OPINION AND ORDER ON STIPULATED RECORD
GENE CARTER, Chief Judge.
This case involves an interpleader action initiated by Centex-Simpson Construction Company, Inc. (“Plaintiff” or “Centex”) against Fidelity & Deposit Company of Maryland (“Fidelity”), The Fels Company, Inc. (“Fels”), and the Federal Deposit Insurance Corporation (“FDIC”).
Fidelity filed on
March 25, 1991, a counterclaim against Centex, cross-claims against Fels and the FDIC, and a third-party claim against Donald and Cynthia Gleason. NMNB filed a counterclaim against Centex on March 27, 1991.
The parties originally submitted motions for summary judgment but, during a pretrial conference held on December 18, 1991, at the suggestion of the Court,
see Boston Five Cents Savings Bank v. Secretary of Department of Housing and Urban Development,
768 F.2d 5, 11-12 (1st Cir.1985), they agreed to submit cross-motions for judgment on a stipulated record. On January 24, 1992, Centrex, Fidelity, and the FDIC submitted to the Court their cross-motions and the stipulated record.
This procedural device requires the Court to decide the case on its merits, based on the stipulated record. For the reasons that follow, the Court finds that Fidelity is entitled to the interpleaded funds.
I.
On May 2, 1983, Fels executed and delivered to MNB a security agreement that provided MNB with a security interest in Fels’ accounts receivable.
See
S.R., Joint Exhibit A. MNB perfected its security interest in Fels’ accounts receivable by filing financing and continuation statements under 11 M.R.S.A. sections 9-302, 401 with the Maine Secretary of State on May 4, 1983, and March 9, 1988.
See
S.R., Joint Exhibits B-C. MNB made several loans to Fels, which were secured in part by the security agreement, including loans of $50,-000 on January 21, 1987; $150,000 on March 19, 1987; $200,000 on October 29, 1987; and $1,200,000 on August 25, 1989.
On September 29, 1988, Fels, as subcontractor, entered into a subcontract with Centex, the general contractor, to perform mechanical work in connection with a federal construction project at the Veterans Administration Medical/Regional Office Center (“VA”) in Togus, Maine. On the same date, Fidelity, as surety, issued to Centex payment and performance bonds required by the Miller Act, 40 U.S.C. section 270(a)
et seq.,
as obligee, to cover the subcontract obligations of Fels, as principal, in connection with the project.
See
A.S.R., ¶ C; S.R., Joint Exhibits D-E. Such bonds were required by the subcontract between Centex and Fels.
On or about January 18, 1991, NMNB provided Centex with written notice of (a) the bank’s security interest in all accounts receivables of Fels, (b) Fels’ default on its obligations to the bank and (c) the bank’s entitlement to all amounts due and owing from Centex to Fels.
As Receiver for NMNB, the FDIC is the holder of a judgment in the amount of $1,296,059.03, plus interest, against Fels obtained in an action brought by NMNB for Fels’ default on the four loans from the bank secured, in part, by Fels’ accounts receivable.
As of January 6, 1991, Fels owed substantial sums to its suppliers of labor and materials in connection with the construction project.
On January 24, 1991, Centex notified Fels by letter that it had defaulted on its subcontract obligations. Fels had failed to complete all of the work described in that letter.
See
S.R., Exhibit J.
On February 27, 1991, Centex deposited with the Clerk of this Court $90,713.32,
and commenced an interpleader action, requesting that the Court determine ownership of the funds in question. Thereafter, on the same date, Fels notified Centex that it had “improperly forced [it] into default due to lack of payment. As a result, [it] terminated [its] work force as of 3:30 PM th[at] date.” S.R., Joint Exhibit 0. On March 1, 1991, Centex terminated Fels’ right to proceed under the subcontract. Centex hired another company as a substitute subcontractor to complete the mechanical work.
As surety for Fels, Fidelity has paid Cen-tex $422,911.62 pursuant to its performance bond obligations to reimburse Centex for payments made to complete the mechanical work on the project. Fidelity, however, has withheld $90,713.32, the amount of the interpleaded funds, from the funds that were due either Centex or Fidelity for the purpose of completing the mechanical subcontract. In addition, Fidelity has paid $214,446.04 pursuant to its payment bond obligations to those who supplied labor and materials to Fels in connection with the project.
Fels has never made any claim in the interpleader action to the $90,713,32 or to any other funds due to it on account of the subcontract between Centex and Fels. Moreover, Fels has never received any judgment entitling it to the $90,713.32 or to any other funds, based on this subcontract. The current dispute over the ownership of this fund is strictly one between Fidelity and the FDIC as Receiver of NMNB.
II.
The crux of this dispute between Fidelity and the FDIC regarding the ownership of the interpleaded fund turns on whether Fels ever acquired title to the $90,-713.32. Fidelity argues that title to the fund never passed to Fels because Fidelity became entitled to it, based on its surety relationship to Fels and its right of subrogation that arose in “investing hundreds of thousands of dollars to effect performance of the mechanical work.” Reply Memorandum of Law of Fidelity in Support of its Motion for Judgment on a Stipulated Record at 1-2. The FDIC argues that the “security interest acquired by the Bank ... is the tangible asset which the
D’Oench, Duhme
doctrine is intended to protect.” Reply Memorandum of Law of Defendant FDIC at 3. Furthermore, it asserts that the interpleaded funds are part of that asset because they constitute a portion of the payments owed to Fels by Centex for work performed by Fels.
Id.
The FDIC concludes that the agreements related to Fidelity’s suretyship arrangement with
Fels and Centex do not comply with the
D’Oench, Duhme
doctrine and its statutory requirements under section 1823(e) and, hence, Fidelity’s claim is barred by the doctrine.
Id.
at 3-4.
The issue presented is one of first impression in this district; whether the
D’Oench, Duhme
doctrine,
see D’Oench, Duhme & Co. v. FDIC,
315 U.S. 447, 460, 62 S.Ct.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION AND ORDER ON STIPULATED RECORD
GENE CARTER, Chief Judge.
This case involves an interpleader action initiated by Centex-Simpson Construction Company, Inc. (“Plaintiff” or “Centex”) against Fidelity & Deposit Company of Maryland (“Fidelity”), The Fels Company, Inc. (“Fels”), and the Federal Deposit Insurance Corporation (“FDIC”).
Fidelity filed on
March 25, 1991, a counterclaim against Centex, cross-claims against Fels and the FDIC, and a third-party claim against Donald and Cynthia Gleason. NMNB filed a counterclaim against Centex on March 27, 1991.
The parties originally submitted motions for summary judgment but, during a pretrial conference held on December 18, 1991, at the suggestion of the Court,
see Boston Five Cents Savings Bank v. Secretary of Department of Housing and Urban Development,
768 F.2d 5, 11-12 (1st Cir.1985), they agreed to submit cross-motions for judgment on a stipulated record. On January 24, 1992, Centrex, Fidelity, and the FDIC submitted to the Court their cross-motions and the stipulated record.
This procedural device requires the Court to decide the case on its merits, based on the stipulated record. For the reasons that follow, the Court finds that Fidelity is entitled to the interpleaded funds.
I.
On May 2, 1983, Fels executed and delivered to MNB a security agreement that provided MNB with a security interest in Fels’ accounts receivable.
See
S.R., Joint Exhibit A. MNB perfected its security interest in Fels’ accounts receivable by filing financing and continuation statements under 11 M.R.S.A. sections 9-302, 401 with the Maine Secretary of State on May 4, 1983, and March 9, 1988.
See
S.R., Joint Exhibits B-C. MNB made several loans to Fels, which were secured in part by the security agreement, including loans of $50,-000 on January 21, 1987; $150,000 on March 19, 1987; $200,000 on October 29, 1987; and $1,200,000 on August 25, 1989.
On September 29, 1988, Fels, as subcontractor, entered into a subcontract with Centex, the general contractor, to perform mechanical work in connection with a federal construction project at the Veterans Administration Medical/Regional Office Center (“VA”) in Togus, Maine. On the same date, Fidelity, as surety, issued to Centex payment and performance bonds required by the Miller Act, 40 U.S.C. section 270(a)
et seq.,
as obligee, to cover the subcontract obligations of Fels, as principal, in connection with the project.
See
A.S.R., ¶ C; S.R., Joint Exhibits D-E. Such bonds were required by the subcontract between Centex and Fels.
On or about January 18, 1991, NMNB provided Centex with written notice of (a) the bank’s security interest in all accounts receivables of Fels, (b) Fels’ default on its obligations to the bank and (c) the bank’s entitlement to all amounts due and owing from Centex to Fels.
As Receiver for NMNB, the FDIC is the holder of a judgment in the amount of $1,296,059.03, plus interest, against Fels obtained in an action brought by NMNB for Fels’ default on the four loans from the bank secured, in part, by Fels’ accounts receivable.
As of January 6, 1991, Fels owed substantial sums to its suppliers of labor and materials in connection with the construction project.
On January 24, 1991, Centex notified Fels by letter that it had defaulted on its subcontract obligations. Fels had failed to complete all of the work described in that letter.
See
S.R., Exhibit J.
On February 27, 1991, Centex deposited with the Clerk of this Court $90,713.32,
and commenced an interpleader action, requesting that the Court determine ownership of the funds in question. Thereafter, on the same date, Fels notified Centex that it had “improperly forced [it] into default due to lack of payment. As a result, [it] terminated [its] work force as of 3:30 PM th[at] date.” S.R., Joint Exhibit 0. On March 1, 1991, Centex terminated Fels’ right to proceed under the subcontract. Centex hired another company as a substitute subcontractor to complete the mechanical work.
As surety for Fels, Fidelity has paid Cen-tex $422,911.62 pursuant to its performance bond obligations to reimburse Centex for payments made to complete the mechanical work on the project. Fidelity, however, has withheld $90,713.32, the amount of the interpleaded funds, from the funds that were due either Centex or Fidelity for the purpose of completing the mechanical subcontract. In addition, Fidelity has paid $214,446.04 pursuant to its payment bond obligations to those who supplied labor and materials to Fels in connection with the project.
Fels has never made any claim in the interpleader action to the $90,713,32 or to any other funds due to it on account of the subcontract between Centex and Fels. Moreover, Fels has never received any judgment entitling it to the $90,713.32 or to any other funds, based on this subcontract. The current dispute over the ownership of this fund is strictly one between Fidelity and the FDIC as Receiver of NMNB.
II.
The crux of this dispute between Fidelity and the FDIC regarding the ownership of the interpleaded fund turns on whether Fels ever acquired title to the $90,-713.32. Fidelity argues that title to the fund never passed to Fels because Fidelity became entitled to it, based on its surety relationship to Fels and its right of subrogation that arose in “investing hundreds of thousands of dollars to effect performance of the mechanical work.” Reply Memorandum of Law of Fidelity in Support of its Motion for Judgment on a Stipulated Record at 1-2. The FDIC argues that the “security interest acquired by the Bank ... is the tangible asset which the
D’Oench, Duhme
doctrine is intended to protect.” Reply Memorandum of Law of Defendant FDIC at 3. Furthermore, it asserts that the interpleaded funds are part of that asset because they constitute a portion of the payments owed to Fels by Centex for work performed by Fels.
Id.
The FDIC concludes that the agreements related to Fidelity’s suretyship arrangement with
Fels and Centex do not comply with the
D’Oench, Duhme
doctrine and its statutory requirements under section 1823(e) and, hence, Fidelity’s claim is barred by the doctrine.
Id.
at 3-4.
The issue presented is one of first impression in this district; whether the
D’Oench, Duhme
doctrine,
see D’Oench, Duhme & Co. v. FDIC,
315 U.S. 447, 460, 62 S.Ct. 676, 680-81, 86 L.Ed. 956 (1942), and 12 U.S.C. section 1823(e) may be invoked by FDIC as receiver to defeat the claims of a performing Miller Act surety under its right of equitable subrogation. For the reasons that follow, the Court finds that the doctrine in either its common law or statutory form cannot be invoked in the instant case to bar successfully Fidelity’s claims against the funds in Centex’s possession based on its rights as a performing surety.
A.
The
D’Oench, Duhme
doctrine and its statutory codification under section 1823(e) cannot be invoked in this case because the Court finds that the funds in question never became the property of Fels, which did not complete its performance as a subcontractor, and, hence, FDIC’s security interest in Fels’ accounts receivable does not include the earned but unpaid payments represented by the interpleaded funds. As a result, those funds cannot be found to be an asset “acquired by” Fels and, therefore, by the FDIC. The Court makes this finding based on suretyship law and, in particular, the doctrine of equitable subrogation.
Under equitable subrogation,
surety claims arising under construction projects, including those governed by the Miller Act, must be satisfied before the subcontractor and its creditors become entitled to any contract funds.
See, e.g., Pearlman v. Reliance Insurance Co.,
371 U.S. 132, 137, 83 S.Ct. 232, 235, 9 L.Ed.2d 190 (1962) (“[A] surety who pays the debt of another is entitled to all the rights of the person he paid to enforce his right to be reimbursed.”);
National Shawmut Bank v. New Amsterdam Casualty Co.,
411 F.2d 843, 848-49 (1st Cir.1969) (Miller Act surety’s right of subrogation prevailed over the bank’s security interest in earned but unpaid contract funds).
In the seminal Supreme Court case of
Pearlman,
a bankruptcy trustee and a surety each claimed the superior right to
retainage withheld by the United States out of earnings due a contractor whose contract with the United States had been terminated.
Id.
371 U.S. at 133, 83 S.Ct. at 233. The United States, as owner, had been authorized to retain “a percentage of estimated amounts due monthly until final completion and acceptance of all work covered by the contract.”
Id.
at 134, 83 S.Ct. at 233. The
Pearlman
Court held that the retainage never became the “property” of the contractor or, hence, his bankruptcy estate,
and concluded that the surety, not the bankruptcy trustee, was entitled to the withheld funds:
We therefore hold in accord with the established legal principles stated above that the Government [owner] had a right to use the retained fund to pay laborers and materialmen; that the laborers and materialmen had a right to be paid out of the fund; that the contractor [subcontractor], had he completed his job and paid his laborers and materialmen, would have become entitled to the fund; and that the surety, having paid the laborers and materialmen, is entitled to the benefit of all these rights to the extent necessary to reimburse it. Consequently, since the surety in this case has paid out more than the amount of the existing fund, it has a right to all of it.
Id.
at 141-42, 83 S.Ct. at 237.
Thus, the doctrine of equitable subrogation, grounded in equity not contract, protects the Miller Act completing surety by ensuring that such surety has priority over other parties with respect to either unpaid progress payments or retainages of the defaulting subcontractor.
B.
Here, the Court finds that the aforementioned cases dictate the proper resolution
of the present case. Fels, a subcontractor, executed a security agreement with MNB, assigning its accounts receivable as collateral to MNB for several promissory notes.
Such accounts receivable would include earned but unpaid progress payments owed by Centex, the general contractor, to Fels, the subcontractor, for work
completed
on the construction project for which Fels had been hired by Centex.
With respect to that construction project, Fidelity, Centex, and Fels executed Miller Act Subcontract Performance, and Labor and Material Payment Bonds. The Performance Bond specifically stated:
If the Surety arranges completion or remedies the default, that portion of the balance of the subcontract price as may be required to complete the subcontract or remedy the default and to reimburse the Surety for its outlays shall be paid to the Surety at the times and in the manner as said sums would have been payable to Principal had there been no default under the subcontract.
S.R., Joint Exhibit E. Because of Fels’ default, Fidelity, as surety, arranged and paid for the cost of completion of the contract with another subcontractor. As a result, Fels never acquired ownership of Centex’s funds because Fels did not complete its performance under the contract. Correspondingly, such funds never became a part of Fels’ accounts receivable, and thus not an “asset” subject to the FDIC’s security interest in Fels’ accounts receivable. In the absence of an asset, then, the
D’Oench, Duhme
doctrine on the FDIC’s behalf cannot be invoked.
Cf. Twin Construction, Inc. v. Boca Raton, Inc.,
925 F.2d 378, 382 (11th Cir.1991);
Bateman v. FDIC,
766 F.Supp. 1194, 1201 (D.Me.1991). Accordingly, the Court finds that the right to ownership of the interpleaded funds in the amount of $90,713.32 is in Fidelity, not the FDIC.
III.
In an interpleader action, the Court of Appeals for the First Circuit has stated
the standard for determining who pays for the award of fees and costs as follows: “An interpleader fee is usually awarded out of the fund to compensate a totally disinterested stakeholder who has been, by reason of the possession of the fund, subjected to conflicting claims through no fault of its own.”
Ferber Co. v. Ondrick,
310 F.2d 462, 467 (1st Cir.1962),
cert. denied,
373 U.S. 911, 83 S.Ct. 1300, 10 L.Ed.2d 412 (1963) (footnote omitted).
See also
7 C. Wright, A. Miller & M. Kane,
Federal Practice and Procedure
§ 1719, at 629-30, 632-33 (2d ed. 1986).
The Court concludes that Centex is a disinterested stakeholder and, that it “brought this action based on its good faith belief that there was a threat of possible multiple litigation ... [and that it] sought and did not receive clear direction from fidelity [sic] as to what to do with the $90,713.32 progress payment.”
See
Motion for Judgment on Stipulated Facts at 2. No evidence exists in the record that Centex’s conduct warrants taxing costs and attorneys’ fees directly against it. Therefore, the Court concludes that the award of costs and attorneys’ fees should be paid to Cen-tex directly out of the interpleaded funds.
IV.
Accordingly, it is hereby ORDERED that the interpleaded funds in the amount of Ninety Thousand Seven Hundred Thirteen Dollars and Thirty-Two Cents ($90,713.32), plus interest and costs, be awarded to Fidelity & Deposit Company of Maryland, less the amount of reasonable attorneys’ fees and costs.
Counsel shall confer forthwith and make a good faith attempt to agree upon reasonable attorneys’ fees, and costs and shall file, on or before June 8, 1992, written submissions on the issues generated in respect to assessment of reasonable attorneys’ fees or an agreed-upon resolution of such issues. In the absence of agreement, the Court will resolve any such issues upon the written submissions.