Arch Insurance Company v. A3 Development, LLC, A3 North Development, LLC, A3 Amenities, LLC

CourtDistrict Court, S.D. Florida
DecidedMarch 6, 2026
Docket1:23-cv-23524
StatusUnknown

This text of Arch Insurance Company v. A3 Development, LLC, A3 North Development, LLC, A3 Amenities, LLC (Arch Insurance Company v. A3 Development, LLC, A3 North Development, LLC, A3 Amenities, LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arch Insurance Company v. A3 Development, LLC, A3 North Development, LLC, A3 Amenities, LLC, (S.D. Fla. 2026).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA

Case No. 23-cv-23524-BLOOM/Torres

ARCH INSURANCE COMPANY,

Plaintiff,

v.

A3 DEVELOPMENT, LLC, a foreign Limited liability company; A3 NORTH DEVELOPMENT, LLC, a foreign limited A liability company; and A3 AMENITIES, LLC, a foreign limited liability company,

Defendants. ________________________________/

OMNIBUS ORDER ON CROSS MOTIONS FOR SUMMARY JUDGMENT

THIS CAUSE is before the Court upon Defendants A3 Development, LLC (“A3 Development”), A3 North Development, LLC (“A3 North”), and A3 Amenities, LLC’s (“A3 Amenities”) (collectively “Defendants”) Motion for Summary Judgment, ECF No. [123]. Plaintiff Arch Insurance Company filed a Response in Opposition (“Plaintiff’s Response”), ECF No. [140], to which Defendants filed a Reply, ECF No. [150]. Also before the Court is Plaintiff’s Motion for Partial Summary Judgment as to Liability. ECF No. [129]. Defendants filed a Response in Opposition (“Defendants’ Response”), ECF No. [142], to which Plaintiff filed a Reply. ECF No. [151]. The Court has carefully reviewed the parties’ Motions, the submissions in support and in opposition, the record, and is otherwise fully advised. For the reasons that follow, Defendants’ Motion is denied, and Plaintiff’s Motion is granted. I. BACKGROUND A. Material Facts Based on the parties’ briefings, the statements of material facts, and the evidence in the record, the following facts are not genuinely in dispute unless otherwise noted by the Court.1 a. The Bonds (Coastal Bonds and A3 Bonds) Defendants are developers who set out to construct “a multi-tower condominium

development located at 17901 Collins Avenue and 17975 Collins Avenue in Sunny Isles Beach, Florida 33160, known as The Estates at Acqualina (the ‘Project’).” ECF No. [124] at ¶ 1. Defendants “originally retained Coastal Construction Group (‘Coastal’) to serve as the general contractor for the Project.” Id. at ¶ 3. Coastal hired various subcontractors for the Project, “including R&S Concrete South, Inc. (‘R&S Concrete’).” After being hired, R&S Concrete “entered into various written subcontracts with Coastal for concrete/shell and masonry work [for] the Project (the ‘Subcontracts’),” and commenced work on the Project in October of 2018. Id. at ¶¶ 4-5. Plaintiff is in the business of providing surety bonds. In connection with the Subcontracts, Plaintiff issued the following “four (4) performance bonds on behalf of R&S Concrete, as

principal, and in favor of Coastal, as obligee, and [Defendants] as additional obligees: (i) Bond

1 Before setting out the facts in this case, the Court notes that Defendants failed to file a proper response to Plaintiff’s Statement of Material Undisputed Facts in accordance with the Local Rules. See S.D. Fla. L.R. Rule 56.1(b)(2). Rather than filing a response that “correspond[ed] with the order and paragraph numbering format used by the movant,” starting every paragraph-by-paragraph response [with] the word ‘disputed’ or ‘undisputed[,]’” and providing specific evidentiary citations in support of the disputed facts, Defendants simply refiled the Statement of Material Facts they relied upon in support of their own Motion for Summary Judgment. Compare ECF No. [124] with ECF No. [143]. Accordingly, the Court treats the statements in Plaintiff’s Statement of Material Undisputed Facts, ECF No. [130], as admitted for the purposes of this Opinion, so long as they are supported by properly cited evidence and not contradicted by Defendants’ properly filed Statement of Material Facts. See S.D. Fla. L.R. (56)(1)(c); see also BMU, Inc. v. Cumulus Media, Inc., 366 F. App’x 47, 49 (11th Cir. 2010) (finding no error with district court’s decision to deem all of the facts in the plaintiff’s statement of material facts as admitted where the party’s response to the opposing party’s statement of material facts did not comply with the local rules). No. SU1153414 (‘STS Coastal Bond’); (ii) Bond No. SU1153418 (‘STM Coastal Bond’); (iii) Bond No. SU1153423 (‘NTS Coastal Bond’); and (iv) Bond No. SU1166279 (‘NTM Coastal Bond’) (collectively, the ‘Original Bonds’ or the ‘Coastal Bonds’).” Id. at ¶ 6. The Coastal Bonds contained the following conditions precedent in the event of a claimed

default: Whenever Subcontractor shall be and is declared by [Defendants]2 to be in default under the Subcontract Agreement, [Defendants], having substantially performed [Defendants’] obligations thereunder, Surety shall promptly remedy the default and shall promptly . . .

A. Complete the Subcontract Agreement in accordance with its terms, conditions, and time limitations, or

B. Obtain a bid or bids for completing the Subcontract Agreement in accordance with its terms, conditions, and time limitations, and upon determination by Surety of the lowest responsible bidder, or, if [Defendants] elect[ ], upon determination by [Defendants] and Surety jointly of the lowest responsible bidder, arrange for a subcontract agreement between such bidder and Surety or [Defendants], at [Defendants] sole option, and make available as work progresses . . . sufficient funds to pay the cost of completion less the balance of the subcontract price, but not exceeding, including other costs and damages for which Surety may be liable hereunder . . ..

ECF No. [130] at ¶ 3 (quoting ECF No. [80-1] at 1).

The rider adding additional obligees further provided that:

[T]here shall be no liability of the Surety under the attached bond . . . unless and until the Bond Obligees shall make payment to the Principal or to the Surety (should the Surety arrange for or undertake the completion of the Contract upon the default of the Principal) . . . and otherwise satisfy all terms and conditions and perform all of the other obligations to be performed under the Contract . . . all of the acts of one Obligee being binding upon the other.

Id. at ¶ 4 (quoting ECF No. [80-1] at 7).

2 Although the Coastal Bonds refer to Coastal as the obligee, the parties executed “Riders” to the Coastal Bonds, adding Defendants as additional obligees. See ECF No. [80-1]. For clarity, the Court has replaced Coastal with Defendants wherever the Coastal Bonds refer to Coastal as the obligee. After the Coastal Bonds were issued, Defendants had Suffolk Construction Company, Inc. (“Suffolk”) replace Coastal as the general contractor for the Project. ECF No. [124] at 7. Because a new general contractor was assigned to the Project, Plaintiff, Defendants, and R&S Concrete entered into a Continuation Agreement on September 14, 2020, which required that R&S Concrete

“continue to perform its work on the Project under the same terms as the Subcontracts with Coastal.” Id. at ¶ 9. The Continuation Agreement further provided that the Coastal Bonds were released “except for latent defects in R&S’s prior work.” ECF No. [130] at ¶ 7.3 Since the Coastal Bonds were in large part released, Plaintiff agreed it would issue new performance bonds for the work R&S Concrete performed after Coastal had ceased working on the Project. ECF No. [124] at ¶ 9. Shortly after entering into the Continuation Agreement, Plaintiff issued the following four new performance bonds on behalf of R&S Concrete, as principal, and Defendants, as obligees: “(i) Bond No. SU1166299 (“STS A3 Bond”); (ii) Bond No. SU1166300 (“STM A3 Bond”); (iii) Bond No. SU1166301 (“NTS A3 Bond”); and (iv) Bond No. SU1166302 (“NTM A3 Bond”)

(collectively, the “A3 Bonds,” together with the Coastal Bonds, the “Bonds”). Id. at ¶ 11. The A3 Bonds provided that so long as R&S performed under the Subcontracts, neither Plaintiff nor R&S Concrete had any obligations under the Bonds “except when applicable to participate in a conference as provided in [§] 3.” Id. at ¶ 14. (quoting ECF No. [80-4] at 3, 13, 23, 33, § 2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Bankers Insurance Group v. United States
408 F.3d 1328 (Eleventh Circuit, 2005)
Miccosukee Tribe of Indians of Florida v. United States
516 F.3d 1235 (Eleventh Circuit, 2008)
Shiver v. Chertoff
549 F.3d 1342 (Eleventh Circuit, 2008)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Robert P. Shook and Barbara I. Shook v. United States
713 F.2d 662 (Eleventh Circuit, 1983)
American Home Assur. Co. v. Larkin Gen. Hosp., Ltd.
593 So. 2d 195 (Supreme Court of Florida, 1992)
Ben-Yishay v. Mastercraft Development, LLC
553 F. Supp. 2d 1360 (S.D. Florida, 2008)
Ocean Reef Club, Inc. v. UOP, Inc.
554 F. Supp. 123 (S.D. Florida, 1982)
Atlanta Jet v. Liberty Aircraft Services, LLC
866 So. 2d 148 (District Court of Appeal of Florida, 2004)
JJ Gumberg Co. v. Janis Services, Inc.
847 So. 2d 1048 (District Court of Appeal of Florida, 2003)
Anthony v. Anthony
949 So. 2d 226 (District Court of Appeal of Florida, 2007)
Centennial Mortg., Inc. v. SG/SC, LTD.
772 So. 2d 564 (District Court of Appeal of Florida, 2000)
Ins. Co. of No. Amer. v. Metro. Dade Co.
705 So. 2d 33 (District Court of Appeal of Florida, 1997)
St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)
School Board of Escambia County v. Tig Premier Insurance
110 F. Supp. 2d 1351 (N.D. Florida, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Arch Insurance Company v. A3 Development, LLC, A3 North Development, LLC, A3 Amenities, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arch-insurance-company-v-a3-development-llc-a3-north-development-llc-flsd-2026.