Merritt-Chapman & Scott Corporation v. The United States

429 F.2d 431, 192 Ct. Cl. 848, 1970 U.S. Ct. Cl. LEXIS 157
CourtUnited States Court of Claims
DecidedJuly 15, 1970
Docket44-66
StatusPublished
Cited by28 cases

This text of 429 F.2d 431 (Merritt-Chapman & Scott Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merritt-Chapman & Scott Corporation v. The United States, 429 F.2d 431, 192 Ct. Cl. 848, 1970 U.S. Ct. Cl. LEXIS 157 (cc 1970).

Opinion

ON PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

PER CURIAM:

This Wunderlich Act suit was referred to Trial Commissioner Louis Spector for preparation and filing of his opinion and recommended conclusion of law. The commissioner has done so in a report dated February 25, 1970. The Government has requested review. The plaintiff supports the commissioner’s report. The case has been submitted to *432 the judges on oral argument and briefs. We agree with Commissioner Spector.

Wholly apart from the Suspension of Work clause, it is established that under the Changes and Changed Conditions articles the equitable adjustment can include increased costs which were the direct and necessary result of the change or the changed condition, where that condition or change directly leads to disruption, extra work, or new procedures. See Paul Hardeman, Inc. v. United States, 406 F.2d 1357, 186 Ct. Cl. 743 (1969); Ivey Bros. Constr. Co., Eng. BCA No. 1764 (1960). At least a portion of the claimed cost increase in this case — it is unnecessary to determine how large a portion — falls within this class and would be recoverable even if a Suspension of Work clause had been omitted from the contract.

A Suspension of Work provision was included, however, and under that clause the remainder of the cost increase, to the extent properly proved, can be recovered in this proceeding. There is no doubt, as the trial commissioner holds, that the work was in fact suspended and delayed for the Government’s convenience, and also that there was a significant change in design. It is immaterial, in this instance, whether or not the suspension and delay was due, in whole or in part, to the Government’s fault. There are occasions for the Suspension of Work clause to operate when the Government is at fault, as we recently noted (See Chaney & James Constr. Co. v. United States, 421 F.2d 728, 731-733, 190 Ct.Cl. 699, 705-708, (Feb. 1970)), but the clause can likewise be effective, as we have also held, when there is a suspension not due to the Goverment’s fault, dereliction, or responsibility. See T. C. Bateson Constr. Co. v. United States, 319 F.2d 135, 162 Ct.Cl. 145 (1963); John A. Johnson & Sons v. United States, 180 Ct.Cl. 969 (1967). An instance of the latter category is a suspension and delay which lasts so long (regardless of the absence of government fault) that the contractor cannot reasonably be expected to bear the risk and costs of the disruption and delay. That is one type of suspension and delay “for an unreasonable length of time causing additional expense”, within the meaning of the clause. Depending on the circumstances, a delay due to a non-fault suspension by the Government can obviously be so protracted that it would be unreasonable to expect the contractor to shoulder the added expense himself. We think that in its terms and its purpose the Suspension of Work clause covers that situation, among others.

The trial commissioner has properly concluded that that is the situation here. On this record, and with this project, it is impossible to hold other than that the delay-due-to-suspension of 419 days (considerably more than one year) * was “for an unreasonable length of time.” The contractor, informed by the Suspension of Work article that it would receive compensation for unreasonable delays due to a non-fault suspension, would not expect (and rightly so) to bear the costs of a delay of this character and magnitude. The delay was therefore “unreasonable”. There is no finding by the Board, and defendant does not claim, that some lesser part of this 419 days would have been a “reasonable” delay (cf. Chaney & James Constr. Co. v. United States, 421 F.2d 728, 735-736, 190 Ct. Cl. 699, 712-713 (Feb. 1970)). In any event, the circumstances of the case would preclude a finding that any delay after April 20, 1960, would have been a “reasonable” one for which plaintiff should bear the extra expense.

The court understands Commissioner Spector’s opinion to be fully consonant with this analysis of the case, and therefore adopts his opinion (in the light of and as supplemented by the foregoing discussion) as the basis for judgment.

*433 Accordingly, plaintiff’s motion for summary judgment is granted and defendant’s cross-motion is denied. Further proceedings are stayed pursuant to Rule 167 for a period of ninety (90) days to afford the parties an opportunity to obtain an administrative resolution of the additional adjustment in contract price to which plaintiff is entitled. With respect to the plaintiff’s claim for an extension of time of 419 days, in lieu of the 365 days allowed by the Board, it is held that there is no support in the record for a finding that plaintiff was delayed for any lesser period than that represented by the suspension of the central features of this project (the dam) from April 20, 1960, to June 12, 1961, and therefore that plaintiff is entitled to the additional claimed extension of 54 calendar days.

OPINION OF COMMISSIONER

SPECTOR, Commissioner:

This is a contract claim in the approximate amount of $2,000,00o, 1 2arising out of the construction by plaintiff of a dam and outlet works, power intake works and roads at Cougar Reservoir on the South Fork of the McKenzie River in Central Eastern Oregon. The contract, in the original estimated amount of $23,-985,564, was executed June 9, 1959, and administered on behalf of defendant by the Army Corps of Engineers. The claim has heretofore been the subject of a decision by that agency’s contracting officer and board of contract appeals. 2 Therefore, to the extent that it is a decision on a question of fact, it is subject to review by this court against the record compiled by the agency. 3

Generally, the issue presented involves the adequacy of the adjustment in contract price and time of performance allowed by defendant under the circumstances hereinafter described. At issue are the contract clauses entitled GC-11, “Suspension of Work” 4 ; Article 4, “Changed Conditions” 5 ; and Article 3, “Changes.” 6 As the opinion of the Engineers Board of Contract Appeals states at the outset, “[f] actually the matter is not too complicated.”

Cougar Dam was constructed in very rugged country across a narrow river *434 valley flanked by hills which rise precipitously to a height of about 700 feet on either side of the river. The top of the dam is about 519 feet above the existing river bed (which occurs at about elevation 1270).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GSI Construction Corp.
Armed Services Board of Contract Appeals, 2025
Gideon Contracting, LLC
Armed Services Board of Contract Appeals, 2025
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Doninger Metal Products, Corp. v. United States
50 Fed. Cl. 110 (Federal Claims, 2001)
Croman Corp. v. United States
49 Fed. Cl. 776 (Federal Claims, 2001)
Scheck Mechanical Corp. v. Borden, Inc.
186 F. Supp. 2d 724 (W.D. Kentucky, 2001)
Northern States Power Co. v. United States
43 Cont. Cas. Fed. 77,450 (Federal Claims, 1999)
Bonacorso Construction Corp. v. Commonwealth
668 N.E.2d 366 (Massachusetts Appeals Court, 1996)
Commercial Contractors, Inc. v. United States
39 Cont. Cas. Fed. 76,582 (Federal Claims, 1993)
CCM Corp. v. United States
36 Cont. Cas. Fed. 75,876 (Court of Claims, 1990)
Beauchamp Construction Co. v. United States
34 Cont. Cas. Fed. 75,453 (Court of Claims, 1988)
Penberthy Electromelt International Inc. v. United States
33 Cont. Cas. Fed. 74,887 (Court of Claims, 1986)
G.M. Shupe, Inc. v. United States
32 Cont. Cas. Fed. 72,712 (Court of Claims, 1984)
Savoy Construction Co. v. United States
31 Cont. Cas. Fed. 71,109 (Court of Claims, 1983)
Pathman Construction Co. v. United States
652 F.2d 70 (Court of Claims, 1981)
DeMatteo Construction Co. v. United States
600 F.2d 1384 (Court of Claims, 1979)
Consolidated Molded Products Corp. v. United States
600 F.2d 793 (Court of Claims, 1979)
Fruehauf Corp. v. United States
587 F.2d 486 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
429 F.2d 431, 192 Ct. Cl. 848, 1970 U.S. Ct. Cl. LEXIS 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merritt-chapman-scott-corporation-v-the-united-states-cc-1970.