American Line Builders, Inc. v. United States

38 Cont. Cas. Fed. 76,406, 26 Cl. Ct. 1155, 1992 U.S. Claims LEXIS 433, 1992 WL 229003
CourtUnited States Court of Claims
DecidedSeptember 14, 1992
DocketNo. 290-87C
StatusPublished
Cited by19 cases

This text of 38 Cont. Cas. Fed. 76,406 (American Line Builders, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Line Builders, Inc. v. United States, 38 Cont. Cas. Fed. 76,406, 26 Cl. Ct. 1155, 1992 U.S. Claims LEXIS 433, 1992 WL 229003 (cc 1992).

Opinion

OPINION

HORN, Judge.

Plaintiff, American Line Builders, Inc. (ALB), filed its “Complaint for Additional Compensation,” pursuant to sections 601-613 of Title 41 of the United States Code, 41 U.S.C. §§ 601-613 (1988), alleging that the defendant, the United States, through its agent, the Department of Energy, Western Area Power Administration (WAPA), directed the plaintiff to perform work in addition to that specified in the contract between the plaintiff and WAPA, by amending and delaying the contract work schedules and requirements. Plaintiff, ALB, seeks compensation for the additional material costs and other additional costs allegedly caused by the work delays.

Prior to filing the complaint in this court, by letter, dated November 25, 1985, ALB submitted its claim for additional compensation to WAPA’s contracting officer requesting $643,198.00 for costs incurred as a result of: (1) changes in structure heights included in Change Order A001; (2) changes associated with a number of the cultural sites; (3) delays in right of way and access road releases; and (4) structure changes/moves directed by WAPA after the issuance of Change Order A001. Then, by letter, dated December 4, 1986, plaintiff submitted a revised claim of $1,768,089.20, and a request for a time extension of 200 days. The December 4, 1986, letter included the claims submitted by ALB in the November 25, 1985 letter, and added additional claims for: change of pins to bolts; [1159]*1159supply guy wire spacers; stringing, clipping and deadending; Davis-Bacon Act classification changes; removal operations; re-mobilization costs; extended overhead; and, tightening hardware and plumbing of structures.

On April 23, 1987, WAPA transmitted to ALB the contracting officer’s decision on ALB’s December, 1986 claim. In his decision, the WAPA contracting officer allowed a total equitable adjustment of $23,411.00 for certain claims related to Change Order A001, the cultural resource sites, certain parcel right-of-ways, and to structure changes/moves. The contracting officer denied ALB’s claims for tightening hardware, plumbing structures, removal operations, Davis-Bacon Act classification changes, supply guy wire spacers, and change out pins for bolts.

In its complaint filed in this court, ALB claims it is due additional compensation for: (1) changes in structure heights included in Change Order A001; (2) changes in cultural resource sites; (3) changes in right-of-way releases; (4) restriction to obtaining access; (5) moving structures; (6) change out pins for bolts; (7) supplying guy wires; (8) stringing, clipping and deadening; (9) changes in Davis-Bacon Act classifications; (10) delays in removal operations; (11) additional re-mobilization costs; (12) extended overhead costs; and (13) tightening hardware and plumbing of structures.

A ten day trial was held, after which, each party submitted extensive post-trial briefs, along with responses, replies and supplements thereto. After careful consideration of the facts and arguments presented by the parties, both at trial and in their written submissions, this court finds, as is more fully discussed below, that the plaintiff is entitled to partial recovery on its claim.

BACKGROUND

Overview

On January 16, 1984, ALB and WAPA entered into a fixed price contract, DE-AC65-84WP15857 (hereinafter the WAPA contract) for the removal of an existing 161 kV wood-pole, H-Frame transmission line in its entirety, approximately 188 miles in length. Additionally, the contract required the plaintiff to furnish all materials and construct a new single circuit, 3-phase, wood-pole, H-frame, 230 kV transmission line, approximately 180 miles in length. The original contract price was $11,708,-300.00.1 According to the terms of the WAPA contract, the construction of the new transmission line was to be completed by December 1, 1985, and the removal of the old transmission line was to be completed by April 1, 1986.

The transmission line is located between Fort Peck and Havre, Montana, along geologically undulating plains and farmland. The Fort Peck Substation, located at Fort Peck Dam, Montana, is at the eastern end of the transmission line and is designated for the purposes of the contract and for this Opinion as point O/l.2 Moving west, the Richardson-Coulee Substation is next in line at structure 28/5. The Malta Substation follows, and is located in the middle end of the transmission line at structure 80/1. The Malta Substation is followed by the Harlem Substation at structure 127/7, and the Chinook Substation at structure 154/5. The end of the transmission line is at Havre, Montana, at structure 178/7.

In accordance with the bid solicitation, the successful bidder was to purchase and supply all materials for the project, with the exception of gate closures. To meet the WAPA contract requirements, ALB entered into contractual arrangements with various subcontractors. ALB subcontracted the work for surveying and clearing [1160]*1160gates.3 ALB also subcontracted with Hughes Brothers to supply the pole top assemblies and cross-arms. The supplier of the conductor was Kaiser Aluminum & Chemical Corporation. Indiana Steel & Wire supplied the guy wire and overhead ground wires. A.B. Chance Co. supplied the anchor materials to Montana Electric Supply Co., from which ALB purchased the materials. ALB purchased ground wire from Copperweld Bimetallies Group. Ham-by-Young supplied most of the insulators. Additional pole insulators were supplied by Lapp, Insulation Division.

On February 10, 1984, ALB contracted with the John C. Taylor Lumber Co. (Taylor Lumber) to supply, treat and deliver to holding areas, and to points along the project route, all wood poles required to be furnished under the WAPA contract. Taylor Lumber, in turn, employed Steve Stark to sort and deliver poles from the holding areas and points of delivery along the transmission line construction route to specific structure sites along the transmission line. Bode Inspection, Inc., under contract to ALB, inspected the poles supplied to ALB by Taylor Lumber Co.

The project schedule was provided for in paragraphs 1.1.3 and 1.1.4.a., Construction Program, General Requirements, of the Contract Specifications No. WC-4-15857-116. The relevant portion of section 1.1.3, “COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK,” is:

a. COMPLETION PERIOD: The contractor shall begin work within 30 calendar days after receipt of notice to proceed, and shall complete construction of the new transmission line by December 1, 1985, and removal of the existing transmission line by April 1, 1986. The period allowed for the completion of the work shall be reduced by one calendar day for each calendar day in excess of 10 calendar days, or any extension thereof, elapsing between the contractor’s receipt of and return of properly executed contract, and performance and payment bonds as required in the Bid Form (Standard Form 21).
For notice to proceed purposes the contract is divided into three parts as follows:
PART A: Notice to Proceed will be issued as soon as practicable after award of the contract for preparatory work including planning, organizing, scheduling, and procurement of materials.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
Hartford Casualty Insurance v. City of Marathon
825 F. Supp. 2d 1276 (S.D. Florida, 2011)
Hartford Cas. Ins. Co. v. CITY OF MARATHON
825 F. Supp. 2d 1276 (S.D. Florida, 2011)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Datalect Computer Services, Ltd. v. United States
42 Cont. Cas. Fed. 77,379 (Federal Claims, 1998)
SIPCO Services & Marine Inc. v. United States
42 Cont. Cas. Fed. 77,277 (Federal Claims, 1998)
District of Columbia v. Organization for Environmental Growth, Inc.
700 A.2d 185 (District of Columbia Court of Appeals, 1997)
Valley View Enterprises, Inc. v. United States
40 Cont. Cas. Fed. 76,920 (Federal Claims, 1996)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,406, 26 Cl. Ct. 1155, 1992 U.S. Claims LEXIS 433, 1992 WL 229003, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-line-builders-inc-v-united-states-cc-1992.