Industrial Development Co. v. León Rosado

99 P.R. 615
CourtSupreme Court of Puerto Rico
DecidedFebruary 8, 1971
DocketNo. R-66-138
StatusPublished

This text of 99 P.R. 615 (Industrial Development Co. v. León Rosado) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Development Co. v. León Rosado, 99 P.R. 615 (prsupreme 1971).

Opinion

Mr. Justice Rigau

delivered the opinion of the Court.

This case involves an action to recover liquidated, agreed, and fixed damages for breach of contract, and another amount for construction cost of work in excess of the lump sum agreed upon, in accordance also with the provisions of the contract.

The trial court sustained the complaint but committed errors in the construction of the bond contract, which led it,' [617]*617in turn, to' commit errors in calculating the amounts to he paid to appellant by the surety.

Plaintiff-appellant, the Puerto Rico Industrial Development Company, entered into a contract with Leonardo León Rosado, the contractor, for the development of the lots of an industrial urbanization in the ward Sabana Abajo of Carolina,. P.R. The initial price agreed upon by the contracting parties was $368,400.1 The work would be commenced on February 29, 1960 and would be terminated on or before August 27 of said year. The contract provided for the granting of extensions for different causes, among them, bad weather. Extensions were granted for that reason.

Simultaneously with the construction contract, the contractor, as principal, and appellee herein, American Surety Company of New York, as surety,' signed, in behalf of appellant, a performance bond in the amount of $368,400, the initial price of the work, as security for the performance of said contract. It was agreed upon in the contract that any unauthorized delay would be subject to a daily indemnity of $200.

The Industrial Development Company granted the contractor several extensions which extended the term of delivery of the work until January 24, 1961. In view of the fact that the contractor did not complete the work, the Development Company notified him and his surety, on October 13, 1961, that it considered the contract as rescinded. Appellant made a contract for the completion of the- work with another contractor, who should deliver it complete on or before April 17, 1962. This second contractor was granted an extension of the term for delivery until July 18,1962.

At the time appellant considered the contract entered into with León Rosado as rescinded, said contractor had incurred an unauthorized delay of 262 days. That term is computed [618]*618from January 25, 1961, date on which the last extension granted to him had expired, to October 13 of the same year, date on which appellant rescinded the contract.

On October 20, 1961, appellant took physical possession of the project and performed an inventory of the work carried out and of the materials and equipment therein. Appellant made an estimate of the cost of completion of the work which resulted in the amount of $65,900.

For the purposes of completing the work, appellant made a public call for bids and asked several contractors to submit their bids for the work which was needed for the completion of the project. The bidding was held on November 6, 1961, but appellant was forced to annul it because all the bids submitted by the bidders exceeded greatly the estimate of $65,900, made by appellant. Said bids fluctuated between $92,228.74 and $124,000.

The bidding having been annulled, appellant negotiated with the bidders seeking to obtain a lower bid and finally, on December 13, 1961, appellant awarded contractor Juan Diaz Rivera the contract for the completion of the project on the basis of the cost plus a profit of seven and a half percent.

In the contract with Diaz Rivera, a term of 120 days was fixed for the completion of the work, which term expired on April 17, 1962, since the order for the commencement of the work was given on December 18, 1961. Diaz Rivera was not able to complete the work within the said term and appellant extended same until July 18,1962.

The cost of completion of the project, in accordance with the contract with Diaz Rivera, was $71,701.26, amount notably lower than all the bids made by the bidders in the aforementioned bidding which was annulled by appellant.

On September 11, 1963, appellant filed a complaint in the Superior Court, San Juan Part, against Leonardo León Rosado and his surety, claiming, after it was amended, the amount of $2,727.73 for construction cost in excess of the [619]*619price agreed upon in the contract, and the amount of $89,400 for liquidated damages at the rate of $200 daily, as agreed upon in the construction contract, for the 447 days of delay in the completion of the work the performance of which was secured by the bond issued by the surety, appellee herein.

After the trial was held, the trial court, although it sustained the complaint, ordered León Rosado to pay the plaintiff the amount of $55,127.73 and “from that amount” it ordered the surety company to pay plaintiff the amount of $15,927.73 plus costs and $1,000 for attorney’s fees.2

Plaintiff, in its petition for review assigns several errors which, since they are interrelated among themselves, may be summarized as follows:

1. The court erred in its construction of clause No. 12 of the general conditions of the construction contract entered into between appellant and León Rosado, upon concluding that the contractor and his surety’s liability for liquidated damages by reason of delay was limited only to the 262 days comprised between the expiration date of the last extension granted to León (January 24, 1961) and the date on which appellant rescinded the contract (October 13,1961).
2. The court erred in deciding that appellant failed to take measures to reduce the amount of the liquidated damages as penalty for delay, and that therefore, the surety was liable only for the payment of liquidated damages corresponding only to the 66 days elapsed from the expiration date of the last extension (January 24, 1961) up to March 31, 1961, date on which, according to the particular view of the trial court, appellant should have rescinded the contract with León Rosado.

Let us see, in the first place, whether the Industrial Development Company was entitled, according to the penalty clauses of the contract, to indemnity by reason of delay only [620]*620from the expiration date of the last extension granted to contractor León up to the date on which the Company rescinded the contract, as it was understood by the trial court, or whether it was entitled to indemnity from the expiration date of the last extension granted to León, to the date on which the second contractor should have completed the work, without including the extension which was subsequently granted to said second contractor.

Clause No. 12, insofar as pertinent, provides the following:

“If the Contractor refuses or fails to prosecute the work . . . within the time specified or any extension- thereof, or fails to complete said work within such time, the Puerto Rico Industrial Development Company may . . . terminate his right to proceed-with the work. In such event the Puerto Rico Industrial Development Company may take over the work and prosecute the same to completion, by contract or otherwise, and the Contractor and his sureties shall be liable to the Puerto-Rico Industrial Development Company for any excess cost occasioned to the Puerto Rico Industrial Development Co. thereby, in addition to fixed, agreed and liquidated damages

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Kellett Aircraft Corp.
186 F.2d 197 (Third Circuit, 1950)
United States v. Russell Electric Co.
250 F. Supp. 2 (S.D. New York, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
99 P.R. 615, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-development-co-v-leon-rosado-prsupreme-1971.