BAUGH, Justice. •

This suit involves the proper distribution of funds retained by the state highway commission under a contract dated April 23,1931, by it with D. H. Purvis & Son, for the construction of state highway No. 5, from Gaines-ville, Tex., to the Grayson county line. Purvis & Son subcontracted the construction of said project to Abe Anderson & Son, who in turn subcontracted same to L. G. Owen and’D. H. Seigler. In October, 1931, after the work contracted for had been about 75 per cent, completed, these parties became unable to continue said work, and Purvis & Son forfeited said subcontracts except as to D. H. Seigler, who had not defaulted; and on November 25, 1931, entered into the following contract with appellant, Thurber Construction Company:

“State of Texas, County of Tarrant.
“Know All Men by These Presents:
“That, we D. H. Purvis & Son, of Fort Worth, Texas, herein called First Party, and Thurber Construction Company, a corporation, also of Fort Worth, Texas, herein called Second Party, have this day entered into the following contract and agreement, to-wit:
“1. First Party, as general contractor under the State of Texas, agrees to sublet to Second Party, as subcontractor, all unfinished work, except as noted below in paragraph No. 2, on Job S. P. No. 477-D and Job F. A. P. No. 539-D, in Cook County, Texas, as represented by original contracts from the State Highway Department of the State of Texas to D. H. Purvis & Son, dated the 23rd of April, A. D. 1931, to which original contracts reference is hereby made and the same are adopted as representing the conditions, terms and specifications between the parties hereto for the completion of the unfinished work by Second Party, except as to the time limit contained therein.
“2. Second Party agrees to complete all unfinished work and furnish all labor and material incident thereto, except, that portion of the said work heretofore sublet by Abe Anderson & Sons to Dave Seigler, and which portion of said work the said Seigler is now actually in process of coinpletion. Said Seig-ler is not to be disturbed in his subcontract by the Second Party, but is to be permitted to complete the same in accordance with his subcontract under the said Abe Anderson & Sons.
“3. The said Second Party agrees to commence the work hereunder on or before the 30th day of November, A. D., 1931, and complete the same in accordance with the specifications therefor within sixty (60) working days.
. “4. The Second Party shall receive as its compensation for the work done and material furnished hereunder in the completion of the said work', the same prices which the said contracts between the State Highway Department and the said Purvis specifies to be paid to the said Purvis by the said Highway Department, provided, however, that should said Second Party’s cost exceed the final amount to be received under State Highway Department’s final estimate, then said First Party shall pay to the Second Party such amount as will reimburse it for its actual costs, such excess not to exceed fifteen per cent (15%) of total amount earned as shown by final estimate of State Highway Department. Payment is to be made to Second Party within sixty (60) days after the completion and acceptance by State Highway Department of said work.
[106]*106“5. The said First Party guarantees the payment of amounts payable to said Second Party hereunder and agrees to indemnify said Second Party for any claims filed covering labor, material, equipment purchases and rentals, and for any damage or anticipated profits on the part of any prior contractor or his subcontractor on said work, and against loss from delay due to any court proceedings instituted by or against First Party in reference to former sub-contracts on said work, and will furnish Second Party a good and solvent surety company bond guaranteeing the performance of this contract by First Party.
“Witness our hands, at Fort Worth, Texas, this the 25th day of November, A. D. 1931.” . Thurber Construction Company fully performed its contract at its own expense, and the completed highway was accepted by the highway commission on August 2, 1932. Numerous claims were filed with the highway 'commission by those furnishing labor, materials, etc., to subcontractors Anderson & Son, and to h. G. Owen, for which they had not been paid, and by D. H. Seigler, who had fully performed his subcontract. All of these claims,' except perhaps a part of that of 'Seigler,' had accrued to the claimants prior ■to the date of said contract made with appellant to complete the unfinished portion of said project, and represented labor and materials furnished to the subcontractors who had defaulted prior to November 25, 1931.

This suit was by said claimants either as plaintiffs or as interveners, some 77 in number, against Purvis & Son, Abe Anderson & Son, L. G. Owen, and the highway commission, to establish their Glaims, and have same de'clared a' lien upon and paid out of the funds retained by the highway commission under itó cohtráct with Purvis & Son, and under the provisions of articles 5472a'and 6674m, Vernon’s' Ann. Giv. St. The highway commissioner'answered that it had funds retained ,by it in the sum of $15,016.53, which it tendered ‘ into the registry of the court to be paid out as the court should determine.

. Appellant intervened, set up its contract ,of November 25,1931, above quoted, alleged its complete performance thereof at an expense to it for labor, materials, etc., of $15,003.63, none of which amount had been paid to it by Purvis & Son; that its claim was for labor, materials, etc., furnished by it as subcontractor in the performance of its contract with Purvis & Son; and sought to have its claim adjudged to be prior to those of the other .claimants and to be paid first out of the funds retained by the-highway commission.

The case was tried to the court without a-jury. Judgment was rendered establishing the claims of appellees in the aggregate sum of more than $17,000, denying to appellant any portion of the funds paid by the highway commission into the registry of the court, reducing F. C. Grane Company’s claim from $1,846.25 to $586.25, allowing $2,000 as attorneys’ fees to the attorneys for appellees to be taxed as costs, and ordering the remainder of said fund prorated amongst said claimants.* From this judgment the Thurber Construction Company and F. C. Crane Company have appealed. Further facts will be stated in the discussion of the issues raised.

In findings of fact and conclusions of law the trial court found and concluded that under the contract above set forth Thurber Construction Company took over the original contract between Purvis & Son and the highway commission, agreed to complete said highway for the remainder of the original price due Purvis & Son thereunder, “became assignees of the said D. H. Purvis & Son and stand in the shoes of the original contractor * * * and that the said Thurber Construction Company, so standing in the position of the original contractor and as its assignee, is not entitled to share in said moneys with those who furnished labor and material.” The court also concluded that under said contract with appellant “the claim of the latter to the moneys in the hands of the State Highway Commission was expressly made subject to the claims of those furnishing labor and material.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Bryan Langdon v. Leslie Mathison Gilbert
Court of Appeals of Texas, 2015
Southmark Corp v. FDIC
Fifth Circuit, 1998
In Re Ashford
73 B.R. 37 (N.D. Texas, 1987)
Ex Parte Johnson
654 S.W.2d 415 (Texas Supreme Court, 1983)
Knebel v. Capital National Bank in Austin
518 S.W.2d 795 (Texas Supreme Court, 1975)
John F. Buckner & Sons v. Arkansas Fuel Oil Corp.
301 S.W.2d 325 (Court of Appeals of Texas, 1957)
National Surety Corporation v. Dabney
282 S.W.2d 70 (Court of Appeals of Texas, 1955)
Koenig v. McCARTHY CONSTR. CO., INC.
100 N.E.2d 338 (Appellate Court of Illinois, 1951)
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1944
Verschoyle v. Holifield
90 S.W.2d 907 (Court of Appeals of Texas, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
81 S.W.2d 103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thurber-const-co-v-kemplin-texapp-1935.