Watterson v. Owens River Canal Co.

143 P. 90, 25 Cal. App. 247, 1914 Cal. App. LEXIS 265
CourtCalifornia Court of Appeal
DecidedJuly 29, 1914
DocketCiv. No. 1471.
StatusPublished
Cited by11 cases

This text of 143 P. 90 (Watterson v. Owens River Canal Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watterson v. Owens River Canal Co., 143 P. 90, 25 Cal. App. 247, 1914 Cal. App. LEXIS 265 (Cal. Ct. App. 1914).

Opinion

CONREY, P. J.

In the superior court, the action of the plaintiff Watterson and a separate action of the other plaintiffs, against the same defendant, were consolidated. From a judgment in favor of the plaintiff Watterson and in favor of certain other plaintiffs, and from an order denying defendant’s motion for a new trial, the defendant appeals.

*249 On December 30, 1908, P. N. Snyder and C. A. Collins entered into a Avritten contract with the Hillside Water Company and the Owens River Canal Company, whereby the contractors agreed to perform the excavation work required by certain specifications, for the purpose of making improvements in a canal belonging to defendant Owens River Canal Company. The contract was dated November 30, 1908, and was delivered on December 30th following. Work was commenced early in December, and the contract was not recorded until February 9, 1909. At the time of the execution of the written contract, the plaintiff T. Gr. Watterson executed to defendant Owens River Canal Company an undertaking in the penal sum of five thousand dollars, conditioned upon due performance of the contract by the contractors. As Collins does not appear any further in the transactions, we will discuss the case as if Snyder were sole contractor.

The consideration to be paid for this work as stated in the contract was nineteen thousand dollars, installments payable monthly on estimates to be made by the engineer. As the contract was not recorded before commencement of the work, the transaction became subject to the provision of section 1183 of the Code of Civil Procedure, that such contracts “shall be wholly void, and no recovery shall be had thereon by either party thereto; and in such case, the labor done and materials furnished by all persons aforesaid, except the contractor, shall be deemed to have been done and furnished at the personal instance of the owner, and they shall have a lien for the value thereof.”

The specifications, which are referred to in the contract and attached thereto, contain the following provisions:

“The work to be done consists of excavating one or both banks of the canal to double its present cross section with a view of doubling the present carrying capacity of the canal.
“The company’s engineers will give levels and grade stakes designating the excavations that are to be made, and the contractor is to pay particular attention to these stakes and make the excavation true to the stakes given.
“At the discretion of the engineer in charge the excavations may be made on either the upper or lower bank, or both banks of the canal, as the character of ground and material indicates for the most economical and safest excavation.
*250 “It is also understood and agreed that the said engineer in charge may require changes to be made in the route and line of the canal, particularly where the distance can be shortened, and the engineer in charge may direct such changes; and in settling for the same, allowance shall be made to either party, whether the quantity or quality of the materials removed shall be greater or less or of a different character from the estimates and classifications above referred to and made a part of this contract/’

The contractor Snyder took charge of the work and conducted the same personally and by sub-contractors for various sections until February 16, 1909. Disputes arose between him and the engineer, on account of changes in levels as furnished by the engineer, and on account of a change made by directing a certain cut-off which shortened the canal. On January 8th a conference took place between the contractor and the engineer and some officers of the two corporations named in the contract, as to the manner in which the work should be done, and it was understood that Snyder would follow the directions given as to these changes ordered by the engineer. But dissatisfaction continued on both sides, so that Snyder gave up the work on February 16th, and at the same time the plaintiff Watterson took charge of the work in place of Snyder. Watterson continued the work until April 16th, when it was completed.

Watterson claims that the verbal understanding at which the contractor and the said representatives of the owner arrived on January 8th, constituted a change in the contract, such as to relieve Watterson from the obligations of his bond, and that as the contract itself was void, his work from February 16th to April 16th was on an original request of the owner, entitling him to claim his lien under the provisions of section 1183 of the Code of Civil Procedure, quoted above.

The appellant contends that the changes made in the work were only such as were provided for in the specifications; and that the work done by Watterson was done by him by virtue of his relation to the transaction as bondsman, for the contractor, and for the purpose of protecting himself from liability on the bond.

There was no formal contract, either written or unwritten, between plaintiff Watterson and the owner, by virtue of which Watterson undertook to complete the work. Mr. L. C. *251 Hall was treasurer, and was a director and also attorney for the Owens River Canal Company. Mr. Watterson’s testimony is that on February 9th or 10th Mr. Hall complained to him that Mr. Snyder was not complying with the instructions of the engineer and was not doing the work satisfactorily, and that they had lost confidence in him, and asked Watterson to go ahead and finish the work. On February 15th, Watterson told Snyder about this. Snyder said, “All right, go ahead and finish it.” Watterson replied, “All right.” It was under these circumstances that Watterson took charge of this work and did all that was done by him in completion thereof.

The payments by the defendant amount to sixteen thousand dollars, of which the sum of ten thousand dollars was paid prior to February 16th. All of the payments were delivered to Watterson, who was a creditor of Snyder for supplies furnished, and Watterson’s receipts recite that the moneys so received were on account of the Snyder and Collins contract and were to be used for payment of such accounts as would constitute liens against the canal.

The demand of Watterson in this action is for the sum of $20,189.54, and the decree appealed from is in his favor for the sum of $10,285.71, with interest, and in favor of the other plaintiffs for sums which in the aggregate are a little over one thousand dollars.

The findings of the court state that on the sixteenth day of February, 1909, the plaintiff Watterson “at the personal instance and request of said defendant, and by and with the consent and authority of said contractor, P. N. Snyder, ’ ’ took charge of the described work, and completed the same on April 16, 1909.

The court’s findings declare that on January 8, 1909, “officers and agents” of the defendant, and P. N.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hill & Morton, Inc. v. Coughlan
214 Cal. App. 2d 545 (California Court of Appeal, 1963)
McClintic-Marshall Corp. v. Maryland Casualty Co.
100 S.W.2d 438 (Court of Appeals of Texas, 1936)
W. H. Putegnat Co. v. Fidelity & Deposit Co. of Maryland
29 S.W.2d 1004 (Texas Commission of Appeals, 1930)
Howard v. Fisher
283 P. 1042 (Supreme Court of Colorado, 1929)
Federal Surety Co. v. Lalonde
31 F.2d 673 (Ninth Circuit, 1929)
Southern Surety Co. v. Sealy Independent School Dist.
10 S.W.2d 786 (Court of Appeals of Texas, 1928)
Dodd v. Maddox
238 P. 130 (California Court of Appeal, 1925)
Mazzera v. Ramsey
238 P. 101 (California Court of Appeal, 1925)
Watterson v. Owens River Canal Co.
210 P. 625 (California Supreme Court, 1922)
Wells v. Philadelphia
112 A. 867 (Supreme Court of Pennsylvania, 1921)
Watterson v. Owens River Canal Co.
183 P. 816 (California Court of Appeal, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
143 P. 90, 25 Cal. App. 247, 1914 Cal. App. LEXIS 265, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watterson-v-owens-river-canal-co-calctapp-1914.