Verschoyle v. Holifield

90 S.W.2d 907
CourtCourt of Appeals of Texas
DecidedDecember 18, 1935
DocketNo. 8237.
StatusPublished
Cited by1 cases

This text of 90 S.W.2d 907 (Verschoyle v. Holifield) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Verschoyle v. Holifield, 90 S.W.2d 907 (Tex. Ct. App. 1935).

Opinions

This case arose as follows: On August 29, 1931, the highway commission entered into a contract with Dozier Construction Company to construct a designated highway in Sterling county at a cost to the state of $112,794.97. The Dozier Construction Company executed the statutory bond to guarantee its performance of such contract. Subsequent thereto the Dozier Construction Company sublet the entire project to R. B. Holifield, retaining to itself 9 per cent. of all moneys to be paid by the state under its contract, and assigning the remaining 91 per cent. of the contract price to Holifield, who assumed all obligations and agreed to pay all expenses incurred in the completion of the project. Holifield in turn executed a bond to Dozier Construction Company, with the Public Indemnity Company as surety. This bond was executed by B. M. Bates as attorney in fact for said company in Texas, through the office of C. H. Verschoyle, who was then its state agent, who had a 10 per cent. interest in the underwriting profits of said company in Texas, and who was personally interested in seeing that Holifield performed his subcontract without loss to such surety company. In addition to this interest, it appears that Verschoyle had failed to seasonably report to his company the execution of such bond, as he was required to do, and was fearful that because of that fact he might himself be held personally liable thereon.

In May, 1932, Holifield encountered financial difficulties and was about to default on his contract. Thereupon Verschoyle and other creditors of Holifield advanced to Holifield various sums of money and otherwise assisted him in completing such road project, paid numerous claims against him under an oral agreement with Holifield that they would be subrogated to the rights of his creditors against all funds due him. At the time of the completion of such project, the highway department was withholding $18,731.10 of the contract price which included the percentage retained under the statutes, and sums retained because of claims filed with it by laborers and materialmen. The Gulf Refining Company for itself and on behalf of other creditors, brought this suit on its claim against Holifield for its debt and against the highway commission for a distribution of the funds retained by it. Numerous other creditors intervened. The highway commission tendered into the registry of the court the funds held by it to be distributed as the court might decree. The pleadings of the various claimants and interveners sought additional relief which will be noted, in so far as pertinent to this appeal, in the discussion of the issues raised. Some of the claimants sought additionally a personal judgment against Verschoyle. Verschoyle and Bates sought recovery against Holifield, against the receiver of Dozier Construction Company, which had become insolvent, and the surety on its bond, for the moneys paid out by them for Holifield; asked to have their claim established as a lien upon the funds retained by the highway commission, and sought to participate in the distribution thereof. Judgment was rendered establishing numerous claims of plaintiff and interveners against Holifield and the Dozier Construction Company and prorating the retained fund amongst them, but denying to Verschoyle and Bates any participation in such fund, from which judgment Verschoyle and Bates have appealed. Some of the appellees filed cross-assignments, but these have been subsequently dismissed by them and need not be considered here.

The first and major contention made by Verschoyle is that because he had advanced moneys to Holifield to enable him to perform his contract, had taken an assignment from Holifield of funds due and to become due him from Dozier Construction Company, and had an agreement with *Page 910 Holifield that he should be subrogated to the rights of the laborers and materialmen whom he had paid, and that he should stand in their shoes, he was entitled to assert his claim as a lien against the fund retained by the highway commission, and to participate in the distribution of same. This he was denied by the trial court. This contention is not sustained.

It is admitted that Verschoyle had no personal liability in connection with Holifield's contract. His interest was in the profits of the surety company he represented which had executed Holifield's bond, injury to his business in case Holifield should default, and a fear that because of his own failure to promptly report such bond to his company, he might be held personally liable thereon. All of these grounds, however, were purely personal to him, and none of them would impose any legal liability upon him to answer either to the creditors of Holifield, or to Dozier Construction Company, for any default by Holifield in the performance of the latter's contract. He did not take any assignment from the laborers or materialmen whose claim he paid of their rights in the premises; but looked entirely to Holifield and the funds due Holifield on the project for reimbursement of the moneys advanced by him. Under these circumstances he was in law but a volunteer in the payment of said claims, there being no legal obligation resting upon him to do so, and he would not be subrogated to the rights of the claimants whose claims he paid to fix a lien upon the funds in question. Employers' Cas. Co. v. Rockwall County, 120 Tex. 441, 35 S.W.2d 690, 38 S.W.2d 1098; Brooks Const. Co. v. First State Bank (Tex.Civ.App.) 39 S.W.2d 83; Southern Surety Co. v. Sealy Ind. School Dist. (Tex.Civ.App.) 10 S.W.2d 786; Thurber Const. Co. v. Kemplin (Tex.Civ.App.) 81 S.W.2d 103.

Appellants next complain that the trial court's findings of certain facts relative to an agreement between Verschoyle and the Dozier Construction Company differ from those announced orally from the bench and that such findings are not supported by the evidence. The trial was to the court without a jury. No statement of facts accompanies the record, and the findings of fact were made pursuant to request therefor. Under these circumstances oral announcements of the trial court, not shown by the record, cannot be considered, and the findings of fact made by the trial court will be presumed to have had support in the evidence.

Appellant Verschoyle next complains of the judgment in favor of John W. Goodrum against him and Holifield for $2,250 on the following grounds: (1) That there were no pleadings to sustain it; (2) that same was not supported by the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Verschoyle v. Holifield
123 S.W.2d 878 (Texas Supreme Court, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
90 S.W.2d 907, Counsel Stack Legal Research, https://law.counselstack.com/opinion/verschoyle-v-holifield-texapp-1935.