Page v. United States

120 Ct. Cl. 27, 1951 U.S. Ct. Cl. LEXIS 58, 1951 WL 5342
CourtUnited States Court of Claims
DecidedJune 5, 1951
DocketNo. 47171
StatusPublished
Cited by2 cases

This text of 120 Ct. Cl. 27 (Page v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Page v. United States, 120 Ct. Cl. 27, 1951 U.S. Ct. Cl. LEXIS 58, 1951 WL 5342 (cc 1951).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Plaintiffs,, a partnership composed of Holland Page and Sherman Nelson, sue to recover $210,620.12, the amount to which they say they are entitled under, and because of a breach of their contract for the clearing of certain acreage in the Norfork Eeservoir area in northern Arkansas and southern Missouri.

Bids were invited for clearing six different areas, designated areas 2, 3,4,5, 6 and 7, both separately and as a whole. These areas were within the area of the reservoir to be created by the erection of a dam on the North Fork Biver. One of the plaintiffs, Sherman Nelson, bid on all six parcels and he was low on each of. them, except one, and his bid on the whole was also low. However, the Army Engineer Corps, representing the defendant, hesitated to let a contract to Nelson [53]*53for the entire work because of Ms limited experience and his-lack of capital and eqtiipment. Nelson then brought Holland Page to the Engineer’s office and Page agreed that he and Nelson, as partners, would take a contract to clear three of the six parcels. Parcels 2, 3 and 7 were allotted to them, and the other three parcels were allotted to the Schutt Construction Company;

■ Plaintiffs’ petition is grounded on five complaints: (1) that parcel 7 was eliminated from their contract; (2)- that they cleared more land than they were paid for; (3) that 48.03 acres were erroneously taken from one of the tracts they were-to clear and put in one of the tracts to be cleared by the Schutt Construction Company; (4) that they were erroneously charged with inspection costs; and (5) that they have not been paid the sum of $100.00 retained by defendant and admittedly due them.

> All of these issues, except the last, have been decided against plaintiffs by the contracting officer and the head of the department, and plaintiffs admit that these decisions, except- that relating to inspection fees, would be conclusive except for the fact that they say they were arbitrary and capricious and rendered in actual bad faith. /

■ The trial commissioner has found against plaintiffs. Plaintiffs have excepted to each of his findings, except' three formal ones. We have examined their exceptions and the evidence on which they are based, and conclude they are not well taken.

defendant filed no exceptions.

■1. ■ Plaintiffs’ first complaint is that parcel 7 was deleted from their contract. Plaintiffs consented to tMs, but they say they did so under duress. We do not think so.

" Plaintiffs were far behind with their progress schedule' and they were getting further and further behind. The areas had to be cleared before the dam could be closed and the reservoir filled up, and it was apparent that parcel 7 would not be cleared in time. Plaintiffs, being 31 days behind their schedule on January 1,1943, reorganized their working force and put a new superintendent in charge. This superintendent'wrote'.tlie resident engineer outlining his plan for catching up. The resident engineer sent plaintiff’s letter to-tiré [54]*54District Engineer and suggested himself three alternatives for correction of the situation. One of these alternatives was the elimination of parcel 7 from plaintiffs’ contract. The District Engineer gave serious consideration to this suggestion, but decided not to make this demand on plaintiffs until they could have further opportunity to catch up.

However, plaintiffs got further and further behind. By April 29 they were 68 days behind schedule. At that, .time the defendant proposed to Page over the phone that this parcel be eliminated from the contract. Page promised to come to the Engineer’s office in Little Bock to discuss the matter, but failed to keep a number of appointments. He finally appeared, however, on May 13, but stated that he wanted further time to consider the matter. Pie continued to defer giving defendant an answer to this suggestion; whereupon, defendant advised him that it would exercise its rights under article 9 of the contract and terminate plaintiffs’ right to proceed with parcel 7. Thereupon Page advised defendant that he would agree to the deletion of this parcel from the contract. He, however, refused to sign the release prepared by defendant, but gave defendant a letter in which he said '“yo,u may delete Parcel No. 7 from my contract.”

The following day, the Schutt Construction Company agreed to do the work on parcel 7 for the amount for which plaintiffs had offered to do the work. However, defendant did not wish to enter into a formal contract with Schutt therefor until plaintiffs had signed an agreement to delete this parcel 7 from the contract and to release the defendant from any liability in connection therewith. Plaintiffs refused to do this. Whereupon, defendant told plaintiffs that they would then exercise their rights under article 9 and terminate their right to proceed with this parcel. Plaintiffs then signed the release.

Defendant’s threat to exercise its rights under article 9 did not constitute duress, since it was a threat to do something which the contract gave it the right to do.

While the defendant was negotiating with plaintiffs to sign. this release a progress payment became due. A voucher was prepared on the assumption that plaintiffs would agree to the deletion of parcel 7 from their contract. However, :this: [55]*55voucher was not delivered because of plaintiffs’ delay in making the agreement requested.

When plaintiffs complained about the nonpayment of the progress payment, another voucher was prepared including parcel 7 in the contract work. By the time this revised estimate was returned to the field office it was time for the next estimate to be prepared. By this time plaintiffs had signed the release. Whereupon a new estimate was prepared including two semi-monthly periods, and this was paid. Plaintiffs say that defendant refused to pay plaintiffs their semimonthly estimate in order to force them to sign the release, but we are convinced that this is not so.

2. Plaintiffs claim that they cleared more acreage than they have been paid for. The contracting officer has decided this issue against plaintiffs, and his decision was neither arbitrary nor capricious nor in bad faith.

Field surveys are classified according to the accuracy with which they are made. In a first order survey the error is not expected to exceed one in 25,000. In a second order survey the error should not exceed one in 10,000, and in a third order survey it should not exceed one in 5,000. In determining acreage of large areas third order surveys are considered sufficiently accurate. The field survey on the upper and lower limits of parcel 3 and on the upper limit of parcel 2 was within third order requirements. The survey on the lower limits of parcel 2 did not quite meet third order requirements, but it was close to it.

Irregular tracts of land, such as were involved here, are surveyed by making a traverse survey, which'is a,series of tangents carefully measured as to length and azimuth. In such surveys some of the subject area is outside the traverse and other land not in the subject area is included. In order to determine the area of the subject land the extent of the areas thus excluded or included are balanced' against each other. Sometimes this is done by approximation only and sometimes by measuring these areas by means of offset lines at right angles to the tangents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tester Corp. v. United States
30 Cont. Cas. Fed. 70,544 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
120 Ct. Cl. 27, 1951 U.S. Ct. Cl. LEXIS 58, 1951 WL 5342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/page-v-united-states-cc-1951.