Square Construction Company and La Fera Contracting Company v. Washington Metropolitan Area Transit Authority

657 F.2d 68, 29 Cont. Cas. Fed. 81,782, 32 Fed. R. Serv. 2d 765, 1981 U.S. App. LEXIS 18424
CourtCourt of Appeals for the Fourth Circuit
DecidedAugust 17, 1981
Docket80-1447
StatusPublished
Cited by102 cases

This text of 657 F.2d 68 (Square Construction Company and La Fera Contracting Company v. Washington Metropolitan Area Transit Authority) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Square Construction Company and La Fera Contracting Company v. Washington Metropolitan Area Transit Authority, 657 F.2d 68, 29 Cont. Cas. Fed. 81,782, 32 Fed. R. Serv. 2d 765, 1981 U.S. App. LEXIS 18424 (4th Cir. 1981).

Opinion

WIDENER, Circuit Judge:

This case is before us on the appeal of Square Construction Company and La Fera Contracting Company (Square/La Fera) from the order of the United States District Court for the Eastern District of Virginia denying Square/La Fera’s motion pursuant to Federal Rules of Civil Procedure 60(b)(2) and (3) to vacate its judgment previously entered in favor of the Washington Metropolitan Area Transit Authority (WMATA or the Authority). We hold that the district court’s denial of that motion was an abuse of discretion, and remand the case for further proceedings with instructions.

On February 3, 1972, WMATA awarded Square/La Fera a contract for the construction of the C — 7 section of the Washington metropolitan area subway system at a total contract price in excess of $23,000,000.00. In early January of 1974, following expressions of concern by WMATA over the lack of progress under that contract, the Authority terminated Square/La Fera’s contract for alleged default, with some $14,-895,910.75 in work remaining to be performed. WMATA subsequently agreed to pay another contractor $19,717,576.13 to complete the C-7 contract, and charged the approximately $4.8 million in excess reprocurement costs to Square/La Fera.

Square/La Fera contested its termination for default and the Authority’s assessment of excess costs against it in separate appeals to the Corps of Engineers Board of Contract Appeals. 1 At the August 1977 hearing on the issue of excess costs, Square/La Fera claimed that the assessment of such costs was improper because they were not minimized by WMATA’s method of reprocurement. See Marley v. United States, 423 F.2d 324, 191 Ct.Cl. 205 (1970). As proof, it compared the $19.7 *70 million paid by WMATA for completion of the C-7 contract with La Fera’s estimate of $12 million and an independent expert’s estimate of $13 million.

To bolster its position on this issue in its case before the BCA, Square/La Fera sought information concerning WMATA’s reprocurement process. On March 29, 1977, it formally requested in writing that WMA-TA make the following documents available to it for inspection and copying:

The requested documents are:
1. All documents relating to the reprocurement contract, including but not limited to the following:

When WMATA failed to include any estimate of the reprocurement costs in its response to this request, Square/La Fera specifically requested to be “ . .. furnished with a copy of the Authority’s Estimate (together with the breakdown of items and back-up materials) for completion of C-7 after termination.” This prompted WMA-TA to provide a copy of an estimate originally prepared by DeLeuw Cather, WMA-TA’s General Engineering Consultant, and adopted without alteration by the Authority. This estimate was in the amount of $19,146,463.23, and, as the official Authority estimate, was used for the purpose of assessing the reasonableness of the bids received by WMATA during reprocurement. As. this estimate was within a small percentage of the amount paid upon reprocurement and because the Board discounted Square/La Fera’s estimate of $12 million as self serving and unreliable, the Board found that WMATA’s method of reprocurement was reasonable and that the excess costs were properly assessed against Square/La Fera. The Board’s decisions in favor of WMATA on both default and reprocurement and damages were adopted by the Authority through its General Manager. 2

Pursuant to D.C. Code § 1 — 1434 (1973) and Article 1.6 of the contract, 3 Square/La Fera sought judicial review of those administrative decisions in the United States District Court for the Eastern District of Virginia. The district court affirmed the decision of the Authority on both issues, from which Square/La Fera appealed to this court in No. 79-1510. That case is also today decided.

In late July of 1979, following entry of the district court’s judgment affirming the Board’s order, Square/La Fera became aware that WMATA had withheld an estimate of the cost of completion of the C-7 section that was substantially lower than the DeLeuw Cather estimate it had adopted. While this estimate, prepared by Bechtel Associates, an engineering firm of national reputation and WMATA’s Construction Consultant, has never been produced in court or for Square/La Fera’s examination, WMATA has admitted its existence and variously represents its amount to be either $16,296,097.99 or $16,347,977.99, 4 depending on various options therein which are yet unexplained.

On September 27, 1979, Square/La Fera filed a notice to take the deposition of a certain William Hall, the Bechtel employee responsible for the preparation of the Bechtel estimate. The district court quashed *71 that notice on the grounds of undue delay and that the Bechtel estimate was merely corroborative of La Fera’s testimony. Square/La Fera then moved this court for leave to depose Hall. While that motion was denied, our order noted that appellants might seek relief from the district court pursuant to Rule 60(b), and, if such relief were there denied, might appeal from that order. Square/La Fera filed such a motion to vacate in the district court on June 13, 1980, claiming that WMATA’s failure to disclose the Bechtel estimate constituted fraud, misrepresentation or misconduct under FRCP 60(b)(3), and that the estimate was newly discovered evidence under FRCP 60(b)(2). The district court denied the motion on the grounds that no evidence had been withheld, that the Bechtel estimate would not dictate a different decision by that court, and that, assuming the existence of the estimate in the amount of $13 million, it was merely cumulative of other evidence. The propriety of that decision is now before us on the appeal of Square/La Fera.

A motion under Rule 60(b) is addressed to the sound discretion of the district court and will not be disturbed on appeal save for a showing of abuse. Central Operating Co. v. Utility Workers of America, 491 F.2d 245, 252 (4th Cir. 1974); Consolidated Masonry & Fireproofing v. Wagman Construction Corp., 383 F.2d 249, 251 (4th Cir. 1967). As a threshold matter, the movant must demonstrate the existence of a meritorious claim or defense. Compton v. Alton Steamship Co., 608 F.2d 96, 102 (4th Cir. 1979); Universal Film Exchanges, Inc. v. Lust,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank Morgan v. J. Tincher
90 F.4th 172 (Fourth Circuit, 2024)
W. Scott Davis v. Heckard
S.D. West Virginia, 2023
Welch v. Sam's East, Inc.
W.D. Virginia, 2023
Clinton v. Wolfe
N.D. West Virginia, 2023
Jackson v. Hall
D. South Carolina, 2023
McCray v. Lieber C.I.
D. South Carolina, 2023
Reynolds v. United States Government
E.D. North Carolina, 2023
TEASLEY v. STEIN
M.D. North Carolina, 2022
Ghee v. Walmart Stores East LP
E.D. North Carolina, 2022
Schauber
D. Maryland, 2022
Gray v. Warden of JCI
D. Maryland, 2021
Ervin v. Corizon Health
D. Maryland, 2021
Morgan v. Logan County Commission
S.D. West Virginia, 2021
Bowen v. Adidas America Inc
D. South Carolina, 2021

Cite This Page — Counsel Stack

Bluebook (online)
657 F.2d 68, 29 Cont. Cas. Fed. 81,782, 32 Fed. R. Serv. 2d 765, 1981 U.S. App. LEXIS 18424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/square-construction-company-and-la-fera-contracting-company-v-washington-ca4-1981.