National Fire Insurance v. Fortune Construction Co.

320 F.3d 1260
CourtCourt of Appeals for the Eleventh Circuit
DecidedFebruary 7, 2003
Docket01-15124
StatusPublished
Cited by26 cases

This text of 320 F.3d 1260 (National Fire Insurance v. Fortune Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Fire Insurance v. Fortune Construction Co., 320 F.3d 1260 (11th Cir. 2003).

Opinion

VINSON, District Judge:

The primary issue presented by this appeal is whether a surety on construction contract performance and payment bonds issued on behalf of a subcontractor has superior rights to retained contract balances in the possession of the general contractor when the general contractor completed the performance and has unsatisfied claims against the defaulting subcontractor.

I. BACKGROUND

This case arises out of two construction projects — the Winston Park project in Coconut Creek, Florida, and the West Bric-kell project in Miami, Florida. As general contractor on the projects, Fortune Con1 struction Company (“Fortune”) entered into two separate subcontracts with Arkin Construction Company (“Arkin”) to build the two apartment complexes, the Winston Park Subcontract and the West Brickell Subcontract. National Fire Insurance Company (“National Fire”), as surety, issued on behalf of Arkin, as principal, performance and payment bonds for the two construction projects. The performance bond and payment bond documents for the Winston Park project were standard forms issued by the American Institute of Architects. 1 The performance bond and payment bond documents for the West Bric-kell project were drafted by National Fire with language that materially differed from the Winston Park bonds. Each of the performance bonds and each of the payment bonds incorporated the appropriate subcontract between Fortune and Ar-kin by reference.

During construction of the two projects, Arkin began experiencing financial difficulty. National Fire provided financing to Arkin for a short time, but later refused to' continue to finance Arkin. Both projects were behind schedule by this time. Arkin’s financial difficulties prompted Fortune and National Fire to enter into negotiations about what to do when Arkin defaulted. There was some discussion about National Fire procuring a completion contractor and about the possibility that Fortune could complete construction. The West Brickell project was near completion, but a substantial amount of work still needed to be done on the Winston Park project. Negotiations were still ongoing when, on May 29, 1997, Arkin abandoned both construction projects. On June 12, 1997, Fortune declared Arkin in default and notified National Fire accordingly.

A flurry of letters between the attorneys for Fortune and National Fire ensued. During this increasingly acrimonious exchange, National Fire contends that it tendered, or offered to tender, a completion contractor. While National Fire asserts that Fortune rejected this tender because Fortune wanted to complete construction itself, Fortune maintains that the tender was never made. Fortune demanded that National Fire perform its obligations under both performance bonds by completing the subcontracts. National Fire did not do so. While National Fire made payments to payment bond claimants on both projects, both of the construction projects were actually completed by Fortune as the *1264 general contractor, and Arkin is now a dissolved corporation.

' The construction subcontracts between Fortune and Arkin each contained a clause obligating Arkin to pay liquidated damages for delays in completing the projects. The Winston Park Subcontract provided for liquidated damages of $35 per day per incomplete apartment and $1,000 per day for incomplete common areas. The West Briekell Subcontract provided for liquidated damages after a specified date of $30 per day per incomplete apartment. Due to Arkin’s dilatory performance during the Winston Park and West Briekell construction, Fortune invoked these liquidated delay damages clauses before Arkin abandoned the projects. By the time Ar-kin defaulted, Arkin owed $1,693,500 in liquidated delay damages on the Winston Park project and $93,600 in liquidated delay damages on the West Briekell project. The subcontracts also made Arkin responsible for the acts and omissions of its own sub-subcontractors. Allied Fire Protection Systems (“Allied”), one of Arkin’s sub-subcontractors, failed to pay Davis-Bacon Act wages to its laborers for work performed on the West Briekell project, which apparently involved federally subsidized housing. Consequently, the Department of Labor jointly charged Fortune, Arkin, and Allied a total of $71,126 in back wages attributable to Allied’s improper payments, which Fortune paid.

In addition to the West Briekell Subcontract between Fortune and Arkin, the parties entered into a letter agreement dated January 15, 1996 (the same date as the West Briekell. Subcontract). This letter agreement recognized that the electrical work had been excluded from Arkin’s subcontract on the West Briekell project, but that Arkin had full responsibility for cost overages if the cost of the electrical work exceeded $669,000. Arkin’s responsibility was “either finding a replacement subcontractor” for the- electrical work at $669,000 or “issuing a credit change order to Fortune” for any amount incurred over and above $669,000. 2 However, this letter agreement was not listed as part of the contract documents in the West Briekell Subcontract, which contained two merger and integration clauses. During the West Briekell construction, Fortune’s original electrical subcontractor, Monohan’s Electric Co., defaulted and did not complete the electrical work. Arkin failed to provide another electrical contractor to complete the project within the fixed $669,000 price. In hiring another electrical contractor, Fortune incurred additional costs amounting to $404,118.81 in excess of $669,000, 3 for which Fortune claims a credit against Arkin.

*1265 After Fortune completed the two construction projects, Fortune presented National Fire with an accounting of its “performance” costs to complete the Arkin subcontracts. National Fire then prepared an accounting of the net remaining contract proceeds. 4 According to National Fire, the remaining contract proceeds exceeded Fortune’s costs of completion. National Fire requested that, according to the terms of the bonds, the unpaid contract balances be credited to the respective subcontracts and paid to National Fire, as the subrogee of Arkin. Fortune refused to pay National Fire the contract balances, claiming that it had superior right to the contract balances due to National Fire’s failure to perform on its performance bonds and because of Fortune’s right to set off the remaining contract claims Fortune had against Arkin. National Fire initiated this civil action against Fortune alleging assignment of Arkin’s rights under the subcontracts, equitable subrogation, and breach of the bond contracts. Fortune filed a counterclaim against National Fire for failure to perform under the performance bonds and failure to make the required payments under the payment bonds with respect to payments for Davis-Bacon Act violations, electrical overages, and the liquidated delay damages. Fortune also joined Arkin as a third party defendant responsible for the same damages, due to its breach of the two subcontracts.

Before trial, National Fire filed seven different motions for partial summary judgment. 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper v. Milliman, Inc.
M.D. Florida, 2025
Raeann Bayless v. Coloplast Corp
Eleventh Circuit, 2023
Allied World Nat'l Assurance Co. v. Md. Cas. Co.
357 F. Supp. 3d 1181 (S.D. Florida, 2019)
Jane McGinnis v. American Home Mortgage Servicing, Inc.
817 F.3d 1241 (Eleventh Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
320 F.3d 1260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-fire-insurance-v-fortune-construction-co-ca11-2003.