The Ferber Company v. Theodore J. Ondrick

310 F.2d 462, 1962 U.S. App. LEXIS 3471
CourtCourt of Appeals for the First Circuit
DecidedNovember 28, 1962
Docket6015_1
StatusPublished
Cited by32 cases

This text of 310 F.2d 462 (The Ferber Company v. Theodore J. Ondrick) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Ferber Company v. Theodore J. Ondrick, 310 F.2d 462, 1962 U.S. App. LEXIS 3471 (1st Cir. 1962).

Opinion

ALDRICH, Circuit Judge.

Ferber, short for two New Jersey corporations, joint venturers, was the prime contractor engaged in the construction of a housing project for a government Air Force base in Chicopee, Massachusetts. In August, 1958 Ferber entered into a subcontract with two other joint venturers, Ondrick, a citizen of Massachusetts, and Wilbraham Construction Corporation, a Massachusetts corporation, to do certain clearing, excavation, filling and drainage. It appeared that Ondrick and Wilbraham were equipped to do different parts of this work and desired separate contracts, but Ferber required a single agreement. After the work had been completed and $46,508 of the contract price remained to be paid, Wilbraham went into bankruptcy. Ferber thereupon filed a statutory inter-pleader (28 U.S.C. § 1335) in the Massachusetts district court against Ondrick, Wilbraham and their joint surety, and Wilbraham’s trustee in bankruptcy, naming also all alleged suppliers of labor and materials on their contract as to whom it had notice of claim. The complaint further alleged that Ondrick claimed as an individual, over and above the contract amount, $19,744 for labor, materials and the use of equipment. 1 Ferber paid the sum of $46,508 into court, alleged that this was the total amount due to all defendants, and prayed that the defendants be required to interplead and settle their rights between themselves and that Ferber “be discharged from all liabilities in the premises. * * Ondrick filed an answer in which he admitted making a claim for $19,744 “not as part of the joint venture,” and by counterclaim demanded its payment. Ferber filed a motion to dismiss the counterclaim, which motion was denied. Following trial without jury the court found for Ondrick on his claim in the amount of $7,121, which it subsequently increased to $10,711. The court refused Ferber’s request for an allowance for counsel fees out of the fund, a so-called interpleader fee. Ferber appeals.

The first question is the correctness of the court’s refusal to dismiss the counterclaim on the ground that the parties had provided in the subcontract for arbitration. Assuming that Ondrick’s claim fell within the contract as extra work and was therefore arbitrable, we nevertheless think it clear that Ferber waived this right. Ferber could have brought a bill of strict interpleader solely with relation to the undisputed amount. But having elected, in addition, to raise a disputed claim, see F.R.Civ.P. Rule 22; Standard Surety & Casualty Co. v. Baker, 8 Cirv 1939, 105 F.2d 578, *465 it must take the consequences. It could not ask the court to declare that it owed only so much to Ondrick, and that the court should discharge it from his claim for extra work, and then, when Ondrick resisted such a declaration, demand that Ondrick arbitrate.

Next, Ferber asserts that a series of so-called releases executed from time to time by Ondrick in connection with progress payments bars recovery. These documents do not use the word “release” in the title, nor is it in the body of the instrument except with respect to liens upon the premises. Ondrick is not presently asserting liens. The documents were prepared by Ferber and are to be construed against it. We agree with the court in disregarding them.

We come, therefore, to the merits. The principal contract called for the erection of ninety-six structures, all of which were to have concrete cellars, with drainage fill under the concrete. By the end of September 1958 some of the foundations were ready for the fill. The principal contract required the fill to be placed and, in addition, to be “compacted.” Ferber took the position that all of this work was included in the subcontract and demanded that Ondrick do it. On-drick admitted responsibility for supplying the gravel at the locus, but denied any further obligation. On the evidence most favorable to Ondrick, one Cristello, Ferber’s superintendent, instructed Ondrick to place and compact the gravel, and stated that if this did not prove to be within the subcontract Ferber would pay extra for it. Ondrick thereafter did the filling and compacting for all ninety-six units, and presented a bill in the amount of |19,744.

The court found that installing the fill was not within the subcontract. This was a question of interpretation, and it is sufficient to say that we find the district court’s reasoning persuasive. 2 The contract provided further, under the subtitle “Change Orders Additions and Deductions” that “alterations” should not be effected except by written order of Ferber. No written order was given for this extra work. The court, however, found that Cristello had sufficient authority to alter the contract.

It is, of course, rudimentary that a contractual requirement that agreements be in writing may be waived. Lord Constr. Co. v. United States ex rel. W. E. Sexton Co., 3 Cir., 1928, 28 F.2d 340; Zarthar v. Saliba, 1933, 282 Mass. 558, 185 N.E. 367. The fact, however, that Cristello may have possessed authority to waive a writing, and substantially to enlarge the agreement, is of little help to Ondrick so far as the total amount of the recovery here involved is concerned. On his own testimony the top officials of Ferber informed Ondrick at some point that this work was within his original contract and must be done thereunder. According to Ferber’s evidence this took place in December 1958. Ondrick testified that he was entirely unable to place the date, but he admitted that this work lasted until December 1959 and that many individual unit jobs were done by him after Ferber’s interview, as result of pressure put on him by the top Ferber officials acting through the bonding company, although he constantly maintained that he was not required to do it. It cannot be said that Cristello’s promise to pay extra if this was in fact extra work remained in effect for jobs undertaken after Ferber’s repudiation thereof. The court made no finding which would enable us to separate the amount, or value, of the work done before Ferber’s repudiation and afterwards.

The court, however, made an alternative finding or ruling with which we agree, namely, that Ondrick was entitled to recover on a quantum meruit for unjust enrichment. Normally a party doing work without a contract for another party who has stated in advance *466 that he is not going to pay for it can have no claim. The facts, however, in the case at bar are peculiar. Ferber was obligated under its contract with the government to complete the units, including the placing and compacting of the drainage fill in question. Evidence which we need not detail compels the conclusion that if Ondrick and Wilbraham were not obligated to do this work, no one else was. In other words, if Ondrick had refused to do it, Ferber would have been obliged to obtain someone else. It loses nothing by paying Ondrick the fair value of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

in the Estate of Gus W. Riefler, Jr.
Court of Appeals of Texas, 2020
Hogan v. Jackson National Life Insurance
142 F. Supp. 3d 220 (D. Rhode Island, 2015)
Van Dusseldorp v. Kim Lean Ho
4 F. Supp. 3d 1069 (S.D. Iowa, 2014)
Sun Life v. Plaisted, et al.
2009 DNH 114 (D. New Hampshire, 2009)
Sun Life Assurance Co. of Canada v. Sampson
556 F.3d 6 (First Circuit, 2009)
Jackson v. Economou et al
2008 DNH 094 (D. New Hampshire, 2008)
Jackson National Life Insurance v. Economou
557 F. Supp. 2d 216 (D. New Hampshire, 2008)
SOUTH ADAMS SAVINGS BANK v. Martel
540 F. Supp. 2d 265 (D. Massachusetts, 2008)
Washington Mutual Bank, F.A. v. Macrae
18 Mass. L. Rptr. 499 (Massachusetts Superior Court, 2004)
Unum Life Insurance Co. of America v. Kelling
170 F. Supp. 2d 792 (M.D. Tennessee, 2001)
Goldsmith v. Pinez
84 F. Supp. 2d 228 (D. Massachusetts, 2000)
Foxborough Savings Bank v. Petrosian
84 F. Supp. 2d 172 (D. Massachusetts, 1999)
Pressman v. Estate of Steinvorth
860 F. Supp. 171 (S.D. New York, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
310 F.2d 462, 1962 U.S. App. LEXIS 3471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-ferber-company-v-theodore-j-ondrick-ca1-1962.