Hawaiian Dredging Construction Company, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedFebruary 14, 2023
Docket22-339
StatusUnpublished

This text of Hawaiian Dredging Construction Company, Inc. v. United States (Hawaiian Dredging Construction Company, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hawaiian Dredging Construction Company, Inc. v. United States, (uscfc 2023).

Opinion

In the United States Court of Federal Claims

HAWAIIAN DREDGING CONSTRUCTION COMPANY, INC,

Plaintiff, No. 22-339 (Filed: February 14, 2023) v.

THE UNITED STATES,

Defendant.

Michael Charles Zisa, Washington, DC, for Plaintiff.

Jimmy S. McBirney, Civil Division, United States Department of Justice, Washington, DC, for Defendant.

OPINION AND ORDER

LERNER, Judge.

This is a case under the Contract Disputes Act (“CDA”), 41 U.S.C. § 7101, involving a firm fixed-price, design-build contract (the “Contract”) between Plaintiff Hawaiian Dredging and Construction Company (“HDCC”) and the United States Department of Transportation, acting through the Federal Highway Administration, Central Federal Lands Highway Division (“CFLHD” or the “Agency”). HDCC seeks review of the contracting officer’s final decision (“COFD”) denying its claim for an equitable adjustment. It believes that it is entitled to an equitable adjustment to the Contract “to compensate HDCC for delays and increased costs incurred as a result of changes in the work.” Am. Compl. ¶ 30, ECF No. 14.

The Government moves to dismiss the Amended Complaint under Rule 12(b)(6) of the United States Court of Federal Claims (“RCFC”). It argues that Plaintiff fails to state a claim upon which relief may be granted because it “bore the risk of increased costs” under the Contract, and “does not plausibly allege any directed or constructive contract changes, or that HDCC performed any uncompensated work outside the scope of its contractually mandated responsibilities.” Def.’s Mot. to Dismiss (“Def.’s Mot.”) at 1, ECF No. 15.

For the reasons set forth below, the Motion to Dismiss is GRANTED, and the case is DISMISSED without prejudice. I. Factual Background1

A. The Project

HDCC was the general contractor for the Lahaina Bypass 1B-2 design-build construction project in Lahaina, Maui, Hawaii (the “Project” or “Lahaina Bypass”). Am. Compl. ¶ 4. This was a fixed-unit-price, design-build highway project in the amount of $38,671,000. Id. The goal of the Project was to relocate the terminus of the Lahaina Bypass to stop shoreline erosion, coastal hazards, and traffic congestion on the Honoapiilani Highway. Id. at ¶ 6. The Project anticipated extending the existing road on both sides, constructing an overpass and box culverts, grading for drainage, and installing road and bridge safety features. Id. at ¶ 7. To do this work, HDCC alleges it required final Rights of Way (“ROWs”) from landowners near the highway, relocation of overhead utilities, and local, state, and federal permits. Id. at ¶¶ 8–9. On May 25, 2018, the Project opened to the public, and by July 24, 2018, HDCC’s Contract work was substantially complete. Id. at ¶ 10.

B. The Solicitation and Competition

On October 1, 2015, CFLHD, in partnership with the Hawaii Department of Transportation (“HDOT”), issued a Request for Qualifications (“RFQ”) seeking potential contractors to participate in the pre-qualification phase of the Project. Def.’s App. at 166–68, ECF No. 15-1. Plaintiff alleges that CFLHD “represented that it would acquire the necessary ROWs prior to issuance of the [notice to proceed].” Pl.’s Resp. to Mot. to Dismiss (“Pl.’s Resp.”) at 10, ECF No. 18 (citing Pl.’s Ex. A at 5-6, ECF No. 14-1); see also Am. Compl. ¶ 35. Plaintiff quotes from the RFQ:

There are two (2) right-of-way acquisitions required within the limits of this project; one private landowner and Maui County (sic). The right-of-way acquisition is expected to be completed prior to the issuance of the RFP [Request for Proposals].

Pl.’s Ex. A at 2 (quoting Def.’s App. at 167) (emphasis removed).

On December 7, 2015, HDCC was short-listed to participate in Phase Two of the solicitation. Id. On December 18, 2015, CFLHD, in partnership with HDOT, issued a Request for Proposals (“RFP” or “Solicitation”). Id. The “Government Furnished Information” section of the RFP stated:

1 This section does not set forth factual findings. Rather, it describes the case in terms of the facts alleged in the Amended Complaint, which must be taken as true, with all reasonable inferences construed in Plaintiff’s favor on a motion to dismiss. See Erickson v. Pardus, 551 U.S. 89, 93–94 (2007).

2 Due to their size these files will be placed on CD and sent to each firm. o Right of Way Dedication of Deed documentation o Final Environmental Assessment/finding of No Significant Impact o Survey Data o Alternative No. 3 Profile

Id.; Pl.’s Ex. 1 at A-11, ECF No. 28-1 (RFP). The RFP also required that:

(1) Each proposal include “the plan and profile of the roadway alignment, including typical sections” and the “proposed alignment and maintenance limits as it relates to available right-of-way”; and

(2) The Contractor locate and identify all utilities within the project area and “cooperate with utility owners to expedite the relocation and adjustment of their utilities to minimize interruption of service, duplication of work, and delays if relocations or adjustments are needed” and “prepare utility agreements for [CFLHD], to be executed by HDOT.”

Pl.’s Resp. at 4 (quoting Pl.’s Ex. A at 3) (cleaned up); see also Pl.’s Ex. 1 at A-14, E-11 (RFP). HDCC alleges that the Alternative No. 3 Profile was a “map depicting a roadway alignment which had been previously prepared for, and included as part of, HDOT’s Final Environmental Assessment/Finding of No Impact . . . covering the Project.” Pl.’s Ex. A. at 2.

On April 26, 2016, HDCC submitted its Price Proposal and a Technical Proposal. Pl.’s Ex. A at 3. HDCC alleges that its Technical Proposal “included a detailed roadway plan and repeatedly and unequivocally stated that the basis for the proposed roadway alignment was Alternative No. 3 as described in the Finding of No Impact furnished by CFLHD at the time of issuance of the RFP.” Id. at 3 (cleaned up). Plaintiff states that when it submitted its bid, it believed that CFLHD had already secured the required ROW documents and permits—or would at least do so prior to issuing the notice to proceed—and that neither the Government nor HDCC were required to obtain grading permits from the County of Maui. Pl.’s Ex. A at 6. In fact, these requirements were not completed until after contract performance commenced. Id.

C. The Contract

On June 3, 2016, CFLHD awarded HDCC the Contract. Pl.’s Ex. A at 3. CFLHD issued notice to proceed on June 29, 2016. Id. The Contract incorporated Federal Acquisition (“FAR”) 52.236-7, Permits and Responsibilities, which states:

3 The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work.

Def.’s App. at 38 (Contract). The Contract contemplated that the Government would execute final ROWs, but also required HDCC to “[p]repare right of way plans and any legal descriptions documents to facilitate the final acquisition of the design and permanent right of way to accommodate the maintenance and operation of the facility by . . . HDOT”; “[p]repare the documents according to HDOT standards and specifications”; and “[o]btain any required title work and field work to complete a boundary study if required by HDOT.” Id. at 96 (Contract clause 111.11, Right of Way).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
United States v. Brooks-Callaway Co.
318 U.S. 120 (Supreme Court, 1943)
Erickson v. Pardus
551 U.S. 89 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Rick's Mishroom Service, Inc. v. United States
521 F.3d 1338 (Federal Circuit, 2008)
International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
Figueroa v. United States
466 F.3d 1023 (Federal Circuit, 2006)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Fraser Construction Company v. United States
384 F.3d 1354 (Federal Circuit, 2004)
Crewzers Fire Crew Transport, Inc. v. United States
111 Fed. Cl. 148 (Federal Claims, 2013)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Crewzers Fire Crew Transport, Inc. v. United States
741 F.3d 1380 (Federal Circuit, 2014)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Solaria Corporation v. United States
123 Fed. Cl. 105 (Federal Claims, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Hawaiian Dredging Construction Company, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hawaiian-dredging-construction-company-inc-v-united-states-uscfc-2023.