Pathman Construction Co. v. United States

652 F.2d 70, 28 Cont. Cas. Fed. 81,299, 227 Ct. Cl. 670, 1981 U.S. Ct. Cl. LEXIS 196
CourtUnited States Court of Claims
DecidedApril 14, 1981
DocketNo. 163-80C
StatusPublished
Cited by5 cases

This text of 652 F.2d 70 (Pathman Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pathman Construction Co. v. United States, 652 F.2d 70, 28 Cont. Cas. Fed. 81,299, 227 Ct. Cl. 670, 1981 U.S. Ct. Cl. LEXIS 196 (cc 1981).

Opinion

This contract case, arising under the Wunderlich Act, is to be decided on cross-motion for summary judgment.1 Plaintiff Pathman Construction Company (Pathman) seeks Wunderlich Act review of certain aspects of two related opinions of the Postal Service Board of Contract Appeals (the Board), while defendant asks affirmance of the Board’s decisions and dismissal of the petition. For the reasons set forth below, we grant defendant’s motion, and deny plaintiffs.

The government contract underlying this action was for the performance of certain remodelling work in the Chicago Central Vehicle Maintenance Facility of the Postal Service (the Facility). The $409,900 contract was awarded to Pathman on June 21, 1974, and was to be completed by November 15, 1974 (119 days after receipt of Notice to Proceed). The work involved construction of a dispatcher’s office, remodelling offices and toilet facilities, painting, lighting and decoration. Although Pathman was not aware of this fact when it bid on the job, its contract was actually Phase II of a three-phase renovation project. The first phase of the contract, which was later awarded to another contractor, involved mechanical work on the Facility’s heating, ventilating and air-conditioning systems. The third phase entailed work on the exterior ramps, elevator installation, and changes to the Facility’s power system. The Board found, in its opinion of August 31, 1979 [79-2 BCA para. 14,027], that this out-of sequence award resulted from the Postal Service’s need to get a contract awarded quickly due to union pressure to improve the working conditions at the Facility, and that the Phase II work was awarded first because of its higher visibility. The award was made first even though the Postal Service was aware that there was a risk that later-performed Phase I work would damage previously-performed Phase II work. The board found that this out-of-sequence plan caused substantial delays and interruptions of plaintiffs work since almost all of Phase II had to wait until Phase I work (which was awarded in [672]*672August 1974 and which called for completion 350 days after Notice to Proceed) was performed, and that the contracting officer did not attempt to resolve these scheduling and coordination problems. The Board also found that delays in performance were attributable to the issuance of 19 contract modifications, some of which were major in scope and amount, and were administered in an uncooperative and haphazard manner. Time extensions were granted as part of the modifications, increasing the total time of performance from 119 to 936 days, and making the final completion date November 1, 1976. These modifications also increased the contract price from $409,900 to $1,199,212. Of the $789,312 added to the contract price by the modifications, only $8,978.63 comprised overhead costs. The Board found that this amount did not include extended or stretch out overhead costs, which plaintiff had reserved its right to claim at a later date. This reservation was necessary because there was no way to determine, at the time the modifications were made and the prices charged, what amount of such costs would be produced.

The current dispute arose when, after contract completion, plaintiff claimed extended overhead costs of $185,933.52, which included amounts for: main office overhead; escalation in wage fringes, insurance and taxes; field supervision and non-productive staff; other direct costs (field); extraordinary costs; and a bond premium. These costs were based on the full 717-day2 extension period granted by the contract modifications, and were said to arise under the Suspension of Work Clause or the Changes Clause. The Board determined that plaintiff was entitled, under the Changes Clause, to an equitable adjustment including costs resulting from delay to and disruption of the unchanged contract work. However, the Board rejected Pathman’s position that the full 717-day extension period was the appropriate period on which to base such an adjustment, holding instead that "[t]o the extent that the claimed costs are time related appellant [Pathman] will have to establish the extent of claimed delays.” Board [673]*673Opinion at 40. In rejecting what it termed plaintiffs "total cost” theory, the Board found that

[i]n this connection, it is doubtful that every change had a delaying or disruptive effect on unchanged work. In fact the evidence strongly suggests that some of the changes, such as the truck wash rack, were isolated and nonse-quential and, therefore, would not have caused any significant delay in overall progress of the project. [Id. at 40-41.]

The Board then provided for a remand to the contracting officer to negotiate the amount of the equitable adjustment.

The second Board opinion (issued on January 17, 1980) relates to plaintiffs motion for reconsideration and clarification of the portions of the original Board decision we have quoted. The Board explained its earlier position as follows:

In our original decision we viewed Appellant’s claim for an equitable adjustment based on the 717 days of time extension granted in change orders as a "total time” approach which we rejected for reasons clearly stated on pages 40 and 41. Because the extent of delay was not specifically at issue we remanded that question, along with dollars, to the parties for negotiation.
Should the parties fail to reach agreement on the extent of delay in attempting to negotiate an equitable adjustment and should Appellant return to the Board for a quantum decision, Appellant must be prepared to offer persuasive evidence of change order impacts including specific delays associated therewith. Absent persuasive evidence that change orders delayed unchanged work to the extent of 717 days, we will not accept 717 days as the delay period. A period considerably shorter than that may well be found. [Reconsideration Opinion at 2.]

The parties do not now controvert the Board determination that "[a]n equitable adjustment for impact of modifications on unchanged work under the circumstances of this case should include costs resulting from delay to and disruption of the unchanged contract work,” Bd. Op. at 40, and it would appear that such damages are recoverable under the Changes Clause of the contract. See, e.g., Merritt-Chapman & Scott Corp. v. United States, 192 Ct. Cl. 848, 851, 429 F.2d 431, 432 (1970); Coley Properties Corp. v. United States, 219 Ct. Cl. 227, 234-35, 593 F.2d 380, 384-85 [674]*674(1979). The conflict arises over whether Pathman must establish the extent of the delays for any time-related costs it incurred, or whether it may simply recover its costs based on the full 717 (or 723)-day period of time extensions granted in connection with the numerous contract changes. Plaintiff strongly urges that we adopt the latter position on the ground that the bilateral contract modifications represented accords and satisfactions fixing the period for performance and the extent of delay for unpaid costs reserved in the modifications, thus obviating the need for independently establishing the length of time for which Such unpaid stretch out and extended overhead costs should be paid. As we have said, the Board rejected this view and the plaintiff filed the present suit in our court.3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Doninger Metal Products, Corp. v. United States
50 Fed. Cl. 110 (Federal Claims, 2001)
American Line Builders, Inc. v. United States
38 Cont. Cas. Fed. 76,406 (Court of Claims, 1992)
CCM Corp. v. United States
36 Cont. Cas. Fed. 75,876 (Court of Claims, 1990)
G.M. Shupe, Inc. v. United States
32 Cont. Cas. Fed. 72,712 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
652 F.2d 70, 28 Cont. Cas. Fed. 81,299, 227 Ct. Cl. 670, 1981 U.S. Ct. Cl. LEXIS 196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pathman-construction-co-v-united-states-cc-1981.