United States v. Russell Electric Co.

250 F. Supp. 2
CourtDistrict Court, S.D. New York
DecidedNovember 15, 1965
StatusPublished
Cited by15 cases

This text of 250 F. Supp. 2 (United States v. Russell Electric Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Russell Electric Co., 250 F. Supp. 2 (S.D.N.Y. 1965).

Opinion

COOPER, District Judge.

This is an action for money damages arising from an alleged breach of contract.

Commenced July 6, 1959 by the filing of a complaint, issue was joined by service of an answer on September 4, 1959. The cause was tried before the Court and a jury on February 5, 8, 9 and 10,1965.

Defendant moved for a directed verdict at the close of plaintiff’s case (Tr. 270) 1 After argument by both sides, this motion was denied (Tr. 270-296).

At the close of the entire case, plaintiff and defendant agreed to waive jury trial of the fact issues (Tr. 383).

Having rested, both sides moved for directed verdicts. Defendant moved for dismissal of the complaint on the entire record (Tr. 386). Decision on these motions was reserved pending submission of post-trial memoranda and proposed findings of fact and conclusions of law.

FACTS

The Contract

In April, 1951, the United States of America, by its agent, the United States Naval Ordnance Plant at Indianapolis, Indiana (hereinafter NOP), solicited bids on Contract N163s-947 (hereinafter Contract 947) relating to gyro motors. These motors were to be used in a sighting unit which was being developed by NOP for use in fighter aircraft (Tr. 231-33).

NOP received bids for Contract 947 as follows (Exs. 2-7):

Unit

Company Price

John Oster Manufacturing

Co. $30.20

Universal Electric Company 23.43

A. C. Gilbert Company 22.31

Redmond Company, Inc. 17.25

Russell Electric Company 14.12

On or about May 14, 1951, NOP awarded Contract 947 to Russell Electric Company (hereinafter Russell). Russell’s bid had been signed by William Lightfoot, its General Manager. Commander Lloyd B. Clapham, Jr. was the Contracting Officer for NOP (Ex. 2).

Pursuant to Contract 947, Russell undertook to develop 5 sample motors to NOP’s satisfaction before commencing production (Ex. 2, p. 2); furnish NOP manufacturing drawings (Ex. 2, p. 6); produce all special tooling necessary for the production of the motors (Ex. 2, p. 2); deliver the tooling to NOP “upon *7 completion of the Contract” (Ex. 2, p. 5); and deliver 7,100 production motors no later than January 31, 1952 (Ex. 2, p. 6). Delivery of motors was scheduled as follows: 500 by August 15, 1951; 1,000 in September, 1951; and 1,500 per month thereafter until the full 7,100 motors had been delivered (Ex. 2, p. 6).

The United States agreed, under Contract 947, to pay Russell $113,917 for the 7,100 gyro motors ($14.12 each), and $13,665 for the special tooling (Ex. 2, p. 2). As later modified, Contract 947 provided for payment by the United States of $133,881, including special tooling and 7,100 gyro motors ($14.11493 each).

Termination, Reletting, Claimed Damages

Section 11(a) of the General Provisions of Contract 947 (Ex. 2, pp. 13-14) provides:

11. DEFAULT
(a) The Government may * * by written Notice of Default to the Contractor terminate the whole or any part of this contract in any one of the following circumstances:
(i) if the Contractor fails to make delivery of the supplies or to perform the services within the time specified herein or any extension thereof; or.
(ii) if the Contractor fails to perform any of the other provisions of this contract, or so fails to make progress as to endanger performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days . after receipt of notice from the Contracting officer specifying such failure.

On August 13, 1952, Redmond Manufacturing Co., Inc. (hereinafter Redmond) wrote Russell that it would no longer produce motors for Russell under Contract 947 as had been previously arranged 2 (Ex. 58). A copy of this letter was sent to NOP.

NOP regarded performance under Contract 947 in danger. The need for motors was pressing (Tr. 135). It appeared delivery would not be forthcoming or, at best, unduly delayed. Accordingly, by letter dated August 22, 1952, the Contracting Officer, Commander Clapham, wrote Russell, advising (Ex. 61):

Deliveries of such supplies shall be cured and acceptable evidence that performance will not be delayed shall be furnished * * * within ten (10) days after receipt of this letter; if such is not done, the contract will be cancelled for default in accordance with Section 11(a) (ii) of the contract.

Russell failed to reply to NOP’s “warning” letter. Commander Clapham, under date of September 11, 1962, then wrote Russell (Ex. 62, Tr. 122):

* * * in accordance with Section 11, General Provisions, Contract N163s-947 is terminated for default, with respect to the undelivered balance * * * [specifying the items].

Five bids were received (between September 8 and October 2) in response to NOP’s solicitation of ten companies for price quotations on a replacement contract (Exs. 64-28, Tr. 128-69). Because Redmond offered the best delivery schedule and the Navy’s need for the gyro motors was urgent, the Contracting Officer accepted Redmond’s bid even though others had submitted lower quotations (Tr. 135). Russell interposes no claim that NOP should have accepted another bid (Tr. 239-42); 243-44; 300-02; see Tr. 135; Ex. 2, Article 11(c).

*8 At the time of termination, September 11, 1952, according to the Government, 6,935 motors remained to be delivered under Contract 947. It contends that as a result of administrative error, the replacement contract (Exhibit 63, Contract 163s-2261) entered into between NOP and Redmond on October 15, 1952, called for delivery of 6,768 gyro motors (Ex. 63, Tr. 126-27, see Exs. 64-68 at a unit price of $39.87.

The United States, in this action, seeks to recover damages resulting from Russell’s default under Contract 947 as measured by the difference between the cost under the replacement contract and what would have been the cost under Contract 947 had Russell not defaulted. The excess costs amount to a total of $180,-745.96. 3

Relationship of the Parties

As we see it, Russell contends that during the fall of 1951 it abandoned and repudiated Contract 947; NOP knew of the abandonment; NOP then had a duty to and could have, but completely failed to, mitigate damages; this requires a finding for defendant. Such a result, it is further advanced, would also be reached by the alternative argument that it was the Navy which caused Redmond to cease performing by August, 1952 and any breach of- contract attributed to Russell was, at that time, the result of NOP’s hindrance of performance and a further failure to mitigate damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Bank National Ass'n v. Ables & Hall Builders
696 F. Supp. 2d 428 (S.D. New York, 2010)
Edward M. Crough, Inc. v. Department of General Services
572 A.2d 457 (District of Columbia Court of Appeals, 1990)
Roflan Co. v. United States
32 Cont. Cas. Fed. 73,207 (Court of Claims, 1985)
Aamco Transmission v. Air Systems, Inc.
459 N.E.2d 1215 (Indiana Court of Appeals, 1984)
Southern Packaging and Storage Co. v. United States
458 F. Supp. 726 (D. South Carolina, 1978)
Rasor v. Retail Credit Co.
554 P.2d 1041 (Washington Supreme Court, 1976)
Wyoming Timber Products Co. v. Crow
500 P.2d 683 (Wyoming Supreme Court, 1972)
Industrial Development Co. v. León Rosado
99 P.R. 615 (Supreme Court of Puerto Rico, 1971)
Compañía de Fomento Industrial v. León Rosado
99 P.R. Dec. 633 (Supreme Court of Puerto Rico, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
250 F. Supp. 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-russell-electric-co-nysd-1965.