Pacific Employers Insurance v. City of Berkeley

158 Cal. App. 3d 145, 204 Cal. Rptr. 387, 1984 Cal. App. LEXIS 2296
CourtCalifornia Court of Appeal
DecidedJuly 9, 1984
DocketA016128
StatusPublished
Cited by20 cases

This text of 158 Cal. App. 3d 145 (Pacific Employers Insurance v. City of Berkeley) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Employers Insurance v. City of Berkeley, 158 Cal. App. 3d 145, 204 Cal. Rptr. 387, 1984 Cal. App. LEXIS 2296 (Cal. Ct. App. 1984).

Opinion

Opinion

BARRY-DEAL, J.

Pacific Employers Insurance Company (Pacific) appeals from a summary judgment entered in favor of the City of Berkeley (the city) which established that the city was entitled to withhold certain funds as liquidated damages from its payment to Pacific under a construction contract for which Pacific was the completing surety. We affirm.

The Facts

On or about November 26, 1974, the city entered into a contract with Emerald Builders (Emerald) for construction of the James Kenney Park Community Recreation Center, for the total sum of $759,061. Initially construction was to be completed by October 18, 1975, 300 days after commencement of the work, but the city granted extensions for completion to *148 May 6, 1976. Emerald did not meet that deadline, but it continued to work on the project until it abandoned it on September 17, 1976. During the period between the required completion date and abandonment, the city continued to make progress payments to Emerald.

When Emerald abandoned the project and the city cancelled the contract, Pacific, which had supplied a performance bond to Emerald as principal in favor of the city as obligee, responded to the city’s demand and arranged for another contractor to complete the project. This was accomplished on April 2, 1977, at a cost to Pacific of $138,651.82.

Ultimately the city paid Pacific $57,892.93, leaving Pacific with unreimbursed completion costs of $80,758.89, and an undisbursed contract balance in the hands of the city of $87,982.73. The city claimed an offset against this balance for liquidated damages occasioned by delay in completion of the project at the contract rate of $250 per day from May 6, 1976, to April 2, 1977, for a total of $82,500. 1

In granting summary judgment to the city, the trial court ruled that it was entitled to this offset for liquidated damages. The propriety of that determination is the subject of this appeal.

Discussion

The Bond

The bond given by Pacific appears to be a standard form used by that company. It provides, in relevant part, as follows (italics indicates filled-in blanks): “WHEREAS, the Principal [Emerald] and Obligee [city] have entered into a certain contract in writing, hereinafter called the contract, dated DECEMBER 10, 1974 for: JAMES KENNEY PARK COMMUNITY RECREATION CENTER SPECIFICATION NO. 17.548 a copy of which is or may be attached hereto, and which is hereby referred to, [f] NOW, THEREFORE, The condition of this Obligation is that if the Principal shall well and truly perform the work contracted to be performed under said contract, then this obligation shall be void, otherwise to remain in full force and effect. This bond shall inure to the benefit of the persons herinabove [sic] specified only so as to give a right of action to such persons or their or their [sic] assigns in any suit brought upon this bond.”

*149 The Contract

The provision for liquidated damages in the contract was as follows: “[§] 801.6 Liquidated Damages for Failure to Complete Work in Specified Time. If all the work called for under the contract is not completed before or upon the expiration of the time set forth in the Bidder’s Sheet, damage will be sustained by the City. Since it is and will be impracticable to determine the actual damage which the City will sustain in the event of and by reason of such delay, it is therefore agreed that the Contractor will pay to the City the sum specified in the Bidder’s Sheet [$250 per day] for each and every calendar day beyond the time prescribed to complete the work [May 6, 1976], not as a penalty, but as a predetermined liquidated damage. The Contractor agrees to pay such liquidated damages as are herein provided, and in case the same are not paid, agrees that the City may deduct the amount thereof from any money due or that may become due the Contractor under the contract.”

Surety’s Liability for Liquidated Damages

One leading authority indicates that by virtue of the giving of the bond alone, the completing surety will be found liable for liquidated damages. He says: “A surety completing the contract upon a contractor’s default is subject to any valid penalty provision contained in the contract which could have been asserted by the obligee against the contractor. Hence, a surety, who completes the contract, is subject to the deduction from the retained percentage for delayed completion as is provided in the contract.” (13 Couch on Insurance (2d ed. 1982) § 47:137, p. 314, fns. omitted [hereafter Couch].) This statement is overbroad. The case upon which the author relies does not support his assertion. In Maryland Casualty Co. v. Board of Water Com’rs (2d Cir. 1933) 66 F.2d 730, the court said, “Since completion of the contracts was taken over by the surety, perhaps the provision [for liquidated damages] would include tardy completion by the surety no less than by the contractor. But this need not be decided, for the claim is not for liquidated damages but for smaller actual damages [for which the bond expressly provided indemnity] . . . .” (Id., at p. 735, italics added.) In Couch’s authority, then, the question whether liquidated damages were covered by the bond and were recoverable from the surety was not decided.

Similarly, Miller and Starr state that “. . . if the owner is entitled to recover the liquidated damages from the contractor, the contractor’s surety is also liable to the owner for the same amount of damages . . .” (1 Miller & Starr, Current Law of Cal. Real Estate (rev. ed. 1975) § 8.25, p. 363, fn. omitted [hereafter Miller & Starr]), but they cite two cases which do not wholly support this proposition. In the first, London Guar. & Acc. Co. *150 v. Las Lomitas School Dist. (1961) 191 Cal.App.2d423 [12 Cal.Rptr. 598], the completing surety was held liable for liquidated damages, but the dispute was about whether substantial evidence supported the trial court’s findings of fault on the part of the surety for the delay and whether another factual finding supported the judgment. There was no discussion of the legal question here under consideration. (Id., at pp. 425-426.) In the other (Dunne Inv. Co. v. Empire State S. Co. (1915) 27 Cal.App. 208 [150 P. 405]), the surety bond expressly incorporated the contract and expressly provided the surety would pay liquidated damages in the event that the contractor failed to complete the building on time. (Id., at p. 212.)

We find no authority supporting the proposition that the giving of a performance bond ipso facto subjects the completing surety to liability for liquidated damages provided for in the contract between the contractor and the obligee. To determine whether the completing surety is liable in such a case, the court must look to the contract and to the bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Piveg, Inc. v. General Star Indemnity Co.
193 F. Supp. 3d 1138 (S.D. California, 2016)
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
243 Cal. App. 4th 571 (California Court of Appeal, 2015)
Richards Industrial Park, LP v. Federal Deposit Insurance
572 F. App'x 499 (Ninth Circuit, 2014)
Fort Bragg Unified School District v. Colonial American Casualty & Surety Co.
194 Cal. App. 4th 891 (California Court of Appeal, 2011)
Mepco Services, Inc. v. Saddleback Valley Unified School District
189 Cal. App. 4th 1027 (California Court of Appeal, 2010)
First National Insurance v. Cam Painting, Inc.
173 Cal. App. 4th 1355 (California Court of Appeal, 2009)
East Quincy Services District v. General Accident Insurance Co. of America
105 Cal. Rptr. 2d 694 (California Court of Appeal, 2001)
Cates Construction, Inc. v. Talbot Partners
980 P.2d 407 (California Supreme Court, 1999)
Republic Bank v. Marine National Bank
45 Cal. App. 4th 919 (California Court of Appeal, 1996)
Boys Club of San Fernando Valley, Inc. v. Fidelity & Deposit Co.
6 Cal. App. 4th 1266 (California Court of Appeal, 1992)
Granite Computer Leasing Corp. v. Travelers Indemnity Co.
702 F. Supp. 415 (S.D. New York, 1988)
ITT Diversified Credit Corp. v. Highlands Insurance
191 Cal. App. 3d 301 (California Court of Appeal, 1987)
General Insurance v. Mammoth Vista Owners' Ass'n
174 Cal. App. 3d 810 (California Court of Appeal, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
158 Cal. App. 3d 145, 204 Cal. Rptr. 387, 1984 Cal. App. LEXIS 2296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-employers-insurance-v-city-of-berkeley-calctapp-1984.