1935)
White v. Dozier Const. Co.
70 S.W.2d 240 (Court of Appeals of Texas, 1934)
Stehlick v. Dozier Const. Co.
68 S.W.2d 284 (Court of Appeals of Texas, 1934)
Leifeste v. Stokes
45 S.W.2d 1006 (Court of Appeals of Texas, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
10 S.W.2d 786, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-surety-co-v-sealy-independent-school-dist-texapp-1928.