Irwin & Leighton v. United States

65 F. Supp. 794, 106 Ct. Cl. 398
United States Court of Claims·Decided June 3, 1946·No. 45087·Published·Cited by 6 cases

Opinion

JONES, Judge.

Plaintiffs, under a contract with the defendant, constructed the library building for The Howard University.

The University is maintained, in part, by appropriations from the Treasury of the *796 United States, and in part by funds secured from other sources.

The contract, dated December 5, 1936, was signed by Oscar L. Chapman, Assistant Secretary of the Interior, as contracting officer for the defendant, and by plaintiffs, a partnership.

The plaintiffs were to furnish all materials and perform all work in accordance with plans and specifications which were made a part of the contract. The consideration was $817,225.

Albert I. Cassell was designated as architect. . Edward M. Poynton, an engineer in the Department of the Interior, in a memorandum signed by Oscar L. Chapman, was designated to represent the contracting officer and was given broad powers as set out in finding 6. M. E. Davis, a representative of the plaintiffs, frequently conferred with these representatives.

Work was to begin within ten calendar days after receipt of notice to proceed and was tq be completed within 325 calendar days thereafter. Notice was received December 21, 1936.

There were delays due to weather conditions, strikes, and extra work for which extensions of time were granted. Other delays for which plaintiffs claimed damages are pleaded in five separate causes of action.

The facts are set out in great detail in the findings and will not be repeated here except in so far as may be necessary to a clear statement of the issue involved. The first cause of action covers several items.

First Cause of Action.

Delay in demolition.

An existing old brick building, known as the "Main Building” was on the site of the proposed new building, and was occupied by the University. Demolition was necessary. It was also necessary to move the president’s house which was nearby. On December 23 plaintiffs began stripping the interior of the building while it was still partially occupied. Demolition included relocation of the existing underground electric distribution system, gas, sewer, and telephone services.

The entire building was not available to plaintiffs until January 4, 1937, a twelve days’ delay, but plaintiffs were able to do the equivalent of five days’ work during this period, so that the net job delay was seven days.

The architect extended the time 13 days.

Delay in removal o/f telephone cables.

Delay was alleged in removing the telephone cables. The telephone company maintained service for the University under a contract. The switchboard was located in the Main Building. The telephone company would not disconnect the main switchboard until ordered to do so by the University. It was plaintiffs’ obligation to build manholes and install ducts. Some of these were to be used by the telephone company. The record is not clear as to just when the work on the manholes and ducts had progressed to the point where the change could be made. There was some delay to plaintiff and an extension of time of seven days was granted, but the defendant is not responsible for any damages that may have been caused by this delay.

Delay in ordering foundation changes.

There was some delay in the changes in the plans for the foundation of the president’s house as set out in findings 24 to 28. The plaintiffs were asked to submit a proposal for the changes indicated. They did so, and complain of the delay in acceptance. Whatever delay may have occurred was concurrent with the delay in demolition and other work on the library and therefore did not delay the completion of the entire work.

Delay in mechanical and shop drawings.

Beginning January 4, 1937, and at various times for several weeks plaintiffs submitted to the architect shop drawings and schedules in compliance with specifications, which specifications also called for action by the architect with reasonable promptness.

Bidders on the job had been required to submit proposals on a number of alternatives. One of these related to the installation of an air-conditioning system in the bookstack portion of the building. If the defendant decided not to install air condi *797 tioning, the contract price was to be appropriately reduced.

Prior to the awarding of the contract the architect had decided to include but when the contract was awarded the defendant decided not to include air conditioning. Later the defendant’s engineer concluded that it should 'be installed. Defendant rejected plaintiffs’ proposal as to cost and plaintiffs proceeded on the assumption that air conditioning would not be included.

The architect again consulted with the contracting officer and officers of The Howard University and on April 18, 1937, advised plaintiffs that defendant had prepared an order reinstating air conditioning. In the meantime the cost of air conditioning had greatly increased. Plaintiffs’ proposal was again rejected.

A definite decision was important, since if air conditioning were to be installed it would be necessary to make the structural steel stronger in order to carry the facilities and support the weight of the cooling tower. The bookstacks consisted of eight floors of concrete and steel construction.

The shop drawings were not finally approved until August 8, 1937, greatly delaying construction all along the line.

Plaintiffs claimed an over-all delay of 213 days, but in the meantime there had been delays on account of a strike and because of rain and by the plumbing contractor. Also a reasonable time should be allowed for checking and approval.

Taking all these things into account we find there was an over-all delay on the job of 100 days for which defendant is responsible.

Delays relating to electrical outlets in bookstack areas.

The drawings and specifications required installing outlets for lights in the ceilings over the aisles in the bookstack areas. Bidders had been required to submit alternative bids for the omission of these lights, with appropriate price reductions, and this alternative had been accepted when the contract was awarded.

Defendant later wished to reinstate these items. In response to requests plaintiffs on October 29, 1937, submitted three proposals for the installation of three separate groups of outlets. The additional work required great exactness in drawings and execution. Holes had to be bored through steel beams. Rigid conduits had to be woven through beams and carefully fitted into other parts of the structure.

The proposals were not accepted until December 2. We find that this was 22 days beyond a reasonable time for acceptance.

Strikes resulting from employment of nonunion workmen by The Howard University.

Free access — add to your briefcase to read the full text and ask questions with AI

Irwin & Leighton v. United States, 65 F. Supp. 794, 106 Ct. Cl. 398 (cc 1946).

65 F. Supp. 794 (Irwin & Leighton v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related