Excavation Construction, Inc. v. Washington Metropolitan Area Transit Authority

624 F. Supp. 582, 1984 U.S. Dist. LEXIS 24903
CourtDistrict Court, District of Columbia
DecidedJune 21, 1984
DocketCiv. A. 83-1125
StatusPublished
Cited by4 cases

This text of 624 F. Supp. 582 (Excavation Construction, Inc. v. Washington Metropolitan Area Transit Authority) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Excavation Construction, Inc. v. Washington Metropolitan Area Transit Authority, 624 F. Supp. 582, 1984 U.S. Dist. LEXIS 24903 (D.D.C. 1984).

Opinion

MEMORANDUM

JOHN LEWIS SMITH, Jr., Senior District Judge.

Plaintiff Excavation Construction, Inc. brings this action for monetary relief against defendant Washington Metropolitan Area Transit Authority (“WMATA”). Currently before the Court are cross-motions for summary judgment with respect to Count I of the complaint, and defendant’s motion for summary judgment on Count II.

This case is a dispute about a “disputes clause” in a construction contract. In May 1973, defendant awarded a $21 million contract to plaintiff for construction of the Fort Totten, Takoma Park, and Silver Spring Metrorail stations. The contract included a provision, standard in WMATA construction agreements, concerning disputes “arising under this contract.” In brief, the contract called for administrative disposition involving initial review by a *584 “contracting officer,” and then by WMA-TA’ s “Board of Directors or its duly authorized representative for the determination of such appeals.” The contract also included a standard “suspension of work” clause. 1

Defendant did not issue its “notice to proceed” on the project until August 1973. As a result, plaintiff submitted a claim to WMATA for additional compensation in the amount of $818,000 because of the delay. The matter was processed pursuant to the disputes clause, and in September 1976, the WMATA contracting officer issued a decision awarding some $272,576 to plaintiff.

In December 1976, plaintiff noticed an appeal to the United States Army Corps of Engineers Board of Contract Appeals (“BCA”). The BCA held hearings in October 1979, and on April 30, 1982, granted plaintiff an award of $420,036 (including the $272,576 previously awarded). The award included compensation for “Home Office Overhead” allegedly incurred by plaintiff as a result of the 66-day delay in the issuance of the notice to proceed. 2

In May 1982, defendant moved the BCA to reconsider its ruling on the home office overhead issue. The BCA in a six-page opinion denied the motion on September 14, 1982.

Throughout late 1982 and early 1983, plaintiff and defendant corresponded about the WMATA General Manager’s review of the matter. On February 22, 1983, the General Manager executed a “final decision” on the appeal:

“Pursuant to the authority vested in the undersigned by the Washington Metropolitan Area Transit Authority (WMA-TA) Board of Directors to render a final decision in any dispute under the disputes article of a WMATA contract, and
“upon consideration of the record of proceedings before the Corps of Engineers Board of Contract Appeals together with the advisory opinions of that Board dated April 30, 1982 and September 14, 1982, which I hereby adopt, it is the final decision of the undersigned that the captioned appeal is in all respects SUSTAINED in the amount of $420,036.

*585 /s/ Richard S. Page

Richard S. Page

General Manager”

Defendant, however, did not notify plaintiff of this decision, and plaintiff did not receive a copy until May 1983.

Meanwhile, on April 19, 1983, plaintiff filed this suit, seeking recovery of the $147,460 difference between the BCA’s and the contracting officer’s award, and punitive damages for defendant’s “bad faith in the administering the Contract with respect to the resolution” of this matter (Count I). Count II involved several other disputes and their resolution and sought over $12 million in damages.

Ten days after plaintiff filed suit, defendant’s general manager issued an “amended final decision:”

“[u]pon re-consideration of my unissued decision dated February 22, 1983 in light of the decision of the GSBCA in Capital Electric Company, GSBCA Nos. 5316 and 5317, February 17, 1983, and the legal precedent therein cited, and it appearing that applicability of the Eichleay formula in this appeal rises [sic] a substantial legal question and that by reason of the Contractor’s action in the United States District Court for the District of Columbia, CA No. 83-1125 filed on April 19, 1983, the claim involved in this appeal has been made the subject of litigation between WMATA and the Contractor, it is the final decision of the undersigned that my unissued decision dated February 22, 1983 is hereby vacated; that the advisory opinions of the Eng BCA dated April 30, 1982 and September 14, 1982, to the extent they recommend entitlement for items other than home office overhead in the sum of $317,365.00 for an equitable adjustment to the Contract are hereby adopted; and the captioned appeal is SUSTAINED in the amount of $317,365.00.”

Defendant forwarded this document and the original (February 22) decision to plaintiff on May 2.

A. Count I

As noted, plaintiff filed its complaint before WMATA’s general manager issued his decision; indeed, defendant’s “failure to act on the Board’s decision” was the basis of the suit. See Complaint ¶ 56. Although plaintiff has not sought leave under Fed.R. Civ.P. 15(d) to supplement its pleadings to reflect this development, both parties treat the validity of the general manager’s decision as the central issue presented in Count I. Plaintiff makes a threshold challenge. The dispute resolution provision, plaintiff argues, does not contemplate any participation by the general manager; he- has “no authority to alter, modify, or reverse a decision made by the [BCA]” under the terms of the disputes clause in the contract. Pls.Mem.Pts.Auth.SJ. at 1-4. Defendant submits that the contract places final appeals authority in the general manager and that the BCA merely provides “advisory opinions,” which may be accepted or rejected by the general manager.

Defendant is correct: final authority in disputes clause appeals rests with the WMATA general manager. The question turns on interpretation of the contractual provision placing “final and conclusive” authority in the WMATA “Board of Directors or its duly authorized representative for the determination of such appeals” (emphasis supplied). By resolution dated July 7, 1967, the WMATA Board expressly designated the general manager as its “duly authorized representative” for “fully and finally” deciding disputes clause appeals (DX la). Moreover, the Board by resolution dated June 3, 1971, designated the BCA as its “authorized representative” to “hear and render advisory opinions and to “recommend to the general manager ... final decisions on appeals arising under the Disputes clause of Authority contracts” (DX 1) (emphasis supplied).

It thus appears that the WMATA Board has spoken quite clearly as to the identity of its “duly authorized representative” for final determinations on appeals, see Square Construction Co. v. WMATA, 657 F.2d 68, 69 n.1 (4th Cir.1981); WMATA v. Rago

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
624 F. Supp. 582, 1984 U.S. Dist. LEXIS 24903, Counsel Stack Legal Research, https://law.counselstack.com/opinion/excavation-construction-inc-v-washington-metropolitan-area-transit-dcd-1984.