Mazzera v. Ramsey

238 P. 101, 72 Cal. App. 601, 1925 Cal. App. LEXIS 503
CourtCalifornia Court of Appeal
DecidedMay 11, 1925
DocketDocket No. 2828.
StatusPublished
Cited by12 cases

This text of 238 P. 101 (Mazzera v. Ramsey) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mazzera v. Ramsey, 238 P. 101, 72 Cal. App. 601, 1925 Cal. App. LEXIS 503 (Cal. Ct. App. 1925).

Opinion

FINCH, P. J.

The plaintiff, as owner, and George Balliet, as contractor, entered into a building contract containing the following provisions material to the determination of this appeal:

“Whereas, the said owner is desirous that the hereinafter mentioned one story bungalow building No. 841 be built, erected and fully completed for the sum of . . . $7,516.50, free and clear from all liens and claims of liens, and of any and every other claim and demand . . . and
“Whereas, the said contractor with knowledge of the premises, is ready, able and willing to furnish all labor and materials and to do and fully perform all work essential and proper in such complete performance and completion of the said building for the sum of . . . $7,516.50 subject to the covenants and conditions hereinafter contained and in consideration of the premises.
“Now it is hereby agreed: 1st: That the contractor will at his own charge and cost and within five days from the date hereof, begin and continuously prosecute and perform the said work in a thorough and workmanlike manner and *604 fully complete the same all according to the intent and meaning of the plans, drawings and specifications referred to in this contract . . . for the sum of . . . $7516.50'. . . . 5th: . . . The sixth payment to be made in the sum of $1879 when building is accepted by architect and owner, and all vouchers are presented by contractor pertaining to the payment of all labor and materials for said building, otherwise the owner reserves the right to wait for thirty-five days after acceptance of said "building before making the final payment to contractor. 7th: . . . Should the contractor at any time during the progress of the work refuse, fail or neglect without the fault of the owner to supply a sufficiency of materials or workmen to complete this contract expeditiously or any lawful extension thereof for a period of more than three days after having been notified by the said owner, the owner shall have power to furnish at market rates, material or workmen to finish the said work, and the cost thereof shall be deducted from the amount of such contract price, and if such costs exceed such price, said excess shall within two days be paid to the said owner.”

The contract provided for partial payments as the work progressed, to be made upon presentation of the architect’s certificates. A bond for the faithful performance of the work by the contractor was given in the following form:

“Know all men by these presents, that we, the undersigned, W. C. Ramsey and T. F Emerson, . . . are as sureties and guarantors, held and firmly bound jointly and severally by these presents unto John Mazzera as owner. His executors, administrators and assigns in the sum of three thousand seven hundred and fifty-eight dollars and twenty-five cents ... to be paid, his executors, administrators and assigns jointly and severally by these presents, . . . The condition of the above obligation is such that (here follow recitals to the effect that the contract was executed; that a copy thereof is attached to the bond; that the “contract was entered into upon the express consideration that the full and specific performance thereof should be secured and insured by this bond”; that it “is a bond of indemnity”; and that the contract and the plans and specifications are made a part of the bond). Now, therefore, if the above George Balliet shall well, faithfully and specifically perform the said contract, and hand over to the said owner said *605 work therein mentioned, within the time therein specified, full, completed and in a clean condition and free and" clear of liens as thereby required, and in entire accordance with all of the terms thereof, then this obligation to become null and void, otherwise to remain in full force and virtue.”

The contract, plans, and specifications and the bond were recorded the same day that the contract was executed. A few days later the contractor entered upon the performance of the work and continued therein until the architect’s certificate was issued showing that the second payment was due, at which stage he abandoned the contract. The sureties then undertook the completion of the building. A few days before it was finally completed, the work remaining to be done not appearing from the record, the men employed by the sureties in the construction of the building quit work. The plaintiff induced the men to return and complete the building by promising them to “see they got their money.” It was stipulated at the trial that the building was finally “completed according to the plans and specifications.”

The final payment of $1,879 was not made to the contractor or to the sureties, but the plaintiff paid the amount thereof and the sum of $1,879.02 additional in the discharge of claims for labor and material in the construction of the building which the contractor and the sureties failed and refused to pay. No claims of lien were ever filed against tile building and such payments for labor and material were made by the plaintiff before the expiration of the time within which liens might have been filed. The complaint alleges and the court found that the plaintiff made such payments “with the knowledge and consent of defendants W. C. Ramsey and said T. F Emerson, and at their instance and request.” Emerson died after the payments had been made by plaintiff, and the executrix of his estate is made a party defendant. A claim against his estate for the amount of such payments was duly presented to the executrix and disallowed. The plaintiff was given judgment for the amount of all claims paid by him and defendants have appealed.

Appellants contend that their demurrer to the complaint should have been sustained. The foregoing facts, together with much evidentiary and unnecessary matter, are alleged in the complaint. That such facts constitute a *606 cause of action is so apparent that no discussion of the question is deemed necessary.

The most serious contention of appellants is that the payments made by plaintiff for labor and materials were voluntary. Section 1183 of the Code of Civil Procedure, among other things, provides: “The liens in this chapter provided for shall be direct liens, and shall not in the case of any claimants, other than the contractor, be limited, as to amount, by any contract price agreed upon between the contractor and the owner except as hereinafter provided. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Halbert's Lumber, Inc. v. Lucky Stores, Inc.
6 Cal. App. 4th 1233 (California Court of Appeal, 1992)
Barrientos v. Government of Capital
97 P.R. 539 (Supreme Court of Puerto Rico, 1969)
Barrientos v. Gobierno de la Capital
97 P.R. Dec. 552 (Supreme Court of Puerto Rico, 1969)
American Insurance v. Heritage Construction Corp.
268 F. Supp. 336 (N.D. California, 1965)
Caron v. Andrew
284 P.2d 544 (California Court of Appeal, 1955)
State Bank of Wheatland v. Turpen
34 P.2d 1 (Wyoming Supreme Court, 1934)
English v. Olympic Auditorium, Inc.
20 P.2d 946 (California Supreme Court, 1933)
Pacific Coast Engineering Co. v. Detroit Fidelity & Surety Co.
5 P.2d 888 (California Supreme Court, 1931)
Howard v. Fisher
283 P. 1042 (Supreme Court of Colorado, 1929)
Nohrnberg v. Boley
246 P. 12 (Idaho Supreme Court, 1925)
Sanguinetti v. Ramsey
238 P. 105 (California Court of Appeal, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
238 P. 101, 72 Cal. App. 601, 1925 Cal. App. LEXIS 503, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mazzera-v-ramsey-calctapp-1925.