Standard Accident Ins. Co. v. United States

97 F. Supp. 829, 119 Ct. Cl. 749
CourtUnited States Court of Claims
DecidedJune 5, 1951
Docket46116
StatusPublished
Cited by12 cases

This text of 97 F. Supp. 829 (Standard Accident Ins. Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Accident Ins. Co. v. United States, 97 F. Supp. 829, 119 Ct. Cl. 749 (cc 1951).

Opinion

LITTLETON, Judge.

Plaintiff company, surety on a Government contractor’s performance bond, completed the contract after its principal defaulted. Under the terms of the contract the Government had retained certain percentages from the payments made to the contractor during the progress of the work before its default. The question here is whether the completing surety’s right to the retained percentages is superior to the right of the Government to apply!them, in partial satisfaction of taxes owed by the contractor. It is settled that a surety satisfying its principal’s obligation on a bond securing payment to laborers and .materialmen is not so favored. United States v. Munsey Trust Co., 332 U.S. 234, 67 S.Ct. 1599, 91 L.Ed. 2022. The issue is whether completion under a performance bond gives the surety a better right. We hold that it does not.

Plaintiff’s principal entered into two construction contracts with the United States, an Army contract and a Coast Guard contract. As required by law, it furnished two bonds for each contract, one to secure the contract’s performance, the other to secure payment to laborers and materialmen. Plaintiff was surety on the bonds. The contractor defaulted in its payment o'bligations on both jobs and the surety made good on the payment bonds. The contractor completed the Army contract, freeing the surety from the obligation of the performance bond for that contract. This suit arises out of the Coast Guard contract, which was 95 percent completed when a petition in bankruptcy was filed against the contractor and it suspended performance. Plaintiff took over and completed the contract at a cost of $24,853.33.

Upon completion of the Coast Guard contract there was a balance of $14,658.37 remaining due from the Government. Of this amount, $5,214 represented the percentages retained from the payments made to the contractor for work done before its default, and $9,444.37 was the amount of the contract price 'earned by the completing surety. The General Accounting Office authorized payment to plaintiff of the $9,-444.37. But it set off the entire amount of the retained percentages, which the surety also claimed, in partial satisfaction of social security taxes owed by the contractor. 1

Plaintiff contends that defendant had no right to set off against the retained percentages because they were sums dedicated to the completion of the contract to which the surety became entitled in its own right when it stepped into the contractor’s shoes and fulfilled the contractor’s obligation to the United States. In.other words, plaintiff bases its claim on subrogation to the rights of the United States. A completing surety is of course entitled to retained percentages as against its principal. See Restatement of Security, § 141; see also the annotations at 45 A.L.R. 379; 134 A.L.R. 738; and 164 A.L.R. 613. The surety’s right is superior to the right of an assignee of the principal which lent money to be used in performance. Prairie State Nat. Bank v. United States, 164 U.S. 227, 17 S.Ct. 142, 41 L.Ed. 412; Royal Indemnity Co. v. United States, 92 F.Supp. 1003, 117 Ct.Cl. 736. A surety satisfying its principal’s obligation to the United States *831 is also entitled to be subrogated to the priority of the United States. See 31 U.S.C.A. § 193; see also the annotations at 24 A.L.R. 1502, and 83 A.L.R. 1131. The Supreme Court has held, however, that a surety’s right of subrogation to the priority of the United States cannot operate contrary to the interest of the United States. United States v. National Surety Co., 254 U.S. 73, 41 S.Ct. 29, 65 L.Ed. 143. A similar principle is, we think, applicable here.

The retained percentages represented money earned by the contractor from the United States and due it from the United States when it completed the contract. But the United States has a right to set off its creditor’s debt to it before paying its debt to the creditor. United States v. Munsey Trust Co., supra, 332 U.S. at pages 239-240, 67 S.Ct. at pages 1601— 1602, 91 L.Ed. 2022. The United States cannot be deprived of its right of set-off by the circumstance that the completing surety rather than the contractor is claiming the fund. The contractor, plaintiff’s principal, was both a debtor and a creditor of the United States. Plaintiff surety seeks to step into its principal’s shoes as a creditor of the United States but not as its debt- or. We hold that as against the United States the surety is in no better position than its principal. As we said in Globe Indemnity Co. v. United States, 84 Ct.Cl. 587, 595, certiorari denied 302 U.S. 707, 58 S.Ct. 26, 82 L.Ed. 546:

“Sureties on a Government contract are in contractual relationship with the United States only through the contract of their principal and while in a proper case they may be subrogated to the rights of the United States to any funds or securities in its hands due the contractor under the contract, or which it might use for any legitimate purpose under the contract, such as the payment of claims for materials or labor, or for completion of the contract upon default of the principal, such right of the surety to lay claim against the Government to such fund or securities arises only by reason of their subrogation initially to the rights of the principal, the contractor, with the United States. In other words [the sureties’], right to recover any amount from the United States is and must be based upon [the contractor’s] contract. The party for whose benefit the doctrine of subrogation is exercised can acquire no greater rights than those of the party for whom he is substituted. The doctrine of subrogation was never intended to be used as an instrument to circumvent the principles of equity and by circuitous action to permit the assignee to be placed in a more advantageous position than the assignor from his rights devolved.”

We agree with defendant that the decision in United States v. Munsey Trust Co., supra, controls the case at bar. In that case the contractor completed the work but left laborers and materialmen unpaid. The surety satisfied this indebtedness under the payment bond and claimed the retained percentages. The Comptroller General set off against the retained percentages the damages sustained by the Government as a result of the contractor’s default on a bid on another contract. We. denied the Government’s right to do so and gave judgment for the surety, 67 F.Supp. 976, 107 Ct.Cl. 131. The Supreme Court reversed. The Supreme Court distinguished cases such as Prairie State Nat. Bank v. United States, supra, where the Government was a mere stakeholder with no rights of its own to assert. It specifically rejected the surety’s contention and our holding that the United States was in no better position than a general creditor of the contractor and that its right was therefore inferior to the rights of the surety and the laborers and materialmen whom the surety had paid. The Supreme Court said, 332 U.S. at page 240, 67 S.Ct. at page 1602, 91 L.Ed. 2022:

“ * * * And one whose own appropriation and payment of money is necessary to create a fund for general creditors is not a general creditor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
97 F. Supp. 829, 119 Ct. Cl. 749, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-accident-ins-co-v-united-states-cc-1951.