International Fidelity Insurance Company v. Americaribe-Moriarty JV

681 F. App'x 771
CourtCourt of Appeals for the Eleventh Circuit
DecidedFebruary 28, 2017
Docket16-14861
StatusUnpublished
Cited by5 cases

This text of 681 F. App'x 771 (International Fidelity Insurance Company v. Americaribe-Moriarty JV) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Fidelity Insurance Company v. Americaribe-Moriarty JV, 681 F. App'x 771 (11th Cir. 2017).

Opinion

MARTIN, Circuit Judge:

Americaribe-Moriarty JV (“Americar-ibe”) appeals the District Court’s order granting summary judgment for International Fidelity Insurance Company and Al-leghany Casualty Company (together, “Fidelity”) and denying its own motion for summary judgment. Fidelity was the surety on a performance bond issued for a subcontract between Americaribe, a general contractor, and Certified Pool Mechanics 1, Inc. (“CPM”). After Americar-ibe terminated CPM for defaulting on the subcontract, it notified Fidelity, as required by the bond, but also hired a new subcontractor. The parties dispute whether Americaribe’s hiring of a new subcontractor breached the notice requirements in the termination provisions of the bond. The District Court found Americaribe failed to properly comply with the bond’s notice requirements, and held that Fidelity was therefore not liable for the bond. After careful review, we affirm. The bond incorporated the subcontract, and Ameri-caribe did not comply with the notice requirements in the termination provisions of those documents.

I.

Americaribe entered into a written subcontract with CPM for the pool work at the Brickell CityCentre Super Structure project in Miami, Florida. The subcontract included a termination provision that required Americaribe to provide three-days notice before it could act to complete the job on its own:

12.2(a) Termination for Cause. If Subcontractor at any time ... fails to cure the default after the three (3) day notice in Article 11.2(a), Contractor shall be at liberty to terminate this Subcontract Agreement upon an additional three (3) day written notice mailed or delivered to Subcontractor and take possession of all materials on site and employ others to complete the Work.... If the expense incurred by Contractor in finishing the Work plus damages suffered by the Contractor exceed the unpaid balance to be paid under this Subcontract Agreement then the Subcontractor shall pay the difference to the Contractor.

Fidelity, as the surety, issued a performance bond on behalf of CPM with Ameri-caribe as obligee. Section 1 of the bond expressly incorporated the subcontract.

*773 The bond also included termination provisions. Section 3 set out three steps by which Americaribe could trigger Fidelity’s obligations under the bond, including a notice requirement in § 3.2:

§ 3 If there is no Owner Default under the Construction Contract, the Surety’s obligation under this Bond shall arise after
.1 the Owner first provides notice to the Contractor and the Surety that the Owner is considering declaring a Contractor Default. Such notice shall indicate whether the Owner is requesting a conference among the Owner, Contractor and Surety to discuss the Contractor’s performance....
.2 the Owner declares a Contractor Default, terminates the Construction Contract and notifies the Surety; and
.3 the Owner has agreed to pay the Balance of the Contract Price in accordance with the terms of the Construction Contract to the Surety or to a contractor selected to perform the Construction Contract.

Section 5 provided Fidelity with four options for completing CPM’s work after it was terminated, allowing Fidelity to elect the option that best mitigated its damages:

§ 5 When the Owner has satisfied the conditions of Section 3, the Surety shall promptly and at the Surety’s expense take one of the following actions:
§ 5.1 Arrange for the Contractor, with the consent of the Owner, to perform and complete the Construction Contract; § 5.2 Undertake to perform and complete the Construction Contract itself, through its agents or independent contractors;
§ 5.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract ...; or
§ 5.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances:
.1 After investigation, determine the amount for which it may be liable to the Owner and, as soon as practicable after the amount is determined, make payment to the Owner; or
.2 Deny liability in whole or in part and notify the Owner, citing the reasons for denial.

If Fidelity failed to elect an option “with reasonable promptness,” Americaribe had to provide Fidelity seven-days notice before it could enforce other remedies:

§ 6 If the Surety does not proceed as provided in Section 5 with reasonable promptness, the Surety shall be deemed to be in default on this Bond seven days after receipt of an additional written notice from the Owner to the Surety demanding that the Surety perform its obligations under this Bond, and the Owner shall be entitled to enforce any remedy available to the Owner.

II.

On August 17, 2015, Americaribe issued a notice of default to CPM and Fidelity, as called for by § 3 of the bond. In the notice, Americaribe requested a conference call with Fidelity “to substitute CPM’s scope ... with an alternative subcontractor.” On August 20, Fidelity responded to Ameri-caribe requesting more information and directing Americaribe “not to take any steps with respect to the completion of the project without the written consent of the Surety.” On September 2, the parties held a conference call.

On September 21, Americaribe sent CPM and Fidelity a letter terminating *774 CPM, notifying Fidelity, and agreeing to pay the balance of the contract price, consistent with § 3 of the bond and § 12.2 of the subcontract. However, on September 16, Americaribe got a proposal from Dillon Pools, Inc. for completing the work that remained on the subcontract. And on September 17, Dillon sent Americaribe a schedule with a presumed start date of September 21. Then on September 22, Am-ericaribe sent vendors of CPM a letter, again copying Fidelity, and informing them of CPM’s termination and that “[Am-ericaribe] intends to award the subcontract to complete the remaining work ... to Dillon.” As of September 23, Dillon had begun “supplementation work and on site investigations to determine corrective work required for the project.”

On October 1, Americaribe sent Fidelity the “additional written notice” required by § 6 of the bond, which started the seven-day clock toward Fidelity defaulting on its obligations under the bond. On October 8, Fidelity responded to Americaribe that its actions in engaging Dillon may have discharged Fidelity’s obligations under the bond. On October 9, Americaribe responded that Fidelity was in default of the bond for not acting under § 6 with reasonable promptness. On November 5, Fidelity issued a formal denial of Americaribe’s claim because Americaribe materially breached the bond “by commencing efforts to supplement CPM’s work before providing the Surety with an opportunity to remedy any alleged default.”

In the following months, Americaribe formalized its relationship with Dillon. On November 4, Dillon signed a subcontract with Americaribe.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
S.D. Florida, 2026
Wildewood Operations v. WRV Holdings
Court of Special Appeals of Maryland, 2023

Cite This Page — Counsel Stack

Bluebook (online)
681 F. App'x 771, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-fidelity-insurance-company-v-americaribe-moriarty-jv-ca11-2017.