Trinity Universal Insurance Company and First National Bank in Dallas v. United States

382 F.2d 317, 20 A.F.T.R.2d (RIA) 5479, 1967 U.S. App. LEXIS 5139
CourtCourt of Appeals for the First Circuit
DecidedSeptember 12, 1967
Docket24246
StatusPublished
Cited by67 cases

This text of 382 F.2d 317 (Trinity Universal Insurance Company and First National Bank in Dallas v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trinity Universal Insurance Company and First National Bank in Dallas v. United States, 382 F.2d 317, 20 A.F.T.R.2d (RIA) 5479, 1967 U.S. App. LEXIS 5139 (1st Cir. 1967).

Opinion

RIVES, Circuit Judge.

This case presents the clear-cut issue of whether, when a Miller Act 1 surety completes a defaulted contract pursuant to its performance bond, the government may set off taxes owed by the contractor against the surety’s claim to the fund retained by the government to insure performance.

Dallas Building, Inc., the contractor, was awarded a contract for the construction of a nuclear warfare laboratory at Kirtland Air Force Base, Albuquerque, New Mexico, for the total sum of $1,-008,889.36.

Trinity Universal Insurance Company, the surety, executed for the contractor the two bonds required by the Miller Act; one to guarantee performance and the other payment of laborers and material-men for work done. When 90% of the contract had been completed and most of the progress payments made, the contractor defaulted and its right to proceed further was terminated by the government. The retained, unpaid amount earned by the contractor was then $39,-906.96, and the amount to be earned upon completion of the remaining work was $67,276.16. Federal unemployment, withholding and F.I.C.A. tax liabilities of the contractor in the amount of $6,-495.07 were unpaid. 2

The surety, in discharge of its obligations, agreed with the government to *319 take over and complete the contract. The surety thereafter expended the amount of $116,623.37 for the work done. It was paid for that work by the government the sum of $67,276.16. In addition, on October 14, 1965, the government paid the surety $33,411.89, the retainage for work done by the contractor less the $6,-495.07 owed by the contractor for taxes. In this suit the surety seeks to recover the $6,495.07 setoff.

Upon some of the principles of law in-' volved, the surety and the government are in agreement, viz: 1) The government has no claim against the surety by reason of the taxes of the contractor. 3 2) The surety has certain equitable or derivative rights, such as rights acquired through subrogation or assignment. 4 3)

The surety is subrogated to the rights of the contractor, but such rights will, of course, not suffice because the government has a valid setoff against the contractor. 5

The decisive question in dispute between the parties is whether a surety under a Miller Act performance bond which, under agreement with the government, completes the contract upon contractor’s default and expends in such completion more than the full contract price has a right to have the contract price, free from setoff, applied to the completion of the project.

The surety’s claim was rejected by the district court upon the authority of United States v. Munsey Trust Co., 1947, 332 U.S. 234, 67 S.Ct. 1599, 91 L.Ed. 2022. In that case the contractor had failed to pay materialmen and laborers and they had been paid by the surety on the payment bond. The Court held that the laborers and materialmen paid by the surety had no rights to which the surety could be subrogated, and rejected the surety’s claim to the retainage free from setoff. The Court noted, however, that a distinction might exist in the case of a surety which chose to complete the contract under its performance bond:

“Respondent argues that if the work had not been completed, and the surety chose not to complete it, the surety would be liable only for the amount necessary to complete, less the retained money. Moreover, if the surety did complete the job, it would be entitled to the retained moneys in addition to progress payments. The situation here is said to be similar. But when a job is incomplete, the government must expend funds to get the work done, and is entitled to claim damages only in the amount of the excess which it pays for the job over what it would have paid had the contractor not defaulted. Therefore, a surety would rarely undertake to complete a job if it incurred the risk that by completing it might lose more than if it had allowed the government to proceed. When laborers and materialmen, however, are unpaid and the work is complete, the government suffers no damage. The work has been done at the contract price. The government cannot suffer damage because it is under *320 no legal obligation to pay the laborers and materialmen. In the case of the laborers’ bond, the surety has promised that they will be paid, not, as in the case of performance bond, that work will be done at a certain price. The law of damages is therefore not pertinent to the payment bond.” 332 U.S. at 244, 67 S.Ct. at 1604.

In Pearlman v. Reliance Insurance Co., 1962, 371 U.S. 132,138, 83 S.Ct. 232, 236, 9 L.Ed.2d 190, the Supreme Court recognized the well-established doctrine that “a surety who completes a t contract has an ‘equitable right’ to indemnification out of a retained fund.” 6 Munsey did not disturb this rule, for as the Court noted in Pearlman:

“We held that the Government could exercise the well-established common-law right of debtors to offset claims of their own against their creditors. This was all we held. * * * We hold that Munsey left the rule in Prairie Bank and Henningsen [infra] undisturbed.” 371 U.S. at 140, 141, 83 S.Ct. at 237.

The rights of the surety in Munsey were those of a subrogee of the contractor. Whoever, be it the contractor or his surety, pays the laborers and material-men would be a creditor of the government insofar as the retained funds are concerned. Pearlman at p. 141, 83 S.Ct. 232. Of course, however, the government has a right to set off claims against its creditors.

A different situation occurs when the surety completes the performance of a contract. The surety is not only a subrogee of the contractor, and therefore a creditor, but also a subrogee of the government and entitled to any rights the government has to the retained funds. 7 If the contractor fails to complete the job, the government can apply the retained funds and any remaining progress money to costs of completing the job. The surety is liable under the performance bond for any damage incurred by the government in completing the job. On the other hand, the surety may undertake to complete the job itself. In so doing, it performs a benefit for the government, and has a right to the retained funds and remaining progress money to defray its costs. The surety who undertakes to complete the project is entitled to the funds in the hands of the government not as a creditor and subject to setoff, but as a subrogee having the same rights to the funds as the government. 8

We recognize that our holding is in conflict with that of the Court of Claims in Standard Accident Insurance Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-Con, Inc.
Armed Services Board of Contract Appeals, 2017
Jutte Elec., Ltd. v. Ohio Facilities Constr. Comm.
2016 Ohio 8580 (Ohio Court of Claims, 2016)
Harris County Flood Control District v. Great American Insurance Co.
359 S.W.3d 736 (Court of Appeals of Texas, 2011)
Travelers Indemnity Co. v. United States
72 Fed. Cl. 56 (Federal Claims, 2006)
Nova Casualty Co. v. United States
69 Fed. Cl. 284 (Federal Claims, 2006)
National Fire Insurance v. Fortune Construction Co.
320 F.3d 1260 (Eleventh Circuit, 2003)
Federal Insurance v. Maine Yankee Atomic Power Co.
183 F. Supp. 2d 76 (D. Maine, 2001)
Miller-Stauch Construction Co. v. Williams-Bungart Electric, Inc.
959 S.W.2d 490 (Missouri Court of Appeals, 1998)
Fidelity & Deposit Co. of Maryland v. United States
39 Cont. Cas. Fed. 76,675 (Federal Claims, 1994)
In re Modular Structures, Inc.
27 F.3d 72 (First Circuit, 1994)
Liberty Mutual Insurance Co. v. Sharp
874 S.W.2d 736 (Court of Appeals of Texas, 1994)
Transamerica Insurance Company v. The United States
998 F.2d 972 (Federal Circuit, 1993)
Hartford Accident & Indemnity Co v. Arizona Department of Transportation
838 P.2d 1325 (Court of Appeals of Arizona, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
382 F.2d 317, 20 A.F.T.R.2d (RIA) 5479, 1967 U.S. App. LEXIS 5139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trinity-universal-insurance-company-and-first-national-bank-in-dallas-v-ca1-1967.