United States of America v. AHTNA Construction and Primary Products, LLC

CourtDistrict Court, D. Alaska
DecidedAugust 17, 2021
Docket4:19-cv-00010
StatusUnknown

This text of United States of America v. AHTNA Construction and Primary Products, LLC (United States of America v. AHTNA Construction and Primary Products, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Alaska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America v. AHTNA Construction and Primary Products, LLC, (D. Alaska 2021).

Opinion

3 IN THE UNITED STATES DISTRICT COURT

4 FOR THE DISTRICT OF ALASKA 5

6 UNITED STATES for the use & 7 benefit of MIDSTATE EQUIPMENT, INC.; MIDSTATE EQUIPMENT, Case No. 4:19-cv-00010-JWS 8 INC., 9 Plaintiffs, FINDINGS OF FACT AND 10 CONCLUSIONS OF LAW 11 vs.

12 AHTNA CONSTRUCTION & PRIMARY PRODUCTS, LLC; 13 GREAT AMERICAN INSURANCE 14 COMPANY,

15 Defendants. 16

18 19 I. INTRODUCTION AND STATEMENT OF JURISDICTION 20 This Miller Act lawsuit was tried to the court from July 12, 2021, through 21 July 16, 2021, in Anchorage, Alaska. This court has subject matter jurisdiction 22 pursuant to 40 U.S.C. § 3133. The parties’ several state law claims also were tried. 23 24 They are so related to the Miller Act claim as to form part of the same controversy. 25 This court has jurisdiction over the state law claims pursuant to 28 U.S.C. § 1367(a). 26 Pursuant to Federal Rule of Civil Procedure 52, the court sets out its 27 28 findings of fact and conclusions of law below. 1 II. FINDINGS OF FACT 2 1. Plaintiff Midstate Equipment, Inc. (hereinafter “Midstate”), is an 3 Alaska corporation. It is a civil construction contractor located in Delta Junction, 4 5 Alaska. 6 2. Defendant Ahtna Construction and Primary Products, LLC 7 (hereinafter “Ahtna”), is an Alaska limited liability company. It is a general contractor 8 9 specializing in civil construction. 10 3. Defendant Great American Insurance Company (hereinafter 11 “Great American”) is an Ohio corporation authorized to do business in Alaska as a 12 surety. 13 14 4. Ahtna entered into an agreement with the United States 15 Department of Agriculture, Natural Resources Conservation Service (hereinafter 16 “NRCS”), in 2018 to perform work at the Delta Clearwater Remediation Project 17 18 Phase 2 near Delta Junction, Alaska (hereinafter “the Project”). The NRCS/Ahtna 19 contract is referred to hereinafter as the “Prime Contract.” 20 5. As required by law, Ahtna provided a payment bond (“the Bond”) 21 22 for the Project. The Bond was issued by Great American. 23 6. Among other things, the Prime Contract required Ahtna to 24 provide and spread topsoil and woody debris on the Project site in accordance with the 25 specifications in the Prime Contract. Ahtna agreed that it would be paid on a unit price 26 27 basis of a fixed amount per square yard. 28 1 7. Prior to submitting its bid for the Project, Ahtna had received a 2 proposal from Midstate (hereinafter “Quote”) to supply and deliver top soil and woody 3 debris to the Project. The Quote was given to Ahtna on January 4, 2018. In the Quote, 4 5 Midstate offered to deliver up to 424,450 square yards of topsoil and up to 517,829 6 square yards of woody debris. No other supplier proposed to provide and deliver 7 topsoil and woody debris. Ahtna used Midstate’s Quote in preparing its bid to 8 9 construct the Project. 10 8. Midstate proposed to provide and deliver topsoil at a price of 11 $2.62 per square yard. The Quote stated: “Measurement for payment will be by an 12 agreed price per cuyd per truck load.” 13 14 9. Midstate proposed to provide and deliver woody debris at a price 15 of $2.60 per square yard. The Quote states: “Measurement for payment will be by the 16 truck load.” 17 18 10. Ahtna issued purchase order PO-07020-001 to Midstate 19 (hereinafter “Purchase Order”) for supplying and delivering topsoil and woody debris 20 among other things. The Purchase Order was executed by both parties. The Purchase 21 22 Order included as an attachment a copy of Midstate’s Quote and stated in bold 23 italicized language, “Midstate Original Quote Attached as Reference Only.” For 24 NRCS, the Quote would have been very significant because it showed Midstate would 25 provide the quantities of topsoil and woody debris required by the Prime Contract. The 26 27 Purchase Order was a unit price agreement using square yards for units of delivery. It 28 1 specified payment terms of “Net 30.” Unit costs were specified as $2.62 per square 2 yard for topsoil and $2.60 per square yard for woody debris. 3 11. Prior to commencement of deliveries by Midstate, Ahtna and 4 5 Midstate did not discuss, much less agree on, the dimensions of a truckload nor a unit 6 price per truckload for either topsoil or woody debris. 7 12. NRCS estimated that the Project would require 424,450 square 8 9 yards (“SY”) of topsoil and 517,829 square yards of woody debris.1 NRCS prepared 10 detailed Project specifications (“Specifications”) describing the types of materials to 11 be used and the methods employed for their placement.2 12 13. The Specifications stated Ahtna would be paid for both topsoil 13 14 and woody debris based on “in-place” measurements. Ahtna and NRCS would 15 together use professional surveyors to measure the total surface covered by these 16 materials, determining the amount of surface area through a “horizontal projection” of 17 18 the surveyed “perimeter.”3 19 14. For topsoil measurements, the parties would then calculate total 20 square yards of material according to the measured perimeter and the uniform 21 22 thickness or “lift” of the topsoil spread by Ahtna.4 23 24 25 26 1 Trial Exhibit (hereinafter “Ex.”) 6, p. 6. 27 2 Ex. 3. 3 Ex. 3, pp. 7, 11. 28 4 Trial Transcript (hereinafter “Tr.”). Vol. 3, pp. 107–11 (T. Champine) (describing process of measuring placed materials). 1 15. The Project drawings instructed Ahtna to spread the “loose” 2 topsoil into an eight-inch-thick lift throughout the Basin and adjoining areas.5 The 3 Specifications instructed Ahtna to spread the topsoil using a “low ground pressure 4 5 (LGP) type dozer . . . equipped with and operating by GPS machine control.”6 GPS 6 devices mounted on the blade of the dozer monitored the height of the blade from the 7 subgrade.7 The GPS machine control would adjust the height of the blade to 8 9 compensate for any changes in the subgrade.8 The result was a consistent “loose” lift 10 thickness. 11 16. Section 7(a)(6) of the Specifications provided: “The measured 12 thickness of the topsoil shall be from the approved subgrade to the top of the loose 13 14 topsoil before track-walking.”9 “Track-walking” refers to the compression of the 15 topsoil lift by the tracks of the dozer immediately after the blade at the front of the 16 dozer has cut the loose topsoil into a lift.10 The Specifications thus required that the 17 18 dozer maintain a blade height of eight inches to create the loose lift for purposes of 19 measurement for payment, but did not require any particular compaction density or 20 depth after the blade had “cut” this lift and the tracks of the dozer immediately 21 22 compacted the topsoil. 23 24

25 5 Ex. 2, pp. 7–10, 17–19. 26 6 Ex. A, p. 53. 7 Tr. Vol. 4, p. 134 (D. McKoon); Tr. Vol. 4, p. 99 (D. O’Donnell) (“That dozer blade does 27 not go below that 8 inches.”). 8 Tr. Vol. 3, pp. 108–09 (T. Champine). 28 9 Ex. A, p. 53. 10 Tr. Vol. 3, pp. 108-109 (T. Champine). 1 17. The Project Specifications also provided detailed requirements 2 for “furnishing and spreading woody debris at locations shown on the drawings.”11 3 The woody debris needed to have “a minimum stem length of four (4) feet and a 4 5 minimum diameter of four (4) inches at the largest end.”12 Ahtna needed to spread the 6 woody debris in a way that would result in “ground coverage” of 20 to 40 percent.13 7 18.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alexander v. Gardner-Denver Co.
415 U.S. 36 (Supreme Court, 1974)
S & R Metals, Inc. v. C. Itoh & Co. (America), Inc.
859 F.2d 814 (Ninth Circuit, 1988)
Brady v. State
965 P.2d 1 (Alaska Supreme Court, 1998)
Alaska Sales and Service, Inc. v. Millet
735 P.2d 743 (Alaska Supreme Court, 1987)
Western Pioneer, Inc. v. Harbor Enterprises, Inc.
818 P.2d 654 (Alaska Supreme Court, 1991)
City of Whittier v. Whittier Fuel & Marine Corp.
577 P.2d 216 (Alaska Supreme Court, 1978)
Sumner v. Fel-Air, Inc.
680 P.2d 1109 (Alaska Supreme Court, 1984)
State v. O'Neill Investigations, Inc.
609 P.2d 520 (Alaska Supreme Court, 1980)
Dowling Supply & Equipment, Inc. v. City of Anchorage
490 P.2d 907 (Alaska Supreme Court, 1971)
Guard v. P & R ENTERPRISES, INC.
631 P.2d 1068 (Alaska Supreme Court, 1981)
In Re Marion Merrell Dow Inc., SEC. Lit.
965 F. Supp. 25 (W.D. Missouri, 1997)
GNP Commodities, Inc. v. Walsh Heffernan Co.
420 N.E.2d 659 (Appellate Court of Illinois, 1981)
Pomerantz Paper Corp. v. New Community Corp.
25 A.3d 221 (Supreme Court of New Jersey, 2011)
Borgen v. a & M MOTORS, INC.
273 P.3d 575 (Alaska Supreme Court, 2012)
Monzingo v. Alaska Air Group, Inc.
112 P.3d 655 (Alaska Supreme Court, 2005)
Soules v. Ramstack
95 P.3d 933 (Alaska Supreme Court, 2004)
Estate of Polushkin Ex Rel. Polushkin v. Maw
170 P.3d 162 (Alaska Supreme Court, 2007)
Weiner v. Burr, Pease & Kurtz, P.C.
221 P.3d 1 (Alaska Supreme Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
United States of America v. AHTNA Construction and Primary Products, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-v-ahtna-construction-and-primary-products-llc-akd-2021.