Schmoll v. United States

63 F. Supp. 753, 105 Ct. Cl. 415
CourtUnited States Court of Claims
DecidedJanuary 7, 1946
Docket44761-44770, 44999
StatusPublished
Cited by21 cases

This text of 63 F. Supp. 753 (Schmoll v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schmoll v. United States, 63 F. Supp. 753, 105 Ct. Cl. 415 (cc 1946).

Opinion

WHITAKER, Judge.

Between November 19, 1933, and March 19, 1935, Murch Brothers Construction Company, Inc., entered into 27 contracts with the United States, 17 of which were for the construction or remodeling of post offices in various cities. On each of them plaintiff, National Surety Corporation, was surety on the payment bond guaranteeing payment for all labor and material used in the performance of the contracts.

In June, 1935, the Murch Company found itself unable to complete the contracts on account of lack of funds and, in consequence, it suspended work thereon on June 22, 1935. Defendant terminated its right to proceed on June 27, 1935, and let contracts to others for the completion of the buildings.

On January 3, 1936, the Murch Company made an assignment for the benefit of its creditors. Plaintiff Dewey Schmoll is the present assignee under that assignment.

On eleven of the contracts the total amount defendant agreed to pay Murch Company is $60,100.67 more than defendant has paid it and completing contractors. On the remaining six contracts defendant has paid $4,903.10 more than the contract price. This leaves a balance of $55,-197.57. Defendant, however, incurred certain expenses incident to the Murch Company’s default. It now claims that these expenses amounted to $31,547.80, and that it has the right to deduct this amount from the balance in its hands. (The Comptroller General deducted the sum of $32,692.-56, which included rentals paid for temporary quarters after the buildings had been completed, but defendant now admits this was improper. This amount was $1,144.-76.) Plaintiffs admit defendant’s right to deduct all of this amount except $12,795.-27, which is the amount of rental paid for temporary quarters for post offices between the completion dates under the Murch contracts and the actual dates of completion. This is the first item in dispute.

Defendant also claims the right to offset against the balance due on these contracts the sum of $2,552.43, an amount it claims the Murch Company owes it for correcting defective work on two contracts for the Veterans’ Administration, and the sum of $206.53, an amount the Murch Company owes for taxes. On these Veterans’ Administration contracts plaintiff, National Surety Corporation, was not surety and, having paid for labor and material on these contracts a total of $202,011.66, which far exceeds the amount due on the Murch contracts, it denies defendant’s right to offset against it the amounts due on these contracts and the amount due for taxes. This is the second matter in dispute.

The third item is a sum alleged to be due for delays alleged to have been caused by defendant on the Schenectady contract.

1. Plaintiffs say defendant is not entitled to deduct the amount paid for rental of temporary quarters for post offices because the contract makes the contractor and his surety liable only for the excess costs of completion of the contract, in case the contractor’s right to proceed is terminated, and that rental of temporary quarters is not a cost of completion.

We agree that such an item is not a part of the cost of completion of the contracts, and that it may be recovered, if at all, only as damages, and not as a part of the cost of completion. We did not hold otherwise in Collins, Receiver, v. *756 United States, 93 Ct.Cl. 369. In that case such an item was allowed, but no issue was raised nor discussed about the propriety of its allowance.

Plaintiffs further say defendant is not entitled to this deduction as an item of damage for delay in completion, because, first, damages for delay are neither alleged nor proved, and, second, the amount defendant paid for temporary quarters is not the proper measure of damages.

Defendant in its counterclaim did not seek to recover damages, but only excess costs of completion, and it did not specify any of the items of excess cos I, including the cost of temporary quarters; but in its proof it did seek to recover this item, although not as damages for delay, but as an item of excess cost of completion. Counsel for plaintiffs admitted the amount had been spent for this purpose and that it was reasonable, but he said that it was ■“a question of law as to whether or not the Government is entitled to deduct -them.”

Aside from the question of •pleading, we are of opinion that defendant is entitled to deduct the amount of money it lost in rentals on account of the delay. Where the Government terminates the contractor’s right to proceed, liquidated damages are not deductible, 1 but we have held that actual damages are, 2 and so also has the 9th Circuit Court of Appeals. 3 What it has lost in rental is an element of ■damage.

Plaintiffs are correct in saying that ordinarily the proper measure of damages is the reasonable rental value of the building on which construction was delayed; but in the case of a building that has no rental value on the market, such .as a post office, we must arrive at defendant’s loss in some other way. We have no doubt that it lost not less than the amount it paid for temporary quarters, because we are sure if it had rented quarters comparable to those under construction it would have had to pay much more than it did. It is common knowledge that ordinarily the post offices built by the Government are costlier to construct than those it rents temporarily, and that if it rented quarters comparable to those it builds it would have to pay a much larger rental. Unless defendant is barred from doing so by defective pleadings, we ace of opinion it is entitled to deduct the rent paid.

When defendant offered this proof of rent paid, plaintiffs did not object to it as being outside of the counterclaim; they admitted the amount had been spent for the purpose claimed and that it was reasonable. Not until their brief was filed did the defendant know they were objecting to this item because the defendant had called it “excess cost” instead of “damages.” Since plaintiffs were fully apprized of the Government’s claim and its nature in ample time to combat it, we do not think that the fact that the Government called it by the wrong name should deprive it of the deduction.

2. The next matter at issue is the defendant’s right to offset against the amount due plaintiffs the sums which the Murch Company owed it on other contracts on which the plaintiff, National Surety Corporation, was not surety, and also the amount which the Murch Company owed defendant for taxes.

In the case of Maryland Casualty Company v. United States, 100 Ct.Cl. 513, we held that defendant was not entitled to these offsets; but the facts in that case differed from the facts in this, in that there was no formal act of insolvency in that case, whereas in this the Murch Company had made an .assignment for the benefit of its creditors. The defendant says that this differentiates this case from the Maryland Casualty case, because of the provisions of section 3466 of the Revised Statutes, 31 U.S.C.A. § 191, giving to the United States priority where one indebted to it becomes insolvent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tester Corp. v. United States
30 Cont. Cas. Fed. 70,544 (Court of Claims, 1982)
Pathman Construction Co. v. United States
652 F.2d 70 (Court of Claims, 1981)
Autogiro Company of America v. The United States
384 F.2d 391 (Court of Claims, 1967)
Williamsburg Drapery Co. v. The United States
369 F.2d 729 (Court of Claims, 1966)
Midwest Spray & Coating Co. v. United States
176 Ct. Cl. 1331 (Court of Claims, 1966)
United Pacific Insurance Company v. The United States
362 F.2d 805 (Court of Claims, 1966)
United States v. Russell Electric Co.
250 F. Supp. 2 (S.D. New York, 1965)
Hunt & Willett, Inc. v. United States
351 F.2d 980 (Court of Claims, 1964)
Robert E. Lee & Co. v. United States
164 Ct. Cl. 365 (Court of Claims, 1964)
Olsen v. United States
122 Ct. Cl. 106 (Court of Claims, 1952)
Standard Accident Ins. Co. v. United States
97 F. Supp. 829 (Court of Claims, 1951)
Royal Indemnity Co. v. United States
93 F. Supp. 891 (Court of Claims, 1950)
United States v. Munsey Trust Co.
332 U.S. 234 (Supreme Court, 1947)
Kjar v. United States
69 F. Supp. 406 (Court of Claims, 1947)
Seaboard Surety Co. v. United States
67 F. Supp. 969 (Court of Claims, 1946)
Manufacturers Casualty Ins. Co. v. United States
63 F. Supp. 759 (Court of Claims, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
63 F. Supp. 753, 105 Ct. Cl. 415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schmoll-v-united-states-cc-1946.