Alvin H. Leal, Trading as Plains Construction Company, and Mercantile National Bank at Dallas, a Corporation v. United States

276 F.2d 378, 149 Ct. Cl. 451, 1960 U.S. Ct. Cl. LEXIS 86
CourtUnited States Court of Claims
DecidedApril 6, 1960
Docket199-53
StatusPublished
Cited by34 cases

This text of 276 F.2d 378 (Alvin H. Leal, Trading as Plains Construction Company, and Mercantile National Bank at Dallas, a Corporation v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alvin H. Leal, Trading as Plains Construction Company, and Mercantile National Bank at Dallas, a Corporation v. United States, 276 F.2d 378, 149 Ct. Cl. 451, 1960 U.S. Ct. Cl. LEXIS 86 (cc 1960).

Opinion

LARAMORE, Judge.

The plaintiffs claim that the contractor Leal (hereinafter referred to as plaintiff), in performing a contract with the Corps of Engineers of the War Department, encountered changed conditions within the scope of Article 4 of the contract, or in the alternative, that the defendant breached the contract by withholding from plaintiff information regarding ground water conditions, which changed conditions or withholding caused Leal to incur extra expense in performing the contract for which he should have been paid.

Plaintiff Mercantile National Bank of Dallas, Texas, is a party to this suit by reason of an assignment by plaintiff Leal on April 26, 1946.

The contract was entered into on April 17, 1946. As part of the construction of the Hulah Dam on the Caney River, a permanent stream in an alluvial valley in northeast Oklahoma, plaintiff was to excavate a temporary diversion channel, and to build part of the embankment. All suitable material from the diversion channel excavation, together with all other suitable material excavated from the spillway area and from designated borrow areas, were to be used in the construction of the rolled-fill embankment of the dam.

The diversion channel was to have its starting point at the Caney River, about 2,100 feet northwest of the dam axis and center line of the spillway, extend eastward intersecting Hickory Creek, and thence southeast to the point where the Caney River intersects the dam axis. It was 2,800 feet long, approximately 30 feet deep, with a bottom width of 40 feet at elevation 690, with one vertical on two horizontal side slopes. The elevation of the bottom grade of the diversion channel was 690, plus or minus, but to be determined in the field by the contracting officer. This elevation was fixed at 690 on the upstream end, decreasing to 688 at the downstream end to correspond with the elevation of the channel of the Caney River between these two points. The grade was established and the slopes staked out by the defendant in April 1946.

Plaintiff’s bid of $699,917.00 was the lowest of the eleven bids submitted on the contract. The Government’s estimate for the work involved was $769,767.50.

All of the work under the contract was completed on time, the contract completion date, as extended, being August 16, 1947.

In 1939, the Army Engineers had made subsurface explorations at the dam site by means of core borings, auger borings, test pits, and undisturbed sample borings. The primary purpose of the explorations was to test the strength of the foundation materials for the dam and determine their suitability for the embankment construction.

With the exception of core hole No. 12, which was located at the intersection of the left bank of the Caney River and the axis of the dam (through which point the southeast periphery of the diversion channel was cut), no subsurface explorations were ever performed within the limits of the work area of the diversion channel.

Prior to bidding, plaintiff Leal was furnished with the plans for construction of embankment and excavation for spillway for Hulah Dam, which included drawings of foundation explorations, borings made, and materials recovered. Drawing C104-4 is a profile of 35 borings and test pits made across the Caney River valley along the axis of the dam. The downstream end of the diversion channel intersects the left bank of the Caney *380 River at the axis of the dam. Hole number 12 contained a line drawn on its left side at the approximate elevation of 689, and the letters “WT” were written above this line. Ten of the other 34 borings along the-axis of the dam were labeled in a like manner. Although the legend at the bottom of the sheet did not contain an interpretation of the letters “WT,” such letters were placed on the sheet to indicate the existence of a water table.

The work here in question was plaintiff’s first experience with the construction of a diversion channel and the compacting of an earth-filled dam, although plaintiff had previous experience in excavating dirt and compacting it on a fill.

Mr. L. M. Bush, a consulting engineer, prepared the plaintiff’s bid estimate for the work covered by the contract. He made preliminary investigations on the job site on three occasions in March 1946, the last of these occasions with plaintiff Leal. On these occasions, he took a set of the plans and drawings and specifications with him, examined the cores which were kept in the coring shed, looked over the general requirements, observed the river banks, studied the field conditions, and analyzed the plans and layout. Plaintiff Leal and Mr. Bush checked for possible ground water by walking the banks of the Caney River for about three-quarters of a mile in each direction from the axis of the dam. They found no seepage of water into the river from the river banks, and concluded that excavation in the diversion channel would be an entirely dry operation.

Mr. Bush went to the resident engineer’s office on the second trip to the job site, but found he was not in. Neither Bush nor Leal made any further attempt to contact the resident engineer prior to the preparation of plaintiff’s bid. During the period between February 21, 1946, and March 21,1946, ten prospective bidders contacted the resident engineer, George A. McClaskey, and he personally escorted them around the job site. He pointed out the various phases of the job, including work on the embankment and the diversion channel. Several prospective bidders raised the question of ground water, indicating that they had expected to encounter ground water and wet material in the diversion channel.

The water table does not represent the maximum elevation at which wet material might be expected. Immediately above the water table there is a narrow zone of the fine-grain material, which usually ranges from about one to ten feet in thickness, which is kept constantly wet by capillary attraction. This zone is called the capillary fringe. The height of the capillary fringe depends upon the molecular forces of the soil particles. For example, coarse material, like gravel and sand, has a smaller capillary fringe than finer soil, like silt and sandy soil. The log record of explorations in adjacent areas revealed the existence of a fine-grained material, indicating that a capillary fringe up to five feet could be expected above the water table in the area of excavation for the diversion channel.

Prior to making his bid, plaintiff Leal and his estimator, examined the core borings on the job site and determined that the required excavation in the diversion channel would be a silty type of soil, but did not consider its capillary characteristics for absorption of underground water.

The plaintiff encountered water and saturated material at elevation 698, and, by letter dated September 4, 1946, advised the contracting officer that the resident engineer had instructed that the wet material be excavated to elevation 690, and compacted on the embankment as originally planned. Because he'would incur increased costs and be delayed, plaintiff requested that the elevation of the diversion channel be raised above the level of the water or that the wet material be wasted. He also requested reimbursement for increased costs and an extension of time in the event it was found necessary to continue the operation as instructed by the resident engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Hendry Corp. v. Metropolitan Dade County
648 So. 2d 140 (District Court of Appeal of Florida, 1995)
A.S. McGaughan Co. v. United States
37 Cont. Cas. Fed. 76,239 (Court of Claims, 1991)
Maintenance Engineers, Inc. v. United States
36 Cont. Cas. Fed. 75,950 (Court of Claims, 1990)
Al Johnson Construction Co. v. United States
36 Cont. Cas. Fed. 75,850 (Court of Claims, 1990)
Gardner-Zemke Co. v. State
790 P.2d 1010 (New Mexico Supreme Court, 1990)
McCormick Construction Co. v. United States
35 Cont. Cas. Fed. 75,721 (Court of Claims, 1989)
North Slope Technical Ltd. v. United States
34 Cont. Cas. Fed. 75,430 (Court of Claims, 1988)
Weeks Dredging & Contracting, Inc. v. United States
34 Cont. Cas. Fed. 75,356 (Court of Claims, 1987)
Baltimore Contractors, Inc. v. United States
34 Cont. Cas. Fed. 75,267 (Court of Claims, 1987)
Pleasant Excavating Co. v. United States
229 Ct. Cl. 654 (Court of Claims, 1981)
Aerojet-General Corp. v. United States
467 F.2d 1293 (Court of Claims, 1972)
Roscoe-Ajax Construction Co. v. United States
458 F.2d 55 (Court of Claims, 1972)
H. N. Bailey & Associates v. The United States
449 F.2d 376 (Court of Claims, 1971)
L. W. Foster Sportswear Co., Inc. v. The United States
405 F.2d 1285 (Court of Claims, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
276 F.2d 378, 149 Ct. Cl. 451, 1960 U.S. Ct. Cl. LEXIS 86, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alvin-h-leal-trading-as-plains-construction-company-and-mercantile-cc-1960.