Siegel v. Hechler

183 P. 664, 181 Cal. 187, 1919 Cal. LEXIS 433
CourtCalifornia Supreme Court
DecidedSeptember 3, 1919
DocketL. A. No. 4935.
StatusPublished
Cited by10 cases

This text of 183 P. 664 (Siegel v. Hechler) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Siegel v. Hechler, 183 P. 664, 181 Cal. 187, 1919 Cal. LEXIS 433 (Cal. 1919).

Opinion

SHAW, J.

The Southwestern Surety Insurance Company appeals from a judgment against it in favor of plaintiff upon a bond executed by it as surety for G. A. Hechler for the performance of a subcontract between Hechler and the plaintiff for the doing of a part of the work upon a building under erection by Siegel.

The Marlborough school for girls, a corporation engaged in the business of conducting a girls’ school, made a contract with Siegel for the erection of a school building on its premises *188 at the contract price of seventy thousand dollars. The contract, with elaborate plans and specifications, was duly filed in the recorder’s office on July 12, 1915. Siegel and Hechler entered into a subcontract whereby Hechler agreed to do the excavation and concrete work on the building as required by said plans and specifications, for the sum of seven thousand dollars. Hechler began work on the subcontract about September 7, 1915, and continued at the work until November 7, 1915, at which time he absconded, leaving the work unfinished. Siegel completed the subcontract work at his own expense. Hechler was made a defendant, but he was not served with process. The case proceeded to judgment against the surety company alone.

The -complaint alleges that while Hechler was engaged in the work Siegel paid him, in accordance with the terms of the contract, $4,537.87; that after Hechler abandoned the work Siegel paid for labor performed upon, and materials and supplies used in, the subcontract work by Hechler and left unpaid by him, sums amounting to $3,925.33, and that in completing the building after the abandonment by Hechler plaintiff- expended $2,139.43, which was the reasonable cost of such completion. He asked judgment for the difference between the aggregate of these sums and seven thousand dollars, the subcontract price.

The denials and affirmative allegations of the answer set up the defense that the sums amounting to $4,537.85 alleged to have been paid to Hechler while the work was going on, were not paid “in accordance with the terms of said contract,” and that Siegel violated his agreement with Hechler, for the performance of which the bond was given, by paying money to Hechler in excess of the amount due on the subcontract at the time of such payment, whereby, it is claimed, the surety was released.

The court found that while Hechler was engaged in the work Siegel paid him, “in accordance with the terms of said subcontract,” $4,526.90; that after the abandonment Siegel paid $3,925.33 on bills due from Hechler for materials and labor used in the subcontract work, and that Siegel completed the work on the subcontract at the reasonable expense of $2,139.43. This made an excess of $3,591.66 paid out by Siegel over the subcontract price, for which excess judgment was" given in favor of the plaintiff.

*189 The terms of the subcontract regarding payments by Siegel to Hechler and which it is claimed Siegel violated by premature payments were as follows:

“Second: That the said General Contractor will in consideration of the said covenants and' agreements being strictly performed and kept by the said Sub-contractor, as herein-above mentioned, well and truly pay, or cause to be paid, unto the said Sub-contractor the said sum of money above mentioned as the Sub-contract price.
“In the manner following: Such amounts as Heehler may need for pay roll on or before twelve o’clock noon of each and every Saturday following beginning of work and balance thirty-five days after completion of this contract, but in the event that the General Contractor should deem himself insecure by reason of a possibility that the laborers or the materialmen of the Sub-contractor may file claims of liens upon said property, or may give to the Owner notices to withhold money from the General Contractor, then the General Contractor may at his option withhold further payments until furnished with receipts or releases from all such materialmen and laborers.”

It is the contention of the plaintiff that the phrase “such amounts as Heehler may need for pay-roll on or before twelve o’clock noon of each and every Saturday following beginning of work” covers only payments of the weekly wages of the men employed by Heehler, or other regular weekly sums contracted to be paid by him for the doing of work on the subcontract. It appears from the evidence that in the course of the work Hechler incurred bills in the performance thereof upon which Siegel paid the sums following, to wit: On September 28, 1915, to Butterfield & Scaer $350, for steam shovel work; October 1, 1915, to E. E. Scott, for hauling and excavating, $450; and on October ”21, 1915, to L. A. Rock and Gravel Company $759, for materials used in the work, a total of $1,559. The point made by the appellant is that these sums could not have been included in any pay-roll, within the meaning of the subcontract, and that tmder its terms they did not become due to Heehler, or payable on his account, until thirty-five days after the completion of his subcontract. The argument is that by this departure ’ from the terms of the contract the surety was prejudiced and thereby it was released from its obligation. If the word “pay-roll” has the *190 meaning this argument assumes, 'the above-mentioned payments were premature, so far as the terms of the subcontract just quoted are concerned.

[1] It is not an accurate statement of the law to say that the surety would be released from the entire obligation by reason of premature payments. They would not be an alteration of the contract for the performance of which the defendant had become surety. They would be a departure therefrom or a violation thereof, effected by the parties during its performance, without the consent of the surety. The legal result of such departure would not be to release the surety from the entire obligation. The effect would be that Siegel would have no cause of action on (the bond1 to recover from the surety that part of Hechler’s defalcation that was made up of these premature payments. The authorities cited by appellant concerning the effect of a material alteration in the contract after the surety has become bound thereon and without its consent are not strictly applicable.

There are persuasive reasons, growing out of the nature of the subcontract and the work to be done thereunder, in connection with the law as to the liens of mechanics, for giving the above-quoted word “pay-rolls” a broader meaning. But we take a view of the case which renders it unndcessary to determine whether the narrower or broader interpretation is correct and we therefore leave the question undetermined. There are other terms of the subcontract and there were other circumstances, both of law and fact, which must be taken into consideration and which show that Siegel had the right to pay these bills at the time they were paid.

The subcontract provides that Hechler shall save Siegel “free and harmless” from any and all liability which might accrue against or upon Siegel as the result of any default of Hechler in the performance of the subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wattenbarger v. City of Vinita
1934 OK 562 (Supreme Court of Oklahoma, 1934)
English v. Olympic Auditorium, Inc.
20 P.2d 946 (California Supreme Court, 1933)
Pacific Coast Engineering Co. v. Detroit Fidelity & Surety Co.
5 P.2d 888 (California Supreme Court, 1931)
Roberts v. Security Trust & Savings Bank
238 P. 673 (California Supreme Court, 1925)
Nohrnberg v. Boley
246 P. 12 (Idaho Supreme Court, 1925)
Mazzera v. Ramsey
238 P. 101 (California Court of Appeal, 1925)
Burr v. Gardella
200 P. 493 (California Court of Appeal, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
183 P. 664, 181 Cal. 187, 1919 Cal. LEXIS 433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/siegel-v-hechler-cal-1919.