Great American Insurance Company v. The Weitz Company, LLC

CourtDistrict Court, N.D. California
DecidedJuly 30, 2025
Docket3:25-cv-02079
StatusUnknown

This text of Great American Insurance Company v. The Weitz Company, LLC (Great American Insurance Company v. The Weitz Company, LLC) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Great American Insurance Company v. The Weitz Company, LLC, (N.D. Cal. 2025).

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 NORTHERN DISTRICT OF CALIFORNIA 6 7 GREAT AMERICAN INSURANCE Case No. 25-cv-02079-LJC COMPANY, 8 Plaintiff, ORDER GRANTING MOTION TO 9 COMPEL ARBITRATION v. 10 Re: Dkt. No. 11 THE WEITZ COMPANY, LLC, 11 Defendant.

12 13 Plaintiff Great American Insurance Company (Great American), a surety company, sued 14 The Weitz Company, LLC (Weitz), a general contractor, for breach of contract and declaratory 15 judgment relating to a dispute over a performance bond issued by Great American. Weitz 16 contends that these claims must be arbitrated and has moved to compel arbitration. ECF No. 11. 17 For the following reasons, Weitz’s motion to compel arbitration is granted.1 18 I. BACKGROUND 19 Weitz, part of a global construction conglomerate, is the general contractor for a 20 construction project (the Enso Project) in Healdsburg, California. ECF No. 1 (Compl.) ¶ 10; ECF 21 No. 20 at 16-17; see ECF No. 13. It solicited bids for subcontractors to complete HVAC work on 22 the Enso Project. ECF No. 20-2 ¶ 5. California Environmental Systems, Inc. (CES) submitted a 23 1 Great American’s request for judicial notice at ECF No. 20-4 is also granted. Great American 24 requests that the Court take notice of four exhibits consisting of filings from other litigation Weitz was a party to, from the Southern District of Ohio, the District of Arizona, and Sonoma County 25 Superior Court. Id. at 2. Federal Rule of Evidence 201 permits courts to take judicial notice of facts “not subject to reasonable dispute[,]” such as matters of public record. This “may include 26 court records[.]” United States v. Raygoza-Garcia, 902 F.3d 994, 1001 (9th Cir. 2018). Although a court may take judicial notice of the existence of such documents, it cannot take judicial notice 27 of “disputed facts contained in such public records.” Khoja v. Orexigen Therapeutics, Inc., 899 F. 1 bid, which Weitz selected. Id. ¶¶ 6, 8. CES is certified by the State of California as a small 2 business entity and, in 2021, had an average annual revenue of between $15 and $20 million. Id. 3 ¶¶ 2-3. After Weitz accepted CES’s bid for HVAC work on the Enso Project, Weitz sent CES a 4 form subcontract agreement and related documents, totaling 133 pages. Id. ¶ 8. CES requested 5 that certain terms regarding the scope of CES’s work be modified, which Weitz accepted. Id. ¶ 6 12. Weitz “refused to make” other requested revisions. Id. ¶¶ 12-20. CES and Weitz executed 7 the final subcontract (the Subcontract) for CES to complete HVAC work on the Enso Project in 8 June 2021. Compl. ¶ 10. 9 A. The Subcontract 10 The Subcontract governs CES and Weitz’s obligations to each other with respect to CES’s 11 work on the Enso Project.2 The Subcontract provides that the total sum payable to CES for proper 12 completion of CES’s work on the Enso Project is $7,358,386.52 (the Subcontract Sum), and, at 13 Exhibit A, details the scope of CES’s work. Compl. at 16-17, 18-74. There is no Exhibit B. 14 Exhibit C to the Subcontract lists “Special Terms and Conditions” that CES and Weitz must 15 comply with, such as CES using “battery-operated tools wherever and whenever possible” and 16 Weitz providing hardhats and safety vests to CES’s employees. Id. at 76-81. Exhibit D lists 17 “Standard Terms and Conditions,” including requirements for workplace safety, procedures for 18 modifying the scope of CES’s work, CES’s termination rights, and dispute resolution procedures. 19 Id. at 82-128. There is no Exhibit E or F to the Subcontract. Exhibit G lists CES’s insurance 20 requirements. Id. at 129-41. 21 The instant dispute turns primarily on terms in Exhibit D. Section 2.2 of Exhibit D 22 requires CES to obtain a performance bond from a surety guaranteeing that, in the event CES does 23 not fulfill its contractual obligations for its work on the Enso Project, the surety will complete or 24 pay for CES’s default. Id. at 89. The penal sum (that is, the maximum amount the surety would 25 pay) is equal to the Subcontract Sum. Id. Section 2.2 provides that the penal sum of the 26 performance bond “shall be automatically adjusted by any modifications” to the Subcontract Sum 27 1 and that the “surety waives all requirements for notice of modifications” of the Subcontract Sum 2 and penal sum. Id. It further provides that “reference to [the Subcontract] within the 3 Subcontractor’s performance bond, if any, shall be deemed as an express acknowledgment and 4 consent by surety to be bound by all duties, liabilities and obligations which Subcontractor has to 5 Contractor in the event of delays or time related damages suffered by Contractor as a result of 6 Subcontractor’s performance or failure to perform.” Id. 7 Section 9 of Exhibit D sets out “Claims and Dispute Resolution” procedures. Id. at 100. 8 In relevant part, section 9.1 provides:

9 The Subcontractor [CES] agrees to be conclusively bound by the Contractor’s [Weitz’s] decisions on all matters, unless the 10 Subcontractor disputes such decision in writing within seven (7) calendar days following receipt of the Contractor’s decision. In the 11 event of any dispute, controversy or Claim (“Claim”) between the Contractor and Subcontractor arising out of or related to the 12 Subcontract Documents or the breach thereof, each party shall promptly notify the other upon discovery of any Claim, and shall in 13 good faith meet to resolve the Claim by mutual agreement…

14 Id. Section 9.2 (the Arbitration Provision) specifies that:

15 Any Claim not resolved under item 9.1 shall, at the option of the Contractor, be determined by arbitration in accordance with the 16 Federal Arbitration Act. The arbitrator shall address all then pending and unresolved Claims…The Contractor and Subcontractor shall 17 mutually select an independent arbitrator within five (5) working days following notice of intent to arbitrated delivered by Contractor to 18 Subcontractor…The award rendered by the arbitrator shall be final, and judgment may be entered upon it in accordance with applicable 19 law in any court having jurisdiction thereof… 20 Id. Section 9.3 provides that if Weitz elects not to arbitrate a claim, then “all requirements and 21 conditions…pertaining to arbitration shall be deemed appropriated adjusted to permit (i) 22 Contractor to pursue such Claims at any times as otherwise permitted or required by the 23 Subcontract Documents or by law or equity” and to permit CES “to pursue all Claims through a 24 single litigation at any time after substantial completion of the Project[.]” Id. Section 9.6 provides 25 that section 9 shall not be deemed a limitation of rights or remedies which the parties may have 26 under state mechanics’ lien laws, public contract claims laws or under applicable performance 27 bonds or payment bonds. Id. at 101. 1 and related documents. It provides that the agreement between CES and Weitz consists of the 2 two-page Subcontract, the exhibits to the Subcontract, any modifications to the Subcontract, 3 CES’s payment and performance bonds, and the prime contract (the contract between Weitz and 4 the property owner), collectively referred to as the “Subcontract Documents.” Id. at 88. It 5 provides that, in the event of any conflicts between the Subcontract Documents, the provisions 6 govern in the following order of priority: 1) modifications to the Subcontract, 2) Exhibit F to the 7 Subcontract, if any, 3) Exhibit A to the Subcontract, 4) the Subcontract, 5) Exhibit C to the 8 Subcontract, 6) Exhibit G to the Subcontract, if any, 7) Exhibit D to the Subcontract, 8) Exhibit B 9 to the Subcontract, 9) any other exhibits to the Subcontract in letter order, 9) the performance and 10 payment bonds, and 10) the prime contract. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
Joyce Bickerstaff v. Vassar College
196 F.3d 435 (Second Circuit, 1999)
Jessica Kramer v. Toyota Motor Corporation
705 F.3d 1122 (Ninth Circuit, 2013)
Zenia Chavarria v. Ralphs Grocery Company
733 F.3d 916 (Ninth Circuit, 2013)
Pacific Employers Insurance v. City of Berkeley
158 Cal. App. 3d 145 (California Court of Appeal, 1984)
First National Insurance v. Cam Painting, Inc.
173 Cal. App. 4th 1355 (California Court of Appeal, 2009)
Boys Club of San Fernando Valley, Inc. v. Fidelity & Deposit Co.
6 Cal. App. 4th 1266 (California Court of Appeal, 1992)
Concat Lp v. Unilever, Plc
350 F. Supp. 2d 796 (N.D. California, 2004)
Fidelity & Deposit Co. v. Parsons & Whittemore Contractors Corp.
397 N.E.2d 380 (New York Court of Appeals, 1979)
Armendariz v. Found. Health Psychcare Servs., Inc.
6 P.3d 669 (California Supreme Court, 2000)
Grand Prospect Partners v. Ross Dress for Less, Inc.
232 Cal. App. 4th 1332 (California Court of Appeal, 2015)
Baltazar v. Forever 21, Inc.
367 P.3d 6 (California Supreme Court, 2016)
Aalwyn's Law Institute v. Martin
159 P. 158 (California Supreme Court, 1916)
Lorrie Poublon v. C.H. Robinson Co.
846 F.3d 1251 (Ninth Circuit, 2017)
United States v. Noe Raygoza-Garcia
902 F.3d 994 (Ninth Circuit, 2018)
Witherby v. Thomas
55 Cal. 9 (California Supreme Court, 1880)

Cite This Page — Counsel Stack

Bluebook (online)
Great American Insurance Company v. The Weitz Company, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/great-american-insurance-company-v-the-weitz-company-llc-cand-2025.