Dunne Investment Co. v. Empire State Surety Co.

150 P. 405, 27 Cal. App. 208, 1915 Cal. App. LEXIS 86
CourtCalifornia Court of Appeal
DecidedApril 21, 1915
DocketCiv. No. 1293.
StatusPublished
Cited by13 cases

This text of 150 P. 405 (Dunne Investment Co. v. Empire State Surety Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dunne Investment Co. v. Empire State Surety Co., 150 P. 405, 27 Cal. App. 208, 1915 Cal. App. LEXIS 86 (Cal. Ct. App. 1915).

Opinion

HART, J.

This is an action to recover the sum of $23,036.59 on a surety bond executed by the defendant, Empire State Surety Company, to insure the faithful performance of the terms of a building contract made and entered into between the plaintiff, as owner, and the defendants, Condon and MeGlynn, as contractors, on the twenty-first day of October, 1908, at the city of San Francisco.

The Surety Company answered the complaint by denials and certain affirmative defenses, the latter involving the charge that the terms of the building contract were varied from in material respects without the knowledge or assent of the said defendant.

The other defendants defaulted.

A trial of the issues was had before a jury and a verdict awarding the plaintiff the sum of $12,219.50 returned. Judg *211 ment was thereupon entered for the plaintiff in said amount.

This appeal is prosecuted by the defendant, Surety Company, from said judgment and the order denying it a new trial.

The building contract, which is a lengthy document, was entered into and executed on the twenty-first day of September, 1908, and under its terms the defendants, Condon and MeGlynn, building contractors and doing business as such under the firm name of Condon & MeGlynn Company, were to construct a building for the plaintiff on a lot leased by the latter, or, strictly speaking, by its assignor, and which is situated on Ellis and Stockton streets, in the city of San Francisco, for the expressed consideration of fifty-two thousand seven hundred and fifty dollars. The building provided for by said contract was to be erected and completed in conformity with plans and specifications prepared by McDonald & Applegarth, architects, which plans and specifications were annexed to and made a part of the contract. The contract provides that the contractor should enter upon the performance of said work on or after October 26, 1908, and to steadily proceed with and hasten the same to completion as rapidly as practicable, and “to deliver said work to the owner, completely finished, and free from all claims, liens or charges, on or before the 120th working day after October 26, 1908.” It is further provided therein that, since, “from the nature of the case, it would be impracticable or extremely difficult to fix the actual damage which would be suffered by the owner by a failure of the contractor to complete this contract, and the work therein provided for, within the time herein specified,” the sum of fifty dollars per day should be deemed and considered as the fixed and liquidated damage suffered by said owner on account of said noncompletion, “and for each day the building is completed before the contract time a bonus of $50 shall be paid the contractor.”

The contract then proceeds, and this provision is here given in full because upon its construction as a part of the bond of the Surety Company by the light of the evidence adduced, largely rests the determination of the question, which is the ultimate one submitted for decision, whether there was a material deviation from the terms of the said contract without the assent of and to the detriment of the Surety Company:

*212 “Payments to be made after the completion of portions of the work on the first day of each calendar month, as the work progresses, in installments, based upon monthly estimates of all work done and material furnished and paid for in the building up to and including the last day of the preceding month, in sums equal to seventy-five per cent of the value of said work done and materials furnished, to be estimated by the architect, provided that no more than seventy-five per cent of the whole contract price shall be paid up to the time of completion. The balance to wit: twenty-five per cent of the whole contract price, to be paid thirty-six days after final completion of the contract and acceptance of the work covered by it, provided that when such payments of installments shall become due, and at the final completion of the work, certificates in writing shall be obtained from the architect, stating that the payment or installment is due, or the work is completed, as the ease may be, and the amount then due; and shall be less the total amount of accrued liens as disclosed by the contractor, or of which the owner or architect may have received written notice, and also less the sum of one hundred dollars counsel fees, and the reasonable costs of such lien or claim. The certificate so issued by the architect shall be paid by the owner, immediately upon presentation; and a final settlement, as to the remainder and for all extras, if any, shall be had, and payment made thirty-six days after final completion of this contract and the acceptance of said work, the same to be free from all liens, charges and claims whatsoever, and the architect shall so certify in writing.
“The monthly estimates of the architect are, however, subject to correction by him in any subsequent monthly or in his •final estimates. Serving merely as a basis for payment on account, they are presumed to be only approximate.”

The defendant, Surety Company, furnished the usual surety bond for the faithful performance of the terms of said contract. This bond expressly made the building contract a part thereof, and expressly provides that, in case the contractors fail to complete the building within the specified time, they would pay to the plaintiff the sum of fifty dollars per day for each and every day beyond said time during which the building remained uncompleted in accordance with the terms of the building contract and the plans and specifications. It further expressly provides that it would pay to the *213 plaintiff any liens or encumbrances which, might be placed upon said building arising by reason of the construction thereof.

The contractors proceeded with the construction of said building according to the requirements of their contract and continued with said work until the first days of July, 1909, at which time the structure was well under way, when they abandoned the contract for the reason, so the members of the firm declared, that they did not have sufficient financial means to proceed with and complete the building. Up to this time the contractors had been paid by the plaintiff on the contract price the aggregate sum of $31,397.50, said sum having been paid from time to time in installments based upon the estimates and authorized by the certificates of the above named architects.

On July 8, 1909, the plaintiff gave the contractors the written notice, prescribed by the contract, that, said contractors having failed or neglected to carry out their contract, it would, on the twelfth day of July, 1909, exclude the contractors from further connection with said work and itself take charge thereof. On the same day, the plaintiff served a formal written notice on the Surety Company of the abandonment of the contract by the contractors and of the fact of service of notice on the latter as required by the contract.

The plaintiff, through its officers, immediately thereafter took up the matter of the default of the contractors with the Surety Company through James C. Hayburn, its general agent for California, his office being in the city of San Francisco. The plaintiff submitted to Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Employers Insurance v. City of Berkeley
158 Cal. App. 3d 145 (California Court of Appeal, 1984)
A. A. Baxter Corp. v. Colt Industries, Inc.
10 Cal. App. 3d 144 (California Court of Appeal, 1970)
Amerson v. Christman
261 Cal. App. 2d 811 (California Court of Appeal, 1968)
American Insurance v. Heritage Construction Corp.
268 F. Supp. 336 (N.D. California, 1965)
Safeway Stores, Inc. v. Massachusetts Bonding & Insurance
202 Cal. App. 2d 99 (California Court of Appeal, 1962)
Pacific Coast Engineering Co. v. Detroit Fidelity & Surety Co.
5 P.2d 888 (California Supreme Court, 1931)
United States Building & Loan Ass'n v. Burns
4 P.2d 703 (Montana Supreme Court, 1931)
Milwaukee Building Co. v. Wetzel
270 P. 382 (California Court of Appeal, 1928)
Roberts v. Security Trust & Savings Bank
238 P. 673 (California Supreme Court, 1925)
Mazzera v. Ramsey
238 P. 101 (California Court of Appeal, 1925)
Lamson v. Maryland Casualty Co.
196 Iowa 1185 (Supreme Court of Iowa, 1923)
Burr v. Gardella
200 P. 493 (California Court of Appeal, 1921)
First Congregational Church of Christ v. Lowrey
165 P. 440 (California Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
150 P. 405, 27 Cal. App. 208, 1915 Cal. App. LEXIS 86, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dunne-investment-co-v-empire-state-surety-co-calctapp-1915.