Globe Indemnity Co. v. United States

84 Ct. Cl. 587, 1937 U.S. Ct. Cl. LEXIS 207, 1937 WL 3219
CourtUnited States Court of Claims
DecidedApril 5, 1937
DocketNo. 42862
StatusPublished
Cited by12 cases

This text of 84 Ct. Cl. 587 (Globe Indemnity Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Globe Indemnity Co. v. United States, 84 Ct. Cl. 587, 1937 U.S. Ct. Cl. LEXIS 207, 1937 WL 3219 (cc 1937).

Opinion

Littleton, Judge,

delivered the opinion of the court:

December 27, 1927, plaintiffs became sureties on a conract of December 7, 1927, between Charles A. Blume and the United States for the construction of certain buildings at Pearl Harbor, T. H.

Blume ceased work under his contract February 1, 1929, before the buildings were completed, and their construction was completed by the United States. In October 1929 Blume brought suit in this court alleging breach of contract by the United States and seeking to recover damages in the amount of $297,930.49. During prosecution of that case a plea of fraud was filed by the United States under section 172 of the Judicial Code. After the introduction of proof by both parties and a hearing, the court sustained the plea that Blume had committed fraud against the [589]*589United States in the prosecution of the case and entered judgment forfeiting all claims under Blume’s contract with the United States in accordance with section 172 of the Judicial Code, U. S. Code, title 28, section 279. The motion of these plaintiffs to intervene in that proceeding for the purpose of seeking to recover a certain amount to which they claimed to be entitled, because of certain matters hereinafter more fully stated arising and growing out of Blume’s contract with the United States, was denied and this suit was later instituted. In this suit plaintiffs, as sureties on Blume’s contract, seek to recover $77,638.65. They paid this amount in settlement of suits against Blume for certain labor and materials furnished to Charles A. Blume. The defendant has filed a special answer and plea in bar praying that the petition be dismissed for the reason that it is predicated upon the same subject matter of the Blume claim which had previously been declared and adjudged to be forfeited to the Government of the United States and forever barred from the jurisdiction of this court. Plaintiffs demur to the plea in bar on the ground that the matters pleaded therein do not constitute a good defense to their cause of action. For the purpose of the demurrer and the plea in bar, the pertinent facts are as follows:

December 7, 1927, Charles A. Blume entered into a contract with the United States through the Chief of the Bureau of Yards and Docks for construction of a barracks, a subsistence building, a laundry, and a boilerhouse at the Naval Operating Base at Pearl Harbor, T. H., in compliance with specifications 5407 and amendments thereto, all of which are attached to the petition herein as Exhibit A and are made a part hereof by reference. Thereafter on December 27, 1927, in compliance with the statute relating to Government contracts (Hurd Act, U. S. Code, title 40, section 270), Blume, as principal, and the Globe Indemnity Company and The Fidelity and Deposit Company of Maryland, as sureties, gave bond for faithful performance by Blume in the undertaking and payment by him for labor and materials on the proposed construction work, all of which more fully appears from a copy of the bond attached [590]*590to the petition herein as Exhibit B and made a part hereof by reference. The bond was accepted and approved by the defendant.

Blume, the contractor, began work under his contract with the United States in February 1928. February 1,1929, long after the dates allowed and granted for completion of the work Blume abandoned further performance of the contract and thereafter refused and failed to carry on and complete the work required thereunder. Thereafter the contract work was carried on and completed by the Navy Department at great expense and cost to the United States by the purchase of the necessary building materials and the employment of its own construction engineers and technical staff, and hired mechanics and laborers. The record herein does not definitely show just when the work was completed by the United States, but for the purpose of this opinion it is found that it was completed by the Government on or shortly prior to May 21, 1930. The total contract price as modified, specified in the contract between Blume and the United States, was $445,815.41.

Prior to the abandonment of the contract by Blume, the Navy Department made payments to him from time to time as the work progressed, as provided by the contract, and on January 7,1929, the date of the last progress payment made to Blume, the aggregate of such progress payments was $314,666.16. The cost to the Government of completing the work upon Blume’s abandonment of the contract was $89,123.49. In addition Blume was charged with penalties for delay amounting to $12,715. The difference between the total contract price and the amount paid to Blume before his abandonment of the contract, plus the cost of completion and penalties for delay, was $29,310.76. Upon receipt from Blume of notice on February 1, 1929, of his abandonment of the contract and of the work required thereunder, the Navy Department made no further payments to him for materials, supplies, and labor performed since the date of the last progress payment and ceased making any further payment's after his refusal and failure to proceed with the work.

[591]*591It does not appeal’ wbat amount, if any, in excess of progress payments made was due Blume for work performed and materials furnished to the date of Ms abandonment of the contract. Art. I of Blume’s contract of December 7, 1927, obligated the contractor, among other things, to furnish all labor and materials and perform all work required for constructing and erecting the barracks, a subsistence building, a laundry and boiler house, and completing the construction of said buildings within a certain specified time. Blume did not furnish all labor and materials for this purpose and did not in fact complete the construction of the buildings but he abandoned the work on February 1, 1929, as hereinbefore stated.

October 29, 1929, Blume, the contractor, instituted suit in this court to recover damages from the United States, alleging breach by the Navy Department of the contract entered into between him and the Chief of the Bureau of Yards and Docks, December 7, 1927. December 7, 1929, the United States filed an answer to .this petition denying each and every allegation thereof. An amended petition was filed March 5, 1931, alleging damages of $282,472.02, to which the defendant filed a general denial.

In November 1930 the American Factors Co., Ltd., who had furnished certain materials to Blume for use in the construction work performed by him under his contract with the United States, instituted suit under the Hurd Act, U. S. Code, title 40, section 270, in the United States District Court of Hawaii against Blume as principal and plaintiffs as sureties on Blume’s bond to recover the sales price of such materials so furnished to Blume for which he had not made payment. Soon thereafter other creditors of Blume intervened in that suit and were made parties thereto, as provided by the Hurd Act. As a result of these suits plaintiffs, as sureties for Blume, paid $58,834.48 in October 1931 and $18,804.27 in September 1932, totaling $77,738.75, in settlement of the claims for labor and materials furnished to Blume for use in connection with his contract with the United States.

After issue was joined and the suit instituted in this court by Blume both he and the defendant called and [592]*592examined numerous witnesses and introduced into the record a large amount of documentary evidence and proof on the issue of fraud raised and joined in the pleadings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Travelers Indemnity Co. v. United States
72 Fed. Cl. 56 (Federal Claims, 2006)
Liberty Mutual Insurance v. United States
70 Fed. Cl. 37 (Federal Claims, 2006)
Home Insurance v. United States
46 Fed. Cl. 160 (Federal Claims, 2000)
O'Brien Gear & Machine Co. v. United States
591 F.2d 666 (Court of Claims, 1979)
Associated Engineers & Contractors, Inc. v. State
567 P.2d 397 (Hawaii Supreme Court, 1977)
F. B. Berkeley v. United States
276 F.2d 9 (Court of Claims, 1960)
Arlington Trust Co. v. United States
100 F. Supp. 817 (Court of Claims, 1951)
Standard Accident Ins. Co. v. United States
97 F. Supp. 829 (Court of Claims, 1951)
Irwin & Leighton v. United States
65 F. Supp. 800 (Court of Claims, 1946)
Maryland Casualty Co. v. United States
53 F. Supp. 436 (Court of Claims, 1944)
Jerman v. United States
96 Ct. Cl. 540 (Court of Claims, 1942)
Mervin Contracting Corp. v. United States
94 Ct. Cl. 81 (Court of Claims, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
84 Ct. Cl. 587, 1937 U.S. Ct. Cl. LEXIS 207, 1937 WL 3219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/globe-indemnity-co-v-united-states-cc-1937.