Collins ex rel. Waldrop Heating & Plumbing Co. v. United States

93 Ct. Cl. 369, 1941 U.S. Ct. Cl. LEXIS 115
CourtUnited States Court of Claims
DecidedApril 7, 1941
DocketNo. 43312
StatusPublished
Cited by4 cases

This text of 93 Ct. Cl. 369 (Collins ex rel. Waldrop Heating & Plumbing Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Collins ex rel. Waldrop Heating & Plumbing Co. v. United States, 93 Ct. Cl. 369, 1941 U.S. Ct. Cl. LEXIS 115 (cc 1941).

Opinion

Green, Judge,

delivered the opinion of the court:

The plaintiff, LeRoy Collins, is Receiver of the National Construction Company, a Florida corporation, which on July 14, 1930, entered into a contract with the United States to furnish all labor and materials and perform all work required for the demolition of certain buildings and remodeling of and construction of certain other buildings at Richmond, Virginia. On September 10, 1930, the National Construction Company entered into a contract with the Waldrop Heating & Plumbing Company to do certain of the work and install the mechanical equipment required by the contract with the defendant, as shown by Finding 3.

The contract and specifications entered into between the National Construction Company and the United States provided among other things as follows:

17. Manner of conducting the work. — The building will be occupied during the life of the contract hereunder. The work shall be so done as to cause the least possible-interruption to the Government business. The contractor shall provide satisfactory temporary facilities to permit all business to be continued during the operations under the contract.
$ ‡ $
38. Temporary heat. — The contractor shall provide temporary heat as necessary to protect all work and materials against injury from dampness and cold, to the satisfaction of the Construction Engineer.
$ ‡ * . %
1019. Temporary heat. — The contractor is to furnish temporary heat to portions of building occupied during construction.

[380]*380One of the items called for under the contract with the Government was the removal of the old heating plant in the building which was being remodeled and replacing it with a new and larger plant. That item was covered by the contract between the contractor and its subcontractor, the Waldrop Heating & Plumbing Company. This work was to be carried on while the building was occupied and heat was to be furnished by the contractor pursuant to paragraph 1019 set out above. The subcontractor planned to carry out this work by removing only a part of the heating equipment and replacing the equipment removed with new equipment before proceeding with the further removal of the old equipment, thus leaving enough of the heating system in place and in operation to enable it to supply heat for the occupied portion of the building.

When the subcontractor entered into its contract with the contractor the former understood that it was to commence work within thirty days thereafter and it was ready within such time to proceed with the work, including work in the old building. In October 1930 the subcontractor began work in the new building being constructed, and in November and December 1930 applied for permission to begin work on the heating plant in the old building, but permission was denied. Request was renewed in January 1931 and again denied Permission was not finally granted until about May 15,1931, when the subcontractor was permitted to have access to the old building for the purpose of beginning work on the heating plant.' Thereafter work on both the old and new buildings required by the contract was carried on concurrently. The subcontractor completed its work on November 24,1931, and the contractor completed the work under the principal contract about August 1, 1932, when the work was accepted by the United States. If the work had not been delayed by failure to gain access to the old building until about May 15, 1931, and the subcontractor had not been subjected to further delay through changes made in the plans and specifications, the subcontractor would have completed its contract by October 1, 1931, and the contractor would have completed its part, insofar as necessary to be relieved of any necessity to furnish temporary heat, by November 24,1931.

[381]*381During the heating season of 1930 and 1931 the United States supplied the heat required for the old building and made no request upon either the contractor or subcontractor to furnish such heat; and likewise furnished such heat as was required for the period from October 1 to October 24, 1931. From the date last named to November 24, 1931, the subcontractor furnished heat for the old building, and thereafter, until the completion of the contract of the contractor with the United States, the contractor furnished the required heat.

The total cost of furnishing the heat supplied by the Government during the 1930-1931 heating season and for the period from October 1 to October 24,1931, was $4,883.61. The cost of furnishing heat by the subcontractor from October 24 to November 24, 1931, was $462.29, and by the contractor from November 24, 1931, to May 1932, the end of the 1931-1932 heating season, was $3,936.98.

About October 1931 the question arose as to who was required under the contract to furnish heat for the old building. In response to a request for an interpretation of the contract the supervising architect replied, with reference to the extension of the Post Office building and in regard to paragraph 1019 of the specifications calling for temporary heat: “As this was to be a partially occupied building it was contemplated that the Government’s regular fireman and Government fuel for the existing building would be used.” This ruling was later reversed by the supervising-architect by a letter to the contractor on December 5,1931, in which it was held that the contractor was required “to furnish the necessary heat in the occupied portions of the building in addition to the temporary heat to protect the work.”

In the final settlement by the defendant of its contract with the contractor, defendant determined the “completion date” under the contract was November 24, 1931; that is, the date when the contractor would have been able to complete the work under the contract and be relieved of the responsibility for furnishing temporary heat. On the ba,sis of that determination, the defendant withheld from the amount otherwise due the contractor the sum of $4,883.61, representing the cost to the defendant of furnishing heat to the [382]*382old building during the 1930-1931 heating season ($4,455) and the cost to the defendant for a like purpose for the period October 1 to October 24, 1931 ($428.61). The defendant, however, credited the contractor with the cost to the contractor of furnishing temporary heat after the completion date, November 24, 1931, to the end of the 1931-1932 heating season, such credit amounting to $3,936.98.

• After the amount of $4,883.61 had been withheld by the defendant from the amount due the contractor, the contractor withheld a like sum from the amount due the subcontractor. The amount withheld hajg not been paid by the United States either to the contractor or the subcontractor and is the amount sought to be recovered in this suit. The plaintiff conceded in argument that the defendant furnished heat for the period and at the cost as stated above.

The plaintiff’s case depends upon the construction of the specifications of the contract which relate to, or provide ,for, the contractor’s obligation for supplying heat. The fir,st of these, paragraph 17 of the specifications, set out above, is general in its terms and has given rise to no controversy between the parties.

Paragraph 38 relates only to the supplying of temporary heat for the protection of work and materials, and its meaning is not in dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Page v. United States
120 Ct. Cl. 27 (Court of Claims, 1951)
Evans Electrical Const. Co. v. Wm. S. Lozier, Inc.
68 F. Supp. 256 (W.D. Missouri, 1946)
Schmoll v. United States
63 F. Supp. 753 (Court of Claims, 1946)
Fireman's Fund Indemnity Co. v. United States
63 F. Supp. 750 (Court of Claims, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
93 Ct. Cl. 369, 1941 U.S. Ct. Cl. LEXIS 115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/collins-ex-rel-waldrop-heating-plumbing-co-v-united-states-cc-1941.